“President or a Vice President of the Royal Institution of Chartered Surveyors.”
“Pending execution of a formal contract based upon an amended standard form of Building Contract with Contractor’s Design 1998 Edition issued by the Joint Contract Tribunal with amendment 1 1999, TC/94/WCD and any further amendments as specified, drafts of which were included in the tender documents, and any other amendments as may be agreed between ourselves, we hereby issue this letter of intent of instruction in relation to your firm price tender dated12th April 2000 for the execution and completion of the above works, including the development and completion of design and within a construction period to be agreed prior to contract.”
“The scope of the works is outlined in the Employers Requirements dated March 2000 at a total estimated cost of£4.55 million , or such other sum as may be agreed.”
“Until the execution of a contract in the form referred to above, neither you nor we shall be bound or committed in any way beyond the scope of the works instructed by this letter, and the terms of payment and all other terms and conditions, including the arbitration agreement in Article 5, shall be as contained in the form of contract referred to above.”
“If you want to place orders for work or materials, you must get prior written authorisation.”
“The payment for any works will be administered in accordance with the terms of the proposed contract as set out above. However, there will be no payment for the pre-construction services prior to January 2001. Until the formal building contract is completed, our maximum liability to you will be£3.25 million . The value of the works carried out by you will, in due course, form part of the contract sum under the above mentioned contract if our negotiations are successful.”
“Where the entry in the appendix stating that clause 39B applies has not been deleted, then, subject to Article 5, if any dispute or difference as to any matter or thing of whatsoever nature arising out of this contract or in connection herewith, except in connection with the enforcement of any decision of an Adjudicator appointed to determine the dispute or difference arising thereunder, shall arise between the Parties either during the progress or after the completion or abandonment of the Works or after the determination of the employment of the Contractor,….. it shall be referred to arbitration under clause 39B and the JCT 1988 edition of the Construction Industry Model Arbitration Rules (CIMAR).”
“If it had been intended to qualify the word ‘decision’ in some way, then this could have been done. Why not give the word its plain and ordinary meaning? I confess that I can think of no good reason for not so doing, and none was suggested to me in argument. If his decision on the issue referred to him is wrong, whether because he erred on the facts or the law, or because in reaching his decision he made a procedural error which invalidates the decision, it is still a decision on the issue. Different considerations may well apply if he purports to decide a dispute which was not referred to him at all.”