“Q. Does it follow from the comparison of items 3 and 11 – and I am not putting a positive case to you, I am merely enquiring. Does it follow from a comparison of those two items that you are satisfied that your reduction took sufficient account of the eight inch/four inch point? A. I believe so, yes. Q. Very well”
“Q. Could you briefly explain to the learned judge how, as a practising engineer, you regard the distinction between change and detailing? A.. Indeed, I will do my best to summarise without reading word for word. The approach I took, I felt it was important that my view on the definition of detail be put across, because I think there is reference to it at various occasions in this joint statement. Detailing is a very familiar concept to engineers. We produce drawings broadly in two classifications, the first being classification of general arrangements and then the second group being detailed drawings. The general arrangements are those which show the overall layout, plans, elevation sections, the arrangements for the buildings or the construction as a whole. Because there is insufficient space on these drawings to show the full extent of what is required to construct the project, they are supplemented and complemented by what we call detailed drawings. The detailed drawings are where one goes to look for the fine detail that is too specific to be included in the general arrangement. I have listed some examples there with the bullet points two-thirds of the way down: the hidden steel reinforcement within a reinforced concrete base, for example, the window and door details, roof lashings, weather proving, et cetera, et cetera. So, in each case there, the detailed drawing is expanding upon what has already been shown in general terms in the general arrangement. It is providing the full and detailed particulars for that in order to allow construction and the proper ordering of parts. So, my view on what constitutes detail are detailed elements which do not go outside the scope of the general arrangement. The reinforcement must fit inside the concrete elements which are dimensioned on the general arrangement. The detailed door furniture has to fit in with the general indication of the size of the door shown on the general arrangement. Detailed dimensions of floor ducts and channels have to be consistent with how they are shown on the general arrangement. So I take it – at least my interpretation is that detail refines the general arrangements but it does not change or expand any of the information shown on the general arrangements.”
“It is agreed that the experts will be bound by the results of a 3-d analysis to be carried out and jointly agreed. The analysis will examine in greater detail the effect of the change in stanchion layout in the Warehouse, in compliance with the design criteria set out in the Employer’s Requirements, Contractor’s Proposals and Contractors Response. Analysis to be run for the relevant parts of the building (at least to include for an area at tender comprising a 2 bay adjacent to a 3 bay stanchion spacing as well as the as built comparison between two adjacent 3 bay spacings. It is agreed that the outcome of this exercise will be to establish a prudent and economic design in compliance with contract requirements at the time of the offer and a prudent and economic design to comply with the final requirements. It is agreed that the experts will be bound by the result and that the entitlement to payment shall be assessed as the difference between the two designs.”
“I make the point in my report that that is all very well, but that is with the benefit of the 3D sophisticated analysis which we had to use to prove the point that there was some change, some measurable change that required additional steelwork in the warehouse. That point had been proved by what we did , hence the additional 64 tonnes now conceded by Mr Walsh. But we had tools and time that was not available to the designers of the warehouse at the time from the point at which the change was instructed. Time was also of the essence in reaching a conclusion to the process of pre-ordering the steel. So in my view, if the two experts with the 3D analysis and unlimited time could come within 2 per cent of each others figure, still not the exact figure but within 2 per cent of the figures, then it seemed to me to be reasonable to allow a certain further leeway to a designer under the pressue of time, and also with only a 2d analysis available to him, which would be normal practice in the industry, and I identified a figure of 5 per cent. Q. We are talking about Mr Lupton doing it at the time, back in 1997 now? A. Correct, yes. There is no scientific basis to my figure of 5 per cent but it seems to be a reasonable figure in relation to the 2 per cent tolerance that Mr Walsh and I reached with a more sophisticated – through a more sophisticated route. So, with my reasoning I would therefore be adding the leeway of 5 per cent to our refined and perfect figure of 654 tonnes to come up with what would have been a reasonable weight of steelwork to have been designed in response to the change instructed by the client at the time. Q. Does that then take you very close to the as-built figure of – A. It is as it happens very, very close, because 654 tonnes plus 5 per cent is quite close to the as-built tonnage.”
“The valuation of additional or substituted work shall be consistent with the values of work of a similar nature set out in the Sub Contracts making due allowance for any change in the conditions under which the work is carried out and/or any significant change in the quantity of the work set out. Where there is no work of a similar character set out in the Sub Contracts a fair valuation shall be made.”
“In my opinion support steel for process plant is quite different from structural steel. The section sizes and length tend to be smaller; there is far less repetitive work and site erection costs can be disproportionately high. Moreover, from my examination of the invoices from suppliers it appears that KCBL were ordering stock steel which is always more expensive.”
“The contractor shall provide a compressed air plant to serve the requirements of the productions areas having a system operating pressure of 7 Barr. The compressed air plant shall consist of: 3 Oil injected, rotary screw, air cool compressors each rated at 500 c.f.n. Two duty and one standby. 1 Air receiver sized for the full duty of 1,500 c.f.n. with automatic drain valve piped to drain. 3 Dessicant air driers each sized at 500 c.f.n. 3 Filters each size for 500 c.f.n. to provide content less than 3 mg/m³”
“Q. When Mr Taylor says at his paragraph (i) on 290 ‘the price’ he must mean the price to Baileys or the cost to Baileys, must he not? He cannot be referring to the price set out in the bills because that is clearly a different figure? A He certainly was not talking about the bills because it was not the rate in the bills.”
“(a) The valuation of additional or substituted work shall be consistent with values of work of a similar character set out in the Sub-Contracts making due allowance of any change in the conditions under which the work is carried out and or any significant change in the quantity of the work set out. Where there is no work of a similar character set out in the Sub-Contracts the fair valuation shall be made. (b) The valuation of the omission of work shall be in accordance with the values in the Sub-Contracts or if no Sub-Contract had been concluded the values in the Guaranteed Maximum Price Analysis.”
“Main switch gear for small power to be in switch room KCL to advise on size and preferred location.”
“In my judgment liability is established for the costs of the additional switch room and switch gear.”
“Change in requirement Mechanical and Electrical Mechanical and Electrical Conformation (sic) the ………requirements to accelerate the works as Egger letter28th November 1997 as last paragraph letter2nd December 1997 .”
“In conclusion we confirm your verbal instruction on Friday28th November 1997 to accelerate the works in line with the proposals contained within our letter 1920 dated26th November 1997 and afford all costs incurred in do so for reimbursement by yourselves.”
“The actual efficiency factor – he actually, I think in his survey came to 26% and you reach that after six weeks of continuous overtime …”
“Landscaping: The Contractor is to develop the landscape brief as shown on the drawings, however he is not responsible for providing the works. Planting/Landscaping works to the south part of the site between the car parks and public road. Mounds and bunds are to be prepared for tree planting by others Tree planting will be carried out by the Employer direct. The contractor shall carry out all preparatory work ready for tree planting.”
“SCL has provided the Q.S. with a copy of the accounts submitted by KCBL for this work. This account has been agreed and paid in the sum claimed.”
“We have instigated our own source of investigation regime onsite and enclose some of the CBR values gained to date along the line of the Western approach road which clearly identified the problem we are encountering. We are currently keeping records of all additional works required to overcome the problem areas. Details will be forwarded in due course.”
“The claim also fails to take into account any additional costs which were incurred as a result of the Claimant’s and/or its sub-contractor’s own defaults. In particular the defendant will say that it fails to take into account additional costs incurred in managing problems that which were experienced on site in relation to Barr, the sub-contractor employed to carry out the Excavations and Foundations package. It is the Defendant’s case that delays by Barr and a lack of resourcing on their part caused delays to the project and resulted in additional staff costs being incurred by the Claimant. In support of this assertion the Defendant will rely upon the entirety of Barr’s conduct when on site and in particular the minutes of the meeting between the Claimant and Barr dated8th July 1997 , paragraphs 4.2 and 4.3.”
“(6) If compliance with any instruction affecting a Change increases or decreases the cost of management or design of Works a fair and reasonable adjustment may be made to the Design and Management and Common User Fee.”
“In my opinion the only sensible mechanism open to any contractor in this situation is to calculate the value of the fee payable proportionate to the value of additional work.”
“There remains to be considered the question whether the Respondents are entitled to recover their financing charges only on the basis of simple interest, or whether they are entitled to assess their claim on the basis of compound interest, calculated at quarterly rests, as they have done. Now here, it seems to me, we must adopt a realistic approach. We must bear in mind, moreover, that what we are hear considering is debt due under a contract; this is not a claim to interest as such, as for example a claim to interest under the Law Reform Act, but a claim in respect of loss or expense in which a contractor has been involved by reason of certain specific events. The Respondent, like (I imagine) most building contractors, operated over the relevant period on the basis of a substantial overdraft at their bank, and they claim in respect of financing charges consists of a claim in respect of interest paid by them to the bank on the relevant amount during that period. It is notorious that banks do not themselves, when calculating interest on overdrafts, operate on the basis of periodic rest; on the basis of the principle stated by the Court of Appeal in Minter’s case, which we here have to apply, I for my part can see no reason why that fact should not be taken into account when calculating the Respondent’s claim for loss or expense in the present case …”
“The crane base was ready to accept the cast in by 2nd December of 1997. However, remedial were required to the crane base reinforcement. These remedial were complete by 20th January 1`998 when Barr comment that they were awaiting a price from a scaffolding contractor for these works. On 27th January of 1998 the shuttering works had thus started. On3rd February 1998 the shuttering was still continuing. The above sequence would indicate that any delay to the completion of the crane foundation was as a result of Barr’s remedial works, which then had a knock on effect which required a specialist scaffolding sub-contractor prior to completing the shuttering”
“The shuttering work to which the PCL report refers has nothing to do with reinforcement remedials.”
“I consider that event E8, ‘the Liebherr crane foundation had no effect upon the completion of Barr’s work as in zone E’ is misinterpreted in PCL’s investigation; ’10.5.12 no delay to completion of Barr’s work in the zone’. It is clear from the facts that Barr operations were extended through until mid-February 1998 as a result of the late supply of built-in components by Egger.”
“It is culpable if I give effect to it or do not give effect and it and vice versa”
“I fully accept that the Courts are not normally concerned with what the Plaintiff does with his damages. But it does not follow that his intention is not relevant to reasonableness, at least in those cases where the Plaintiff does not intend to reinstate …”
“The Respondent accepts that the genuineness of the parties indicated pre-dispositions can be a factor which the Court must consider when deciding between the alternative measures of damages where a plaintiff is contending for a high as opposed to a low cost measure of damages, the Court must decide whether in the circumstances of the particular case, such a high costs measure is reasonable. One of the factors which may be relevant is the genuineness of the Plaintiffs desire to pursue the course which involves the higher cost….. I can only say that I find myself in complete agreement with that approach.”
“However, on a provisional basis, provided the dosage of fibres were as their manufacturers normally recommend for such work, it is my opinion that a 225mm steel fibre reinforced concrete slab can be just as good as and in some respects better than, a 300mm thick conventionally reinforced concrete slab. 4.4.2 the reduction of the combined capping and sub-lace bares to 300mm only of sub-base is also acceptable on technical grounds provided adequate ground-baring capacity and stillness has been achieved in practice.”
“Q. If I were to suggest that the cable identification provisions of the specification had been complied with, then the exercises you describe with locating and identifying the cables would have been considerably easier, would it not? A. Possible, yes. Q. I think, as you have already confirmed, the lion’s share of the labour costs are referable to that exercise rather than the actual re-routing exercise? A. Yes.” 486. Mr Davies submits there is no basis upon which the specification laying obligations upon SCL should affect Egger. Mr Garrett was shown the passage in the Institute of Electrical Engineer’s Wiring Regulations 16th Edition at page 540, paragraph 414-01-02, which provides: “…..as far as reasonably practical, wiring should be so arranged or marked that it can be identified for inspection, testing, repair or alteration of installation”. 487. Mr Garrett accepted that the cable should be marked. He confirmed that it conformed with good practice as he knew it and said that some of the cables that he was tracing and replacing and that he could not identify, were only marked at the extremities. Mr Garrett’s lengthy and extensive exercise underlined the obvious failure of Egger to adequately identify the cabling in these ducts. This cabling is for sophisticated process plant. It is not general service cabling. It would be absurd to ignore the standard prescribed in Eggers own GMP contract specification, and the IEE Wiring Regulations and the difficulties now encountered by Mr Garrett because of the marking regime installed and not to draw the inference that it would have been both practical and constituted good practice for Egger to have complied with their own specification in the original installation. They have not proved that their original work conformed with good practice. They have through Mr Garrett demonstrated that the absence of practicable identification has greatly added to the cost of labour. 488. Mr Garrett’s evidence further indicates that the sub-contractor labour records leave a lot to be desired in terms of validation and signing. It is evident that the sub-contractors Livingston’s were employed on site and doing other electrical sub-contract works not the subject of this claim. How their labour costs were allocated to the various different works in this case, was important to establish. I am told that some helpful records were stored on a computer, without any copying back-up. They have been lost. That makes proof more difficult. In the absence of other reliable evidence, the court is not entitled to make speculative assumptions in lieu of proof. I am told wiring diagrams were also stored on computer records which were not copied, and the originals of which have been lost. The latter sad loss rather underlines the need for the practicable taped marking envisaged by Egger’s own GMP specification. In such a situation as this, the braces should accompany the belt. In relation to the labour element, Egger have proved on the evidence costs caused by water ingress in the ducting to the extent of£75,500 . SUMMARY Labour Costs£75,500 Original excavation£13,332 Sealing£7,572 Materials£24,500 External groundworks/sealing of redundant ducts£3,000 Total claim proved£123,904 COUNTERCLAIM: H(1) M & E MINOR ITEMS 489. Eighty-six items previous in dispute have been agreed by the experts both as to liability and quantum, which total£77,851.23 . 490. There are a number of outstanding items which fall into two categories, mechanical items and claims where the issue in dispute is one of proper interpretation of Clause 22 of the Conditions of Contract. Egger are entitled to recover interest on the minor items below held in their favour by reference to the information in the estimates provided by Mr David Gardner. ITEM 12:I 491. This relates to the air receiver in the compressor room. Rusting has occurred as is to be expected where air and moisture is drawn into an air receiver. The unit was fitted directly after the compressors which have allowed the moist warm air to enter and hence condensation to form. 492. SCL contend that the level of corrosion is within the appropriate British Standard and has been taken into account in the sacrificial calculation in complying with the specification. Scott Air state that the normal life expectancy of an air receiver is expected to be 20 years. Egger seek the assurance of a guarantee, which this letter clearly is not. The plant is now over 5 years and has a planned life of 25 years. Damages are assessed at£1 . ITEM 17:I 493. Egger contend that in the tool sharpening room, as in other locations, incoming MWS and HWS water systems have exposed pipelines and no insulation is fitted adjacent to the water entry point. Pipelines enter within 750 mm. of the external wall and thus fall within Water Supplies Byelaw 49. 494. There is no reliable evidence to the extent of the problem since it is hidden. Investigation for the purposes of conducting a survey doubtless will form a significant part of the cost of any remedial work. The solution where appropriate is to insert insulation material using a lubricant to insert around the pipe. Mr Bailey in cross examination confirmed his view that 100% of the locations need attention and the cost of having this work done by a third party was£15,979 . SCL say that N.G. Bailey are willing to undertake the remedial work. There is some evidence in the written statement of Mr Percy to this effect. There is no reason why almost five years after the work was done that Egger should be obliged to permit N.G. Bailey to remedy work that was badly executed in the beginning. In any event N.G. Bailey are not before the court and although a mechanism could be achieved to permit them to do so without finally adjudicating upon the issues now, this stale matter calls for finality. It would have been open for the remedial proposals of Bailey to have been explored and safeguarded proposals made as to the method and extent of investigation and method of putting them right. It is far too late for SCL to canvass the matter now. This claim is established by Egger in the sum of£15,979 . ITEM 24 495. This claim arises out of the fact that in a number of locations, the sprinkler/hydrant systems have been laid too shallow in breach of water byelaws. Apart from exposing Egger to the consequence of breach, Egger have pipe work vital for fire safety which could be at risk of freezing because it is inadequately protected. This state of affairs which has been brought about by SCL has the corollary that in the absence of accurate records and marking, the exact location of this piping is not easily ascertained. By10th October 2001 when both M & E experts visited the site, six pits were dug as test pits and piping was found in three only. It prompted SCL’s expert to conclude that to establish the extent and state of the piping on a reasonable estimate, 70 trial pits would have to be dug. The economic way of achieving a byelaw depth of coverage of the water pipes would be to cover the pipe runs with chippings where possible and excavate and insulate where the lie of the land does not lend itself to that easy and cheaper solution. Lymburn have quoted for undertaking this work. The pleadings do not cover mains and process water piping. The Lymburn remedial quotation does. Sixty per cent of the works is attributable to the extent of the hydrant and sprinkler pipe work on the basis of measurement by Mr Wright. I accept his assessment. Mr Wright has a much closer first-hand knowledge of the Barony works site than Mr Bailey as Mr Bailey has fairly acknowledged in evidence. Mr Wright’s figure, I am satisfied, discounts the mains and process water element of the Lymburn quotation and takes into account the degree to which expensive remedials are necessary and the extent to which the cheaper solution may be implemented. I was impressed by the pragmatic approach of Mr Wright based on his sound judgment. As I observed earlier, SCL’s neglect should not drive Egger’s commercial priorities. This work was not undertaken earlier. The cost of investigation by reason of SCL’s default are not inconsiderable. The operation of the plant has not yet been affected. I see no reason to discount what I conceive to be the appropriate assessment of the cost of remedial works. I value this claim, therefore, at£43,769 . ITEM 25 496. In a number of locations magnetic marker tape has not been provided to indicate the locations of the sprinkler and hydrant pipe work. There is a real risk that workmen during the 25-year life of this industrial site could inadvertently damage the pipe work, whose physical presence is not marked, when using heavy machinery or plant. Mr Wright in his evidence based on his knowledge of the site, estimated that 45% of the pipe runs need marking. Mr Bailey comments “that the mains are clearly on the record drawings and although I agree that these are not 100% marked as they are in coloured polythene pipe work, tape is generally superfluous”