“The Employer, the Contractor and the Project Manager act in the spirit of mutual trust and co-operation and so as not to prevent compliance by any of them with the obligations each is to perform under the Contract.”
“Actual Cost is the amount of payments paid to Subcontractors for work which is subcontracted and the cost of the components in the Schedule of Cost Components for work which is not Subcontracted, less in both cases any Disallowed Cost. For the avoidance of doubt, the cost of items or matters referred to in Item 7 (Insurance) of the Schedules of Cost Components is not Actual Cost.” subcontracted and the cost of the components in the Schedule of Cost Components for work which is not Subcontracted, less in both cases any Disallowed Cost. For of the Schedules of Cost Components is not Actual Cost.”
“Disallowed Cost is cost which the Project Manager decides: is attributable to a compensation event under a Subcontract which is not also a compensation event under this Contract; is payable or paid by the Contractor to the Employer pursuant to this Contract; is not justified by the Contractor’s accounts and records; should not or was not required to have been paid to a Subcontractor pursuant to or in accordance with his Subcontract; was incurred only because the Contractor did not:- follow an acceptance or procurement procedure stated in the Works Information; give an early warning which he could or should have given; comply with this Contract; comply with a Subcontractor; or results from paying a Subcontractor more for a compensation event than is include din the quotation or assessment for the compensation event accepted by the Project Manager; and/or the cost of:- correcting Defects after Completion; correcting Defects before Completion caused by the Contractor not complying with the accepted quality plan referred to in the Works Information or in this Contract or not complying with a requirement for how he is to Provide the Works stated in the Works Information; correcting Defects notified to the Contractor by the Project Manager which the Contractor failed previously to notify to the Project Manager; Plant and Materials not used to Provide the Works (after allowing for reasonable wastage); or resources not used to Provide the Works (after allowing for reasonable availability and utilisation) or not taken away from the Working Areas when the Project Manager requests.” is attributable to a compensation event under a Subcontract which is not also a compensation event under this Contract; is payable or paid by the Contractor to the Employer pursuant to this Contract; is not justified by the Contractor’s accounts and records; should not or was not required to have been paid to a Subcontractor pursuant to or in accordance with his Subcontract; was incurred only because the Contractor did not:- follow an acceptance or procurement procedure stated in the Works Information; give an early warning which he could or should have given; comply with this Contract; comply with a Subcontractor; or results from paying a Subcontractor more for a compensation event than is include din the quotation or assessment for the compensation event accepted by the Project Manager; and/or the cost of:- correcting Defects after Completion; correcting Defects before Completion caused by the Contractor not complying with the accepted quality plan referred to in the Works Information or in this Contract or not complying with a requirement for how he is to Provide the Works stated in the Works Information; correcting Defects notified to the Contractor by the Project Manager which the Contractor failed previously to notify to the Project Manager; Plant and Materials not used to Provide the Works (after allowing for reasonable wastage); or resources not used to Provide the Works (after allowing for reasonable availability and utilisation) or not taken away from the Working Areas when the Project Manager requests.”
“50.1 The Project Manager assesses the amount due at each assessment date. The first assessment date is decided by the Project Manager to suit the procedures of the Parties and is not later than the assessment interval after the starting date. Later assessment dates occur:- at the end of each assessment interval [ie 28 days] until Completion of the whole of the works; at Completion of the whole of the works; four weeks after the project Manager issues the Defects Certificate; and after Completion of the whole of the works:- when an amount due is corrected; at the end of each assessment interval for a period of four months after Completion of the whole of the works; and when a payment is made late by the Employer. “50.2 The amount due is the Price for Work Done to Date plus other amounts to be paid to the Contractor less amounts to be paid by or retained from the Contractor. If the amount to be paid to the Contractor is less than the amount to be paid by or retained from the Contractor, the difference is recoverable from the Contractor as a debt. 50.5 In assessing the amount due, the Project Manager considers any application for payment the Contractor has submitted on or before the assessment date. The Project Manager gives the Contractor details of how the amount due has been assessed. 50.6 The Project Manager corrects any wrongly assessed amount due in a later payment certificate.”
“51.1 The Project Manager by the issue of a payment certificate certifies a payment within 2 weeks of the assessment date, which for the purposes of the HGC&R Act is the due date. ... 51.4 If an amount due is corrected in a later certificate either:- by the Project Manager, whether in relation to a mistake which is not due to an assessment based on incorrect accounts and records provided by the Contractor or a compensation event; or following decision of the Adjudicator or the tribunal, interest on the correcting amount is paid. Interest is assessed from the date when the incorrect amount was certified until the date when the correcting amount is certified and is included in the assessment which includes the correcting amount. 51.5 If the Project Manager does not issue a certificate which he should issue, interest is paid on the amount which he should have certified. Interest is assessed from the date by which he should have certified the amount until the date when he certifies the amount and is included in the amount then certified.”
“The Project Manager assesses a compensation event:- if the Contractor has not submitted a required or revised quotation and details of his assessment or more information within the time allowed. if the Project Manager decides that the Contractor has not assessed the compensation event correctly in a quotation and he does not instruct the Contractor to submit a revised quotation; if, when the Contractor submits quotations for a compensation event, he has not submitted a programme which this Contract required him to submit; or if, when the Contractor submits quotations for a compensation event the Project Manager has not accepted the Contractor’s latest programme for one of the reasons stated in this Contract.” at the end of each assessment interval [ie 28 days] until Completion of the whole of the works; at Completion of the whole of the works; four weeks after the project Manager issues the Defects Certificate; and after Completion of the whole of the works:- when an amount due is corrected; at the end of each assessment interval for a period of four months after Completion of the whole of the works; and when a payment is made late by the Employer. Clause 51 provides: “51.1 The Project Manager by the issue of a payment certificate certifies a payment within 2 weeks of the assessment date, which for the purposes of the HGC&R Act is the due date. ... 51.4 If an amount due is corrected in a later certificate either:- by the Project Manager, whether in relation to a mistake which is not due to an assessment based on incorrect accounts and records provided by the Contractor or a compensation event; or following decision of the Adjudicator or the tribunal, interest on the correcting amount is paid. Interest is assessed from the date when the incorrect amount was certified until the date when the correcting amount is certified and is included in the assessment which includes the correcting amount. 51.5 If the Project Manager does not issue a certificate which he should issue, interest is paid on the amount which he should have certified. Interest is assessed from the date by which he should have certified the amount until the date when he certifies the amount and is included in the amount then certified.” by the Project Manager, whether in relation to a mistake which is not due to an assessment based on incorrect accounts and records provided by the Contractor or a compensation event; or following decision of the Adjudicator or the tribunal, interest on the correcting amount is paid. Interest is assessed from the date when the incorrect amount was certified until the date when the correcting amount is certified and is included in the assessment which includes the correcting amount. should issue, interest is paid on the amount which he should have certified. Interest is assessed from the date by which he should have certified the amount until the date when he certifies the amount and is included in the amount then certified.”
“The Project Manager assesses a compensation event:- if the Contractor has not submitted a required or revised quotation and details of his assessment or more information within the time allowed. if the Project Manager decides that the Contractor has not assessed the compensation event correctly in a quotation and he does not instruct the Contractor to submit a revised quotation; if, when the Contractor submits quotations for a compensation event, he has not submitted a programme which this Contract required him to submit; or if, when the Contractor submits quotations for a compensation event the Project Manager has not accepted the Contractor’s latest programme for one of the reasons stated in this Contract.” if the Contractor has not submitted a required or revised quotation and details of his assessment or more information within the time allowed. if the Project Manager decides that the Contractor has not assessed the compensation event correctly in a quotation and he does not instruct the Contractor to submit a revised quotation; if, when the Contractor submits quotations for a compensation event, he has not submitted a programme which this Contract required him to submit; or if, when the Contractor submits quotations for a compensation event the Project Manager has not accepted the Contractor’s latest programme for one of the reasons stated in this Contract.”
“a. Bechtel will forthwith desist from instructing, persuading or otherwise encouraging any of its employees, ,servants or agents and/or any other person employed by the RLE, from seeking to operate the assessment and certification functions of the project manager under the Contract otherwise than impartially and in good faith. b. Bechtel will forthwith issue written instructions to all its employees, servants or agents who were present at the meeting on15 April 2005 , instructing them to disregard the advice, encouragement or instructions given by Mr Fady Bassily at that meeting, in so far as such advice or instructions required or requested that they seek to operate the assessment and certification functions of the project manager under the Contract other than impartially and in good faith. c. Bechtel will deliver up to us, on behalf of our clients, by no later than 5pm on Friday,14 May 2005 , a list of the names and job titles of the persons attending the meeting held on15 April 2005 . d. Bechtel will (a) forthwith make a reasonable inquiry as to whether any other instructions, requests or advice have been given to its employees, servants or agents in order to persuade them to seek to operate the assessment and certification functions of the project manager under the Contract otherwise than impartially and in good faith; (b) as soon as practicable thereafter, specifically and in writing will countermand any such instructions, requests or advice in respect of any employee, servant or agent so instructed and (c) within 14 days of the date of this letter will deliver up to ourselves a list of the names of the persons to whom such instructions, requests or advice had been given and details of when these were countermanded.”
“In this regard, RLE on its own behalf and on behalf of its Members (particular Bechtel as singled out by you) and Mr Bassily (the Project Director) confirm to CORBER that at all times RLE has sought to carry out and will continue to carry out its Project Management functions in accordance with its obligations. Furthermore at no time has RLE, its members or Mr Bassily intended to encourage any RLE member employee to act otherwise than in accordance with their obligations. RLE, Bechtel and Mr Bassily will continue to comply with their obligations.”
“Mr Bassily, for whose torts Bechtel is liable, has sought to encourage Bechtel’s employees to operate the assessment and certification provisions of the Contract partially and in bad faith. In this way he has encouraged a breach of contract by URN, intending that there should be such a breach or being reckless as to whether such a breach was brought about. On the morning of15 April 2005 at the Shaw Theatre, Novotel Hotel, Euston Road Mr Bassily addressed a meeting of the employees of Bechtel, who were engaged in project management functions under the CTRL Section 2 Contracts. He told them that Bechtel was at risk of losing money on the CTRL Section 2 Contracts and that this was not acceptable. He said that this was ‘a Bechtel issue, not an RLE issue’, by which he implied that the employees should act according to Bechtel’s interests, rather than in accordance with the responsibilities of RLE. ... Bechtel exercising its influence on RLE through its own employees, has sought to operate the assessment and certification functions of the project manager in a partial manner and in bad faith. In so doing it has been motivated by a desire to reduce the risk to Bechtel of cost overruns on the CTRL Section 2 Contracts and has disregarded the proper nature of the project manager’s function and responsibilities. In this way it has encouraged a breach of contract by URN, intending that there should be such a breach or being reckless as to whether such a breach was brought about. The operation of this influence first became apparent to CORBER on8 April 2005 when, in respect of payment Certificate 48, RLE disallowed an unusually large element of costs, without adequate justification and in many cases contrary to its previous representations. Thus, in relation to various subcontracts the sum of disallowed costs exceeds the sum sought. ...”
“IT IS ORDERED THAT: (1) the First and Second Defendants do forthwith desist from instructing, persuading or otherwise encouraging any employee, servant or agent of the First Defendant and/or any other person employed by Rail Link Engineering (‘RLE’) from seeking to operate the assessment and certification functions of the project manager under the Contract dated26 April 2202 (as identified in the Particulars of Claim) otherwise than impartially and in good faith. (2) The First Defendant do forthwith issue written instructions to all its employees, servants or agents who were present at the meeting dated15 April 2005 (identified in paragraph 11a of the Particulars of Claim) instructing them to disregard the advice, encouragement or instructions given by the Second Defendant at that meeting, in so far as such advice or instructions required or requested that they seek to operate the assessment and certification functions of the project manager under the Contract otherwise than impartially and in good faith. (3) The First Defendant do deliver up to solicitors acting for the Claimants, within 14 days of this Order, a list of the names and job titles of the persons attending the meeting held on15 April 2005 . (4) The First Defendant do: (a) forthwith to make reasonable inquiry as to whether any other instructions, requests or advice have been given to its employees, servants or agents in order to persuade them to seek to operate the assessment and certification functions of the project manager under the Contract otherwise than impartially and in good faith; (b) as soon as practicable thereafter, specifically and in writing to countermand any such instructions, requests or advice in respect of any employee, servant or agent so instructed and (c) within 14 days of this order to deliver up to solicitors acting for the Claimants a list of the names of the persons to whom such instructions, request or advice had been given and details of when these were countermanded.”
“Mr Bassily then turned to Section 2 of the CTRL works. Among other things, he indicated that it was important for RLE to carry out its project management role to achieve a cost effective outcome for the project. Mr Bassily told us that there was a significant gap between the Target Cost and the projected Outturn Cost and it was up to all of us to work to narrow that gap.”
“It has often been said, I think rightly, that the architect has two different types of function to perform. In many matters he is bound to act on his client’s instructions, whether he agrees with them or not; but in many other maters requiring professional skill he must form and act on his own opinion. Many matters may arise in the course of the execution of a building contract where a decision has to be made which will affect the amount of money which the contractor gets. Under the R.I.B.A contract many such decisions have to be made by the architect and the parties agree to accept his decisions. For example, he decides whether the contractor should be reimbursed for loss under clause 11 (variation), clause 24 (disturbance) or clause 34 (antiquities), whether he should be allowed extra time (clause 23); or when work ought reasonably to have been completed (clause 22). And, perhaps most important, he has to decide whether work is defective. These decisions will be reflected in the amounts contained in certificates issues by the architect. The building owner and the contractor make their contract on the understanding that in all such matters the architect will act in a fair and unbiased manner and it must therefore be implicit in the owner’s contract with the architect that he shall not only exercise due care and skill but also reach such decisions fairly, holding the balance between his client and the contractor.”
“An examination of the R.I.B.A. contract shows how manifold are the duties of the architect. Being employed by and paid by the owner he unquestionably has in diverse ways to look after the interests of the owner. In doing so he must be fair and he must be honest. He is not employed by the owner to be unfair to the contractor.”
“The rights and remedies of the Contractor as provided for in this Contract are exhaustive of its rights and remedies against each of the Employer and the Project Manager arising out of, under or in connection with the project or the works, whether such rights and remedies arise in respect or in consequences of a breach of contract or of statutory duty or a tortuous or negligent act or omission which gives rise to a right or remedy at common law or in equity. ...”
“When assessing sums payable to CORBER under contract C105, is it RLE’s duty (a) to act impartially as between employer and contractor or (b) to act in the interests of the employer?”