"I have already carried out two adjudications on this particular project between the main contractor and Pring and St Hill. There may well be information from those two adjudications which will be of assistance in this adjudication. I am also asked to run this adjudication in parallel with an adjudication with J C Howell UK Site Fix. I am sure that the reasons for that request will become clear when I receive the referral."
"We wish to advise that our client has not been asked to consent to any such request and does not wish to do so. Whilst we have no wish to suggest that you would not otherwise be competent to act as an adjudicator in either or both of these status two adjudications, both we and our client are concerned that there is a serious risk that a breach of natural justice may arise were you to act as an adjudicator in the present proceedings and/or indeed in relation to the proposed parallel proceedings."
"Our client is quite naturally concerned that in the context of your prior involvement in earlier adjudication proceedings between the referring party and Sir Robert McAlpine and your proposed involvement in yet further proceedings brought by the referring party against yet another party, there is a risk that information gained in other proceedings to which our client is not a party and which has not been made available to our client, may influence your judgment in deciding issues in the present proceedings between the referring party and our client. In those circumstances regrettably we do not believe that it would be appropriate for you to act as adjudicator in the proceeding to which our client is a party. In so far as your appointment may have been validly made in these proceedings (as to which we expressly reserve our client's position) we would therefore invited you to resign from your appointment to act as an adjudicator. A fresh application … could then be made by the referring party with minimal delay"
"There is nothing in my appointment, having regards to the two previous adjudications, that offends natural justice. In terms of any influence from the two previous adjudications I am fully aware of the guidance given in the case of Fox v. Wellfair and it has been my intention from the outset, when I receive the response, to reveal all of the relevant information from the previous adjudications to ensure that both parties are fully informed. I am proceeding with this adjudication."
"Some further explanation is warranted concerning the two previous adjudications I carried out between Pring and St Hill and McAlpine. The first of these adjudication's [sic] concerns a claim for damages by McAlpine against Pring and St Hill. The claim for damages arose through the work being carried out to the Bris Soleil support steelwork on the project at Caspian Point in Cardiff. The claim for damages arose through physical damage caused to the glazing to the building arising through weld spatter and grinding of welded joints when Bris Soleil steelwork was erected. The second adjudication concerned the final account between Pring and St Hill and McAlpine. In the present two adjudication's Pring and St Hill are seeking to pass on the damages claim for the physical damage caused to the glazing, which was the subject of the first adjudication between Pring and St Hill and McAlpine. It may well be that Pring and St Hill thought that my former knowledge of this project would assist in these two adjudication's in terms of the economy. "
"The adjudicator may take the initiative in ascertaining the facts and the law necessary to determine the dispute, and shall decide on the procedure to be followed in the adjudication."
"If the parties [are] not agreed on amalgamating some of the procedure, in order to reduce costs and to ensure exchange of common evidence I am under a duty to ensure that in both adjudication's what materials I have which might touch on each adjudication and importantly those matters which will lead to my decisions. I will therefore ensure that there is nothing in the two adjudication's that the respective parties [are] not aware of."
"The adjudicator, with the consent of all the parties to those disputes, adjudicate at the same time on related disputes under different contracts whether or not one or more of those parties is a party to those disputes."
"10. Where any party to the dispute objects to the appointment of a particular person as adjudicator, that objection shall not invalidate the adjudicator's appointment nor any decision he may reach in accordance with paragraph 20."
"Where any provisions of the Scheme for Construction Contracts apply ... in default of contractual provision agreed by the parties, they have effect as implied terms of the contract concerned."
"The court must first ascertain all the circumstances which have a bearing on the suggestion that the judge was biased. He must then ask whether those circumstances would lead a fair mind and informed observer to conclude that there was a real possibility, or a real danger, the two being the same, that the tribunal was biased."
"37. Bias is an attitude of mind which prevents the Judge from making an objective determination of the issues that he has to resolve. A Judge may be biased because he has reason to prefer one outcome of the case to another. He may be biased because he has reason to favour one party rather than another. He may be biased not in favour of one outcome of the dispute but because of a prejudice in favour of or against a particular witness which prevents an impartial assessment of the evidence of that witness. Bias can come in many forms. It may consist of irrational prejudice or it may arise from particular circumstances which, for logical reasons, predispose a Judge towards a particular view of the evidence or issues before him."
"Issue 2. If SE are liable, what are the damages claimable? The basic damages are£123,456.45 for replacing 318 panes of glass."
"17. The adjudicator shall consider any relevant information submitted to him by any of the parties to the dispute and shall make available to them any information to be taken into account in reaching his decision."
"to reveal all of the relevant information from the previous adjudications to ensure that both parties are fully informed"
"On this basis I have calculated the total number of panes for which I think JCH has liability. This is shown in appendix 1."
"I do not accept that other than replacing the glass the other heads of claim constitute damages. They are actually costs in pursuing JCH prior to this adjudication. I find that the sum due to PSH from JCH in respect of damages is 65 panes of glass @£388.23 =£25,234.95 ."
"To this sum is to be added such value added tax as is due in law."