“… let us have a note, Sir, of particular matters that concern you and your approach to some of these quantity surveying issues. Either on Wednesday, if you follow Ms Gough’s guidance or Friday if you follow mine”: per Mr Alan Steynor, Counsel for LBHF, at page 192 of the Transcript for30th July 2001 . To which Ms Karen Gough, Counsel for HoH, added: “If it is a long list send it sooner (than Friday) if you want the answers by Monday.”
“… during this meeting both the status of the final measurement and the financial aspects of our claim were reviewed by yourself. Of our fifteen heads of claim, two were not considered as part of the claim. These were No1 – Items Not Agreed in the Final Account, which remains the subject of discussions with the Quantity Surveyors, and No 5 – Additional Insurances, which we have included in our overhead calculations. Of the remaining thirteen heads of claim, you rejected four as inadmissible. These were: No 7 Extended Scaffold Hire No 8 Under-recovery of Head Office overhead No 9 Loss of Profit No 15 Claim preparation You also stated that you considered that no money was due under a further two headings. These were: No 6 Additional preliminaries No 12 Additional Labour You agreed that, subject to our providing you with further unspecified information, you would consider the following six heads of claim: No 2 Additional Finance Charges No 4 Additional Bond Charges No 10 Additional Site Cleaning No 11 Additional Safety Visits No 13 Additional Supervision No 14 Escalation of Costs You considered that Item No 3 – Extended Defects Liability would, in the event that you gave it consideration, represent an insignificant sum. We now consider that there is little possibility of your making a realistic assessment of our claim and therefore, with regret, must inform you that we consider that a dispute or difference has arisen between us. In order to resolve this, we require that the dispute or difference be referred to arbitration and have notified the Employer accordingly. A copy of our letter to the Employer is enclosed for your information.”
“Further to our Agreement dated25 June 1996 , a dispute or difference has arisen between ourselves and the Contract administrator regarding the valuation of the amount due to us for disruption. Please accept this letter as formal notification under Clause 9.1 of our Contract that we require this dispute or difference to be referred to arbitration under Article 5 of our Agreement. …”
“23. In late 1998 and early 1999 it also became clear to Home of Homes … that outstanding issues concerning the measured works element of the final account … were unlikely to be resolved by negotiation with the Quantity Surveyor, Consul. 24. To this end, Home of Homes sought to schedule the entirety of the items which remained in dispute between the parties concerning the final account. At the same time, the split of responsibility between the quantity surveyors, Consul, and LBHF’s own contract administrator, Mr C. Stroud, who had assumed responsibility for the evaluation of Home of Home’s claims for disruption, made it impossible for Home of Homes to progress any negotiation of those matters. Home of Homes therefore thought it might be helpful if it sought to provide an alternative basis of evaluation of its claims and to re-evaluate its disruption claims, particularly the labour element of the disruption which formed a substantial element of its claims in the arbitration, under the provisions of clause 3.7 of the Conditions of Contract. 25. This effort manifested itself in the provision of a substantial A3 Schedule Scott Schedule style document … included in which were the outstanding final account items still unresolved by the parties.”
“65 Power to limit recoverable costs (1) Unless otherwise agreed by the parties, the tribunal may direct that the recoverable costs of the arbitration, or any part of the arbitral proceedings, shall be limited to a specified amount. (2) Any direction may be made or varied at any stage, but this must be done sufficiently in advance of the incurring of costs to which it relates, or the taking of any steps in the proceedings which may be affected by it, for the limit to be taken into account.” (1) Unless otherwise agreed by the parties, the tribunal may direct that the recoverable costs of the arbitration, or any part of the arbitral proceedings, shall be limited to a specified amount. (2) Any direction may be made or varied at any stage, but this must be done sufficiently in advance of the incurring of costs to which it relates, or the taking of any steps in the proceedings which may be affected by it, for the limit to be taken into account.”
“E. Costs of the parties was discussed. The Arbitrator agreed to send a copy to each party of the other’s submission to the Arbitrator on costs, both spent and forecast (this is enclosed with this Order). The Respondent had suggested, in its note to the Arbitrator of23rd November 1998 , that a limitation of£60,000 be put on recoverable costs – in clarification the Arbitrator established at the meeting that this was suggested as applicable to each party. The parties agreed to comment to the Arbitrator on these submissions within seven days in order for the Arbitrator to take the parties’ views into account in any limitation of recoverable costs of the parties. The Arbitrator stated he would review parties’ costs once he had received witness statements on or before11th December 1998 . It may then be appropriate to review costs at or before the meeting provisionally reserved for21st December 1998 . F. Mr Moorhead agreed to supply further information on his consultancy costs that have been included as part of the Claimant’s loss and expense claim.”
“Home of Homes concludes its comment by noting that it would be inappropriate to apply any cap on future costs, given the directions which have been issued for the future conduct of the Arbitration and the uncertainty, certainly in so far as the Borough’s future costs are concerned, of the actual costs which are likely to be incurred. In addition, the stage of the Arbitration has been reached where the costs on each side are unequal, the greater burden being on Home of Homes to prepare for the forthcoming hearing. A calculation of a fair allowance would therefore be very difficult and highly likely to prejudice Home of Homes. Accordingly, on the basis of the information before you, a cap on costs would be inappropriate at this stage.”
“G. Agenda Item 7 – Costs of the Arbitration. The Arbitrator referred to (HoH’s) letter of15th December 1998 on costs. (LBHF) re-stated its concern that costs were out of control on a dispute with a claim of around£300,000 . (HoH) stated that it may potentially be prejudiced by limitation of costs at this stage. The Arbitrator gave an indication that he will order a limit of£90,000 to each party’s legal and other costs that would be recoverable from21st December 1998 until the completion of the hearing. (HoH) asked if the Arbitrator would give reasons for his decision. The Arbitrator asked for (HoH) to give authority that required reasons to be given on an Order for Directions. The parties agreed that the Arbitrator had indicated his intention to limit costs of each party to£90,000 , with effect from21st December 1998 until completion of the Hearing but that this would not be ordered until18th January 1999 . (HoH) may make a submission requesting reasons for the Order by8th January 1999 , any response by (LBHF) will be by12th January 1999 and the Arbitrator will give an Order, with reasons if appropriate, after18th January 1999 .”
“(3) Order to limit costs of the parties I have considered the letters and submissions from the Claimant of8 January 1999 and from Respondent of11 January 1999 . I further note that the Claimant has referred to a number of actions it may feel are necessary. I do not consider that I have to give reasons for any Order that costs will be restricted to£90,000 for each party.”
“You say in the final sentence … : “I do not consider that I have to give reasons for any Order that costs will be restricted to£90,000 each party.”
“It is only with great regret that our clients have instructed us to write this letter. However, your recent decisions leave no other option open to our clients. The sum of our client's complaints is that there have been serious irregularities which affect the proceedings in train before you and which will affect the award. The most prominent of these is your decision to make a direction capping the parties' costs in this arbitration. This letter is principally directed to that matter, which has been exacerbated by your refusal to give reasons for such a serious decision. The purpose of this letter is to invite you to reconsider both the decision to cap the costs and the decision to refuse to give reasons. Most unfortunately, given the importance of the matter and the proximity of the hearing, it is not possible to give you a long time to respond. If you continue with an approach which, in our client's view, is so objectionable, it will be necessary to seek relief from the court, and to do so urgently. Accordingly, it will only be possible to afford you until the close of business on Friday 5 February to consider the points made in this letter including any comments by the Respondent. We have copied this letter to the Respondent by facsimile and it will be able to let you have the benefit of its thinking on the matter without delay. On the credit side, the points are short and should not cause you any difficulty. … Had such an order been made much earlier in the proceedings, say in October, but in respect of the period mentioned in your order, it might have been acceptable. However, by the time that you made the order, the costs position had changed substantially from the time when the parties had provided you with their costs information, not least by reason of the amendment that you had decided to allow. The situation was made worse by your insistence upon further meetings with experts and by the fact that you did not have any current (as at the end of December) estimate of the costs likely to be incurred by our clients. In addition you have never had and have not pressed for an adequate estimate of the costs likely to be incurred by the Respondent. In the premises, it is respectfully submitted that you did not have the necessary material for an order under s.65. What is more, it was not done sufficiently in advance of the commitment to incur the costs for either side to take it into account. In the premises, it is respectfully submitted that you have exceeded your jurisdiction and/or that a serious irregularity affecting the proceedings and/or the award has occurred and/or that there is an important question of law which needs to be determined urgently.”
“CAPPING COSTS 36. The Respondent is frankly amazed that this issue has once more been raised. The Respondent's position is that enough is enough. 37. The Claimant does not like the idea of a costs capping order. However, one was made. Implicit and explicit threats were made by the Claimant that it would seek redress from the Courts in relation to that Order. Had its bluff been called, the Respondent has little doubt that no application to the Court would have been made. … 38. The only Order which the Arbitrator, with respect, was not entitled to make was its Order No. 6. That was outside his jurisdiction for 2 reasons: (i) He had no jurisdiction under section 65(2) to revoke his previous order in the absence of any new circumstances affecting the level or fact of the cap. A true construction of section 65(2) inevitably leads to that conclusion. (ii) The direction of a cap of costs which were “reasonable” and "reasonably incurred” does not fall within the ambit of Section 65 which refers only to Orders for a "specified amount”
“In an extraordinary order made on19th February 1999 , as a result of a failure on his part to understand the genesis of a substantial number of Home of Homes’ itemised disruption items, which had been recast in the A3 Scott Schedule served on9th February 1999 , he ordered and purported to exclude the claims in that schedule from the impending hearing scheduled to commence on3 March 1999 ”
“For your information, we are currently preparing a schedule which will list all of the items in dispute between the parties. We have discussed this with the Respondent and it is our intention first to agree that the list is complete, and then to agree how each item is to be dealt with. In the event that we are unable to reach agreement on the method for certain items, we will seek your ruling. Ultimately we hope to have an agreed list of disputed items to put before you for your decision. We hope that this will be of assistance.”
“No allowance shall be made in the valuation for any effect upon the regular progress of the Works or for any other direct loss and/or expense for which the Contractor would be reimbursed by payment under any other provision in the Conditions;”
“We consider firstly the format for Wednesday. As we anticipate matters, the first topic to which the parties will return is how you approach the issues in this case. We would respectfully suggest that the most convenient course would be for the parties to put forward any further remarks that either may have on the matter of jurisdiction and then leave it to you to issue a formal decision, with reasons please for such an important matter, in due course. Until such time as you are in a position to provide your decision, save as set out below, the hearings should be adjourned. … Secondly, the unfortunate event is that the Claimant, in view of the degree of criticism that has been levelled at its quantum expert, has had to take a second opinion on the issues of quantum in the case and may well be seeking leave to call a replacement expert. While this is undoubtedly most inconvenient, fortunately, in view of the more pressing issue of jurisdiction and the need to take time to issue a formal reasoned decision on that matter, there should be no additional disruption to the progress of the hearing. … We therefore with reluctance propose the following timetable for the Hearing:- Wednesday3 March 1999 Submissions of the parties on jurisdiction; outstanding issues of costs. Site visit 4.00 pm as arranged if possible. Adjournment of hearing. Monday8 March 1999 Parties’ submissions on issue of whether "time at large". 1 day. Hearing adjourned to be refixed after formal decision of the arbitrator on costs. In the light of the difficulties over jurisdiction and expert evidence, you will appreciate the difficulties we have had in settling an opening for the case which you are scheduled to hear. We will address you further on this matter tomorrow. ”
“at this juncture, the parties effectively abandoned attempts to have matters dealt with by the Arbitrator and tried to settle the cases through their experts”
“41. Unfortunately, 2001 did not see a smooth path to a contested hearing and the resolution of the disputes before the Arbitrator. Following a hearing on22 March 2001 , at which the Arbitrator had the benefit of a transcript; a note from Counsel, and agreed directions, he managed to make such a mess of his Directions Order No 9 that both Counsel settled extensive letters to him to correct the errors manifest in his Order, at considerable extra cost to the parties. The Arbitrator issued an amended order. Once again, on the part of the Arbitrator this demonstrated: 41.1 a lack of attention to what had taken place during the hearing; and/or 41.2 a failure to understand the issues he was being asked to record by consent in his directions order; and/or 41.3 a complete lack of care in the preparation of his order.”
“4. Following the hearing on3 March 1999 , the parties exchanged submissions as to the extent of the Arbitrator's jurisdiction and he thereafter took leading Counsel's opinion and issued his First Award on16 March 1999 dealing with his jurisdiction and also issues concerning the capping of the parties' costs in the arbitration. … 2. Review of Parties' positions on items in dispute 2.1 The pivotal documents are the First Award and the Akenhead Opinion. As far as the Respondent's list of issues in dispute is concerned, the Counterclaim is not agreed to be within the Arbitrator's jurisdiction following his First Award. The Claimants enclose a table showing the genesis of the claims included in the reference to Arbitration and the Arbitrator's jurisdiction. 2.2 The Counterclaim is an issue about which the Claimant disagrees over jurisdiction. 2.3 The final account items I not yet resolved are outside the arbitrator's jurisdiction, also the non-payment of the retention fund; poss landfill tax in relation to skip hire. There is no agreement either to extend the arbitrator's jurisdiction to include these items within the present arbitration. (this is what the dispute was about in 1999.) 3. Agreement of Jurisdiction None see above …”
“46. Finally, the Arbitrator issued his Second Award on28 May 2001 …The Award runs to some 19 pages and contains many ambiguities and errors. In particular, Home of Homes was appalled to see that the Arbitrator had completely misstated its arguments in the body of his award. 47. Of the 19 pages of the award, the first 15 contain introductory statements and the alleged submissions of the parties. On page 15 at 3.0 the Arbitrator purports to begin to lay out his findings and reasons and immediately seeks to reiterate what he understands to be the parties contentions and then gives, with little or no reasoning, his decision. In relation to the bulk of the matters referred to him for a decision on jurisdiction, he deferred any decision. 48. Following receipt of the ASA Home of Homes considered how best to deal with the award and the issues arising from it. The Arbitrator had, after an expensive and lengthy process, failed to resolve most of the issues put to him for decision or even to indicate to the parties what he required in order for him to do so. This remained the position up to and including the hearing which took place in July 2001 notwithstanding Home of Homes requests that he deal with matters. 49. In the event, Home of Homes decided that the best course to try and keep things moving along towards a final resolution of the issues on the merits of the case and so made an application under section 57 of the 1996 Act …for clarification and correction of the various matters addressed in the ASA so that they would at least have a reasonable understanding of what the Arbitrator had decided and the basis of those decisions.” (2) Paragraphs 43 to 44 of The Grounds are as follows:- “43. The parties having produced their submissions on jurisdiction, the Arbitrator then published on28 May 2001 , his Second Award, "the ASA". Unfortunately, the problems demonstrated in his AFA, were again manifest in the ASA. The ASA: 43.1 Contains errors and ambiguities; 43.2 Misstates in a material manner, arguments put by Home of Homes; 43.3 fails to give any, or any proper reasons for his decisions; 43.4 mixes submissions, decisions and statement of facts so as to render the Award virtually incomprehensible, save that he - 43.5 fails to deal with the majority of the issues which had been put to him for decision in any event; 43.6 fails to indicate to the parties that he had insufficient information or that he required further information in order to make any decisions on the outstanding issues; and 43.7 misconstrues Home of Homes submissions concerning the construction of the AFA, to the opposite of that contended for by Home of Homes and misstated the effect of the AFA and the opinion of leading Counsel adopted thereby; and,. 43.8 on any view, the Arbitrator took insufficient care to seek to decide the issues that had been put before him for decision and, in the event, failed to decide the majority; and, 43.9 as with the AFA, fails to observe the requirement to state the seat of the arbitration. 44. In the event therefore, the parties spent a further substantial amount of time and money on an exercise which failed to advance the resolution of the disputes in the arbitration, due almost entirely to the Arbitrator's inability to understand the issues put to him for decision, and – in accordance with his duties under the 1996 Act, make clear and sensible decisions based on a proper understanding of the evidence and arguments put to him for that purpose.”
“If such an application is made, (LBHF) will deal with this issue at this stage”
“ … at most the Arbitrator may wish to consider whether he needs to clarify his Second Award in certain respects. The Respondent takes the view that the Arbitrator has already dealt with all the issues which were presented to him before he made his Award, but if the Arbitrator feels that he might profitably expand upon his comments, then (LBHF) would have no objection.”
“1. On application from the Claimant I have considered my Order for Directions No. 5 and after hearing further submission I amend my Direction. The legal and other costs of each party that shall be recoverable shall be costs such as are reasonable and have been recently incurred by a party during the period from21 December 1998 until completion of the hearing on17 March 1999 and shall not be limited to£90,000 for each party in accordance with my order for directions No. 5. 2. Liberty is given to either party to apply to me for an amending Direction.” order: "...Accordingly this note confirms that the Arbitrator's jurisdiction under the JCT Arbitration Rules shall include matters arising in the dispute as already referred to him together with. ..." And In paragraph 3.1(4) on page 17, the Arbitrator stated: "It does not, of itself, follow that because I have found that the Claimant's claims under contract clause 3.7 were excluded from my jurisdiction, which I confirmed in the AFA..." And In paragraph 3.1(7) on page 17, he also stated: "I consider that my ruling on jurisdiction given in my First Award, namely that I could deal with matters arising under contract clause 4.11 as within my jurisdiction, whereas I could not deal with matters arising under contract clause 3.7..." 8.1 While it is appreciated that the Arbitrator's statements are directed to the admissibility or otherwise of the Respondent's Counterclaim to reduce the extension of time previously granted by the Contract Administrator, this paragraph raises an important issue of principle concerning the construction to be given to the AFA and should therefore be precise and clear as to that part of the AFA on which the Arbitrator's construction is placed. Please would the Arbitrator therefore identify in his ASA, which clause in the AFA confirms the proposition advanced or otherwise how he has reached the construction of the AFA which he appears to have reached? 8.2 By way of explanation of the Claimant's concerns: see the extract from the Note F to Directions No.1, issued on16 January 1998 where the Arbitrator confirms his jurisdiction as to matters generally to those matters arising in the dispute already referred to him but appears now to say, and construe his AFA as meaning, that some of those original items of claim may be excluded because they arise or could be construed to arise under clause 3.7 of the contract. 8.3 It is therefore imperative that if the Arbitrator is construing his AFA so as to potentially exclude some of the original items of claim from his jurisdiction, that he does so in the clearest terms, so that the Claimant can challenge that decision in the appropriate forum. 8.4 The Arbitrator is referred to the AFA clause 3 where his decision is recorded and where he decided that he has no jurisdiction to consider matters which the Claimant had sought to "introduce" into the hearing via the A3 Scott-Schedule. 8.5 Furthermore, the need for clarification becomes even more urgent in circumstances where the Arbitrator has patently misunderstood the Claimant's submissions on that issue, and may have proceeded to his own conclusion without thinking properly about the matter on the mistaken belief that he was simply making a proposition which was not in contention between the parties. If so, he was wrong in his belief, and the Claimant's contentions are quite different from those summarised and attributed to it by the Arbitrator in the ASA. 9. In paragraph 3.3 on page 18 of the ASA the Arbitrator has considered the Higgins' claim and appears, while deferring any decision in the ASA, to be considering his jurisdiction towards an original item of claim in the context of his construction of the AFA dealt with in paragraph 8 above. However, the Arbitrator's reasoning is extremely limited and unclear. 9.1 In paragraph 3.3(1), the Arbitrator mentions the possibility of an overlap between clauses 3.7 and 4.11 but is unclear about whether his concern is one which is founded in his jurisdiction to determine an original element of the Claimant's claims or whether any overlap issue arises in the context of items of claim which may have already been reimbursed under clause 3.7 in the measured works element of the final account and should not therefore be recoverable a second time under clause 4.11. 9.2 In particular, the ASA at 3.3(2) states: "My decision on jurisdiction on the Higgins claim for loss and expense will be deferred until, if necessary, oral evidence can be heard." 9.3 However, the Arbitrator does not state in his award, whether he considers oral evidence to be necessary and, if it is, what the nature of that evidence should be in order to help him reach a decision as to his jurisdiction. 10. In paragraph 3.4 on page 18: on the issue of extended bond charges, the Arbitrator determined: "My preliminary indication to the parties is that this claim does not fall within the ambit of this arbitration." 10.1 The Arbitrator's preliminary indication is not motivated in any way and the Claimant cannot therefore understand the basis of the indication given. 10.2 While, short of challenging the award before the Court and persuading the Court to order the Arbitrator to give reasons, the Claimant cannot force the Arbitrator to give reasons for his indication, it seems wholly inequitable for the Arbitrator to give such an indication without giving any explanation for the basis of his statement. The parties have expended time and effort seeking rulings on particular issues, and while they may be content with a decision to have one or more of them dealt with at the hearing, if and where the Arbitrator expresses any view as to the merits of a point, reasons are required and they assist the parties to marshal their arguments to address those points at the hearing. 11. In paragraph 3.5 on pages 18/19 the Arbitrator stated at 3.5(2) in relation to the claim for additional supervision: "I conclude that this is an original item in the Claimant's claim but that it has also appeared in matters contended under contract clause 3.7 submissions. I do not consider that I have sufficient information on which to decide this matter now and I will defer a decision on jurisdiction until, if necessary, further evidence is submitted on this item at the hearing. 11.1 This was an issue on which the parties sought a decision, which the Arbitrator failed to give in the ASA. 11.2 The Claimant refers to paragraph 8 above, it is inferred but is not clear what the Arbitrator's attitude is to original items of claim per se. 11.3 The Arbitrator stated at 3.5(2) that he did not make any decision because he did not have sufficient information on which to decide the matter. He did not however, before issuing his award, invite the parties to provide him with the necessary information, and has failed in his award, or since the publication of his award, to give any indication as to what the necessary information might be. 11.4 The award is a "speaking award" but is wrongly silent both as to the information required and the nature and extent of any necessary further evidence which the arbitrator requires to help him decide this issue of jurisdiction. Would the Arbitrator please therefore clarify his award so that the parties know what is required and may understand the basis of his refusal to givean award on this issue of jurisdiction”. THE CLAIMANT'S APPLICATION 5.1.1 The Higgins claim: as to the part challenged: See 3.3(2) "My decision on jurisdiction on the Higgins' claim for loss and expense will be deferred until, if necessary, oral evidence can be heard." 5 .1.2 Extended Bond Charges: See 3.4(2) "I make no decision now on my jurisdiction" 5.1.3 Additional supervision: See 3.5(2): "I will defer a decision on jurisdiction until, if necessary, further evidence is submitted on this item at the hearing”. 3.1 I have noted the Claimant's contentions as set out above, namely that: The same contention is repeated in paragraph 12 of the Claimant's Reply. (i) Whatever the intentions concerning the scope of the AFA, the fact is that the AFA defined my jurisdiction. Therefore my jurisdiction is restricted to matters arising for determination under contract clause 4.11." [emphasis supplied] And In paragraph 3.1(4) on page 17, the Arbitrator stated: "It does not, of itself, follow that because I have found that the Claimant's claims under contract clause 3.7 were excluded from my jurisdiction, which I confirmed in the AFA..." And In paragraph 3.1(7) on page 17, he also stated: "I consider that my ruling on jurisdiction given in my First Award, namely that I could deal with matters arising under contract clause 4.11 as within my jurisdiction, whereas I could not deal with matters arising under contract clause 3.7..."