"Further, and in any event, the first and/or second claimant has wholly failed to mitigate its loss if it has built a new superstore in consequence of the failure of the Keller works when it could and should reasonably have undertaken the further grouting works at a fraction of the cost."
"First and/or second claimant cannot recover the cost of building a new store for the following reasons: "21.2.1. It is unreasonable to build a new store in circumstances where the remedial scheme that had been started could have been completed at a fraction of the cost."
"The best particulars that can be provided at this stage is the figure provided by the defendants' loss adjuster at£900,000 , which includes the cost of remedial works including contingencies, the cost of making good and professional fees. Details of the costs that would have been likely to be incurred and the basis of those costs will follow."
"Making good during and immediately after Soilfrac works 2000 base line:£182,000 . "
"The amount allocated for professional fees represents 29 per cent of construction cost allowances. Previous fee costs represent about 21 per cent. For refurbishment works I would estimate 20 per cent as an appropriate allowance for professional fees."
"Yet further or in the further alternative, the proper measure of the claimants' loss in the circumstances as described above is by reference to the costs of completing Keller's works and not by reference to the cost of a new modern and larger store."
"The estimated cost to complete the Soilfrac works is set out at amended response 18 to the defendants' request for further information. Excluding inflationary costs the maximum cost of completion of these works would be: two visits at£75,000 each,£150,000 ; making good maximum,£382,000 ; professional fees at 20 per cent,£106,400 . Total£538,400 ."
"By reason of the defendants' breach of the civil and structural engineer's agreement the claimants have suffered loss and damage."
"Costs incurred relating to the planned extension to the superstore which was abandoned due to the remedial works of£100,000 ."
"Please set out the reasons and explain how it is said that the defendant is responsible for the costs that it is alleged to have been incurred in relation to the planned extension of the existing superstore."
"The costs were incurred in the normal course of the claimants' business but were ultimately wasted when the extension plan was abandoned. The ongoing settlement suffered by the store was caused by the defendants' breaches of contract as pleaded. The ongoing settlement and the uncertainty that this generated as to the future was a material cause of the decision to abandon the plans and hence the wasted costs. The loss claimed was caused by the defendants' breaches."
"Furthermore, it is apparent that the first and/or second claimant planned to extend the superstore and it is anticipated therefore that the new store has been built to allow the new store to operate, at the very least, as if it had the same facilities as the old store, together with the planned extension. In this regard, the defendant is entitled to a credit to represent: "22.8.1. The sum that it would have cost the claimant to build the extension and/or. "22.8.2. The extra profit generated over the life of the new store by reason of the new facilities in lieu of the extension."