“Please find enclosed the following documents to enable the registration of TU0192GB copy quotation Q0518B cost sheet for car parking cost sheet for hard standing The project is suspended on piles… Our contract for this element is with [GSE]. The internal slab will be with Wates Construction and will be a separate contract and order number. Please confirm you have registered the B & Q external area for July…” copy quotation Q0518B cost sheet for car parking cost sheet for hard standing Please confirm you have registered the B & Q external area for July…”
“Re: New B&Q, Belvedere 38. Lump sum, fixed price, all risk quotation totalling£637,897.46 nett to supply labour, plant and material to concrete all the external hard standing areas to the engineers specification. 39. On my return from holiday, we need to arrange a meeting with Wates Construction to agree a sequence of works.”
“[Mr Parker] will send order at latest by Wednesday 19 December: [Mr Parker] held off placing order until confirmation received by GSE legal team that GSE not in breach of contract; DE [presumably Mr Eddy] threatened an injunction to stop job! AD on phone several times in similar vein”