“Alteration or Modification of the Design HB were responsible for the design of the CDP. That included the bored pile walls and the earthwork support. That is dealt with in detail in Section B2 above. After the soil loss event [that is to say, the occurrence on 13-14 March 1996 ] , their design was changed to one that would work. That change was their responsibility and that change was brought about by their failure to comply with the obligations outlined at Section B1 above. There can be no liability on the part of CIS as a result of the alteration or modification by HB of their own design. 2. Assumption 2: “Alteration or Modification of Quantity of Works This assumption is not understood. For the reasons set out above, there would be a re-measurement provisional/approximate of the excavation items. On the primary case, there would be no re-measurement of the earthwork support element, because of Clause 2.2.2.3. If, contrary to that case, there was such a re-measurement it would be under Clause 13.4.1. This is because the earthwork support items in the Bills were also provisional/approximate. 3. Variation Instruction The issue describes the alteration/modification of HB’s design and the change in the quantity of works as comprising “the said Variation”
“Provided that, in respect of the Contractor’s Designed Portion, any such instruction shall be a statement of an alteration to or modification of the Employer’s Requirements”