"When we moved into number 8 it was in good decorative condition with no visible signs of cracking or structural damage. When we moved into the property, excavation work had commenced next door at number 6. Over the next two months, excavation work continued and piling works commenced. The piling works caused severe disruption to my family and me. I spent much of my time at home with the children and had to endure the daily disruption caused by the piling works. The piling works themselves involved prolonged periods of incessant banging and thudding. These caused severe vibrations making the house literally shake. At one stage the vibrations were so severe they caused picture frames to fall from the walls and caused the kitchen window to crack. I was extremely worried about the structural safety of the property at this time, as there was audible groaning and cracking noises coming from the walls of the house. Approximately two weeks after the piling works commenced at number 6 cracks began to appear in the walls of number 8 and gradually became markedly more severe. What started as very minor cracks quickly increased in size with new cracks also developing throughout the house. I recall that some of the worst affected rooms were the upstairs bedrooms, nearest to the number 6 side of the building. This was especially concerning for me as these were my children's rooms and I was concerned that piling works would cause the external wall to collapse. The disruption continued and the damage to number 8 continued to worsen with the cracks in the walls becoming progressively worse and new cracks beginning to emerge. By May the piling works next door had finished and the disturbance caused by the works lessened. However, the cracks in the property continued to become worse and in fact the cracks in the bedrooms nearest to number 6 became so severe that I moved my children into different rooms, which meant one of my children having to share a bedroom with me."
"The property internally is in good decorative condition. There was no evidence of structural movement at ground floor level."
"There is cause for concern as to the quality of the piles below the depth of casing. I note that the ingress of grout beyond the bored perimeter restricted the use of casing to a full design depth."
"I have two major concerns with the work carried out to date. Both relate to the vast variation in the height above ground of the piles. There would be approximately 700mm difference in the heights. My understanding is that all piles will have to be trimmed to within 30mm or 40mm of each other. Bearing in mind that the site is almost level, I can see no reason for the variations."
"Now we have exposed most of the piling to the final excavation depth, I have had to time to reflect on the overall quality of the job." 33. "
"Case piles were being installed using a 12 tonne machine working on a platform of soft sand on top of a platform of a 6m high sand dune into completely saturated non-cohesive ground."