“VF12 poor quality “Snagging being addressed on the 17th December. “Before we start a project VAS to visit site and [highlight] any issues before the project with site team. “Mike Oldham to be responsible. “Mike Oldham we will hold you responsible in future on all projects. “That level of crap cannot happen again. “We think a hose was damaged by a VAS engineer and the engineer argued that it was not his fault. “Consideration should be made in future for small damage and not arguing the point damaging customer reputation.”
“Expected delivery. “Let me know by the end of week, probably end of January. “ML Agreed to upgrade front and rear top block hanger design FOC. “Check list for VAS to ensure hot zone is 100% before it leaves, MO. “Check list for Derby to ensure furnace is in good condition before hotzone swap commences DB, MO.”
“Position of plates did not matter as long as were attached now hanger design changed”
“ML stated Bodycote traditionally only cared about what was internal in a hot zone and not external ….”
“VAS submit that it is too much of a coincidence that the gas deflection plate came off immediately after Bodycote had done work on3rd July 2019 when prior to then it had been secure and the furnace had run 235 cycles since January 2019… Given that Bodycote have failed to call the men who actually worked on the furnace between January and July 2019 and, in particular, on3rd July 2019 when they are available to give evidence, the court should reject Bodycote’s assertion that the men have said that they did not interfere with the gas deflection plates: Dawkins v Carnival plc[2011] EWCA Civ 1237 per Pill LJ at paras. 21 & 28.”
“It is also apparent from the documents provided by Bodycote that between the reinstallation of the furnace in January 2019 and the incident which happened on5 July 2019 that the hot zone has been worked on, on numerous occasions by Bodycote, who did undertake some of the maintenance on the hot zone themselves.”
“The hot zone in question was worked on, as follows” “(a) 138730 – 06/03/19 – the work is an insurance requirement. I believe the hot zone would have to have been removed to inspect the welds and the wall thickness. The gas deflection plates would have been visible during these works and issues (if there were any) would have been easily identifiable and should have been rectified. “(b) 143282 – 28/05/19 – if this work related to the rear top heating, then Bodycote would have had to either removed the hot zone or repair it in situ. Either way a confined space permit would have been required. I have seen no corresponding permit in Bodycote’s documentation. The gas deflection plates would have been visible during these works and issues (if there were any) would have been easily identifiable and should have been rectified. “(c) 143689 & 142818 – 07/06/19 – I believe these works would have been undertaken whilst the hot zone was out of the furnace. The gas deflection plates would have been visible during these works and issues (if there were any) would have been easily identifiable and should have been rectified. “(d) 143989 – 14/06/19 - The gas deflection plates would have been visible during these works and issues (if there were any) would have been easily identifiable and should have been rectified.”
“47. However, the most crucial work instruction relates to works instruction number 144712 dated3 July 2019 , only 2 days before the incident. A copy of the works order is attached at exhibit “MO6”.” “48. That works order records the following as the description “Whole of top zone load thermocouples going over temp, furnace did not trip in cabinet but alarm load over temp showing on stage” “49. The completion comments say the following “After further inspection we found a couple of issues with the furnace. One was the element hanger pins had broken on the side heating and one of the elements on the top heating had arced. We replaced these and found that the heating breaker would not stay engaged due to a faulty under voltage relay. We changed this component and ran the furnace on a ballast trial.” “50. The repairs could have been undertaken whilst the hot zone was in situ, this would have been a very awkward job but considerably less time consuming than removing the hot zone. To undertake these repairs the gas deflection plates would most likely have been removed, particularly if the top graphite connector block support pins were damaged, during the failure in this area or during the maintenance work carried out in this area. (This is very likely as moly becomes extremely brittle once heated). On the image attached at “MO7”
“Access to gas deflection plates and day to day maintenance “10. On the basis of my experience, I consider it necessary to remove the hot zone in order to gain access to the gas deflection plates. It would not be possible for an engineer to access the gas deflection plates from climbing to the back hot zone whilst installed in the furnace. “11. In addition, given that the hot zone was reinstalled into the V5 furnace only some 6 months before the failure of the hot zone, if an engineer felt that there was an issue which required access to the gas deflection plates or if it was felt any major work needed to be carried out on the hot zone for the repair, we would have simply contacted VAS to rectify the issue. As I recall, VAS was carrying out quite a lot of work for Bodycote at the time and they were very responsive to correcting any issues so it would have been a very straightforward matter for the Bodycote engineers to contact VAS had they noticed such an issue. “12. I have reviewed the witness statement of my colleague Chris Raynor and in particular paragraph 33 in respect of the maintenance work undertaken by Bodycote engineers and the supported document referenced in the table provided in Chris’ statement. Having reviewed these documents it is my view that: “12.1 none of the work undertaken by Bodycote engineers would have required access to the gas deflection plates. “12.2 none of the work undertaken by the Bodycote engineers required removal of the hot zone (which I feel needs to happen before the gas deflection plates can be accessed). I should also mention that removal of a hot zone is not an easy task and requires the furnace to be disconnected for the duration. If an engineer was very experienced in removal of hot zones, this is potentially a task which can be complete in a day (with multiple engineers working on this) but generally I would consider this to be a minimum 2 day job. “13. I have also spoken with the 2 of the site engineers at Derby who would normally be responsible for maintaining the Derby site and they have all confirmed that they did not access or detach the gas deflection plates since the hot zone was installed into the V5 furnace by VAS. I did not speak with the third engineer who normally works at Derby (although I understand my colleagues Gary Starr and Christopher Raynor have) as he had left the Bodycote business at the time I was having these conversations. “Conclusion “14. On the basis of the above it is my view that: “14.1 Bodycote engineers did not access the gas deflection plates between installation of the hot zone into the V5 furnace and failure of the hot zone; and “14.2 the failure of the hot zone, only some 6 months after its installation by VAS into the V5 furnace, is the result of poor workmanship by VAS.” “12.1 none of the work undertaken by Bodycote engineers would have required access to the gas deflection plates. “12.2 none of the work undertaken by the Bodycote engineers required removal of the hot zone (which I feel needs to happen before the gas deflection plates can be accessed). I should also mention that removal of a hot zone is not an easy task and requires the furnace to be disconnected for the duration. If an engineer was very experienced in removal of hot zones, this is potentially a task which can be complete in a day (with multiple engineers working on this) but generally I would consider this to be a minimum 2 day job. “14.1 Bodycote engineers did not access the gas deflection plates between installation of the hot zone into the V5 furnace and failure of the hot zone; and “14.2 the failure of the hot zone, only some 6 months after its installation by VAS into the V5 furnace, is the result of poor workmanship by VAS.”