“If and in so far as Bovis is liable to Braehead in respect of the alleged defects to the fire protection, as Braehead contends, then Bovis claims damages and/or an indemnity from RD Fire in respect of such liability.”
“The sums claimed, being the value of Bovis’ contractual rights under the Main Contract with Braehead which were impaired by Braehead withholding payments against defects in the fire protection works under Clauses 13.4 and 30 of the Main Contract.”
“Further and in any event, Bovis has suffered its ownloss and damage of the same kind and amount as suffered by Braehead, in that, as a result of the defects, Bovis’ performance interest under the Sub-Contract was damaged, because RD Fire did not provide Bovis with the benefit of the bargain entered into under the Sub-Contract, ie the benefit of a proper discharge of the Sub-Contract.”
“The settlement ... was a global settlement in which no specific sumwas attributed to the defects in the fire protection. ... the settlement reflected its liability to Braehead and the impairment of its rights [to payment].”
“Bovis did make a financial loss by entering into the settlement caused by RD Fire’s breaches amongst other causes. But it is impossible to say what that loss was and so no claim is made in respect of it.”
“In entering into the settlement Bovis ... made a reduction of an unascertained amount from the sums otherwise due from Braehead to Bovis. The global settlement represented an overall discount on Braehead’s counterclaims of 22%. On a pro rata basis 22% of£6.4m is£1.4m .”
“In building cases, the pecuniary loss is almost always measured in one of two ways: either the difference in value of the work don or the cost of reinstatement. Where the cost of reinstatement is less than the difference in value, the measure of damages will invariably be the cost of reinstatement. ... That is why it is often said that the cost of reinstatement is the ordinary measure of damages for defective performance under a building contract.”3 However where it is not reasonable to reinstate, Lord Lloyd stated: “If the court takes the view that it would be unreasonable for the plaintiff to insist on reinstatement, as where, for example, the expense of the work involved would be out of all proportion to the benefit to be obtained, then the plaintiff will be confined to the difference in value.”
“indemnify and save harmless the Contractor against and from: 5.2.1 any breach, non-observance or non-performance by the Sub-Contractor or his servants or agents of any of the provisions of the Main Contract as they relate and apply to the Sub-Contract; and 5.2.2 any act or omission of the Sub-Contractor or his servants or agents which involves the Contractor in any liability to the Employer under the provision of the Main Contract in so far as they relate and apply to the SubContract; and 5.2.3 any claim, damage, loss or expense due to or resulting from any negligence or breach of duty on the part of the Sub-Contractor, his servants or agents (including any wrongful user by him or them of the scaffolding referred to in this Sub-Contract or other property belonging to or provided by the Contractor).”
“the settlement ... was a global settlement in which no specific sum was attributed to the defects in the fire protection” and that: “Bovis did make a financial loss by entering into the settlement caused by RD Fire’s breaches amongst other causes. But it is impossible to say what that loss was and so no claim is made in respect of it.”
“Therefore, it is impossible toknow what sum was allowed by the parties against the sum of£6,485,601 [being claimed by Bovis]. .. In entering into the settlement Bovis reasonably mitigated its loss be securing a release from Braehead’s claim for£6,485,601 by making a reduction of an unascertained amount from the sums otherwise due from Braehead to Bovis; the global discount made against all Braehead’s counterclaims was£22,778,226 /£103,584,365 = 22%. ... Bovis gave value in the settlement against this claim for 22% of the sum of£6,485,601 ie£1,426,832 .”