"(1) A party to a construction contract may not withhold payment after the final date for payment of a sum due under the contract unless he has given an effective notice of intention to withhold payment. The notice mentioned in section 110(2) may suffice as a notice of intention to withhold payment if it complies with the requirements of this section. (2) To be effective such a notice must specify - (a) the amount proposed to be withheld and the ground for withholding payment, or (b) if there is more than one ground, each ground and the amount attributable to it, and must be given not later than the prescribed period before the final date for payment. (3) The parties are free to agree what that prescribed period is to be. In the absence of such agreement, the period shall be that provided by the Scheme for Construction Contracts … "
"22. INVOICING TERMS Three copies of the invoice showing all the Contract references must be sent along with all the documents proving that the obligations of the Contractor have been performed. An invoice can only refer to one sole Contract and one sole term of payment. 23.2 CONDITIONS OF PAYMENT It is a condition precedent to any payments being made to the Contractor under the Contract that the Contractor shall have provided to CNIM the following documentation … (d) Properly prepared invoice(s) as required in Clause 22 … Payment by CNIM shall be effected by bank transfer sixty (60) Days after the end of the month in which invoice is received; any bank charges in respect of the Contractor’s bank shall be borne by the Contractor … 25.1 LIQUIDATED DAMAGES FOR DELAY … Liquidated damages shall apply and be payable without prior notice from CNIM’s Representative. CNIM may retain the amount of liquidated damages due and set off these against any payment due to the Contractor. 31.1 SETTLEMENT OF DISPUTES If a dispute or difference arises under or out of the Contract either Party may at any time give notice of his intention to refer such dispute or difference to adjudication under this Clause and may within seven days thereafter refer the same to the decision of the adjudicator (“the Adjudicator”) … 31.6 The Adjudicator’s decision is binding upon the Parties until finally determined by legal proceedings or by agreement. … 31.8 If either party does not comply with the decision of the Adjudicator the other party shall be entitled to take proceedings in the Courts to secure such compliance pending any final determination of the referred dispute or difference pursuant to Sub-Clause … … 31.13 The Adjudicator shall decide the matters in dispute. He may take into account any other matters which the Parties to the dispute agree should be within the scope of the adjudication connected with the dispute. In particular, he may: (a) decide that any of the Parties to the dispute is liable to make a payment under the Contract (whether in sterling or some other currency) and subject to section 111(h) of the Housing Grants, Construction and Regeneration Action 1996, when that payment is due and the final date for payment.
"When Parliament refers in section 105(2) to “a site where the primary activity is …” the reference must be to a place broader than a generator surrounded by a security fence. To make any sense of the Act, one has to look to the nature of the whole site and ask what is the primary purpose of the whole site? Is the primary purpose power generation, or, in this case, printing?"
"12. My understanding is that ‘Integra’ is a reference to ‘Project Integra’, which is the name given to Hampshire County Council’s integrated waste management strategy. The strategy is being implemented by Hampshire Waste Services Limited, a subsidiary of Onyx UK, with whom CNIM contracted to provide the Chineham incinerator plant … 13. This waste management strategy includes the provision of 3 incinerator plants, … located at Chineham (which was the subject of the adjudications between CEL and CNIM), Portsmouth and Marchwood. 14. At KHC1 pages 2-4 I attach copies of pages from the Project Integra website which summarises the aims and objectives of the project."
".. BACKGROUND At the end of the 1980s it became clear that Hampshire was facing a waste disposal crisis as landfill sites were rapidly filling up, incinerators built in the 1970s were not going to meet new EU emission regulations, and waste levels were continuing to increase … Project Integra was formed on the basis of the following seven point action plan: 1. Action on waste minimisation 2. Action on composting 3. Action on recycling 4. Support for anaerobic digestion 5. Use of recovery technologies, including incineration 6. 3 to 5 waste processing facilities (not exceeding 200,000 tonnes per annum) 7. Residual waste to landfill. RESULTS To date Project Integra has achieved a collective recycling rate of over 25% (2000/2001), with over 90% of Hampshire’s households having access to a kerbside collection of recyclables. Developments have been made in terms of infrastructure with the provision of • 2 Materials Recovery Facilities (1 operating in Portsmouth, another has planning permission – to be built in Alton in 2003) • 3 centralised composting sites • 9 transfer stations • A network of 26 Household Waste Recycling Centres • 3 Energy Recovery Incinerators – not operating at the moment, but to be completed within the next few years …"
"The management and staff of Integra North ERF are among the most highly qualified and experienced in the sector. Household waste is sent to an energy recovery facility where it is tipped into a bunker. A crane grabs the waste and places it into the feed hopper. It then drops down a feed chute onto the grate. The action of the grate turns the waste to allow it to burn fully. The burnt out ash passes through the ash discharger onto an ash handling system, which extracts metal for recycling. The remaining ash is sent for recycling or disposal. Hot gasses produced in the combustion process pass through a water tubed boiler where they are cooled. The heated water becomes steam. A turbo-generator uses the steam to produce electricity for export to the National Grid. The gasses from the boiler go through an extensive flue gas cleaning process. This consists of a gas scrubber where lime milk is injected to neutralise acid gasses: then activated carbon is added to remove other pollutants: and finally a bag filter where any remaining particulars are filtered out. The resulting material known as Air Pollution Control Residue (APCR) is sent for disposal at a licensed site. The cleaned gasses are finally released to the atmosphere through the chimney. … How the power is generated The output steam from the heat recovery boiler is fed into the steam turbine. It enters the turbine at high pressure (45 BAR) and leaves the turbine at partial vacuum. After the turbine the condenser turns the steam back into water, which is recycled within the facility. The output shaft of the turbine is controlled to the generator via a reduction gearbox. The generator is water cooled and specifically designed for minimal maintenance. The electricity flows through underground cable at 11,000 volts to Basingstoke substation and then to the National Grid. Integra North provides 8MW of electricity to the National Grid, enough to power more than 8,000 local homes. Technical details of the plant • Refuse throughout – 90,000 tonnes per annum in 12 tonnes per hour refuse burning steam • Storage capacity – four days full plant capacity • Number of tipping bays – 5 • Steam output – 37.5 tonnes of steam per hour at 400oC and 45 BAR • Flue gas treatment – CNIM semi-dry line scrubber followed by high performance bag filters, discharging into a 65 metre high chimney • Energy produced – maximum generating capacity 8MW …"
"CNIM is to design, build and deliver a Waste Incineration Plant"
"Integra North Energy Recovery Facility Chineham Incinerator Site Whitemarsh Lane Hampshire … "
"ENERGY RECOVERY INCINERATION The local council refuse collection vehicles pick up household waste that has not been recycled from outside people’s homes. The waste is taken to an Energy Recovery Incinerator. The refuse collection vehicles tip the waste into a storage bunker. From here it is fed into the furnace of the incinerator. As the waste is burnt at a very high temperature, a lot of heat and gases are given off. The gases are cleaned using filters before being discharged into the atmosphere. The heat is used to turn water in pipes surrounding the furnace into steam. The steam is used to drive generators which produce electricity. This is passed into the National Grid through cables. This whole process is known as Energy Recovery Incineration."
"(1) Every construction contract shall (a) provide an adequate mechanism for determining what payments become due under the contract, and when, and (b) provide for a final date for payment in relation to any sum which becomes due. The parties are free to agree how long the period is to be between the date on which a sum becomes due and the final date for payment … (3) If or to the extent that a contract does not contain such provision as is mentioned in subsection (1) … the relevant provisions of the Scheme for Construction Contracts apply."
"Final date for payment 8.(1) Where the parties to a construction contract fail to provide a final date for payment in relation to any sum which becomes due under a construction contract, the provisions of this paragraph shall apply. (2) The final date for the making of any payment of a kind mentioned in paragraphs 2, 5, 6 or 7, shall be 17 days from the date that payment becomes due." [The kinds of payments mentioned in paragraphs 2, 5, 6 or 7 are instalment or stage payments, final payments, payment of the contract price, and any “other” payments due under a construction contract.] "