“This Agreement and the relationship between the parties shall be governed by and in accordance with Australian law and the parties hereby submit to the exclusive jurisdiction of the courts of Australia.”
“If contracting parties agree to give a particular court exclusive jurisdiction to rule on claims between those parties, and a claim falling within the scope of the Agreement is made in proceedings in a forum other than that which the parties have agreed, the English court will ordinarily exercise its discretion (whether by granting a stay of proceedings in England, or by restraining the prosecution of proceedings in the non-contractual forum abroad, or by such other procedural order as is appropriate in the circumstances) to secure compliance with the contractual bargain, unless the party suing in the non-contractual forum (the burden being on him) can show strong reasons for suing in that forum. I use the word “ordinarily” to recognise that where an exercise of discretion is called for there can be no absolute or inflexible rule governing that exercise, and also that a party may lose his claim to equitable relief by dilatoriness or other unconscionable conduct.”
“Where the dispute is between two contracting parties, A and B, and A sues B in a non-contractual forum, and A's claims fall within the scope of the exclusive jurisdiction clause in their contract, and the interests of other parties are not involved, effect will in all probability be given to the clause.”
“Such overwhelming or very strong reasons do not include factors of convenience that were foreseeable at the time that the contract was entered into (save in exceptional circumstances involving the interests of justice); and it is not appropriate to embark upon a standard Spiliada balancing exercise. The defendant has to point to some factor which it could not have foreseen at the time the contract was concluded. Even if there is an unforeseeable factor or a party can point to some other reason which, in the interests of justice, points to another forum, this does not automatically lead to the conclusion that the court should exercise its discretion to release a party from its contractual bargain…”
“In the nature of things for the court to exercise its jurisdiction so as not to give effect to an EJC the strong reason relied on must ordinarily go beyond a mere matter of foreseeable convenience, and extend either to some unforeseeable matter of convenience, or enter into the interests of justice itself. Even then, it cannot simply be assumed that the court will automatically exercise its discretion so as to release one party from its contractual bargain. Once the interests of justice are engaged, then factors of convenience will be relevant to the exercise by the court, of its discretion.”
“The jurisdiction clause does not say where disputes about the validity of the contract are to be determined, if this is not to be in the forum which is expressly mentioned. The default position is that such claims would have to be brought in the jurisdiction where their opponents were incorporated, wherever and however unreliable that might be, while claims for breach of contract have to be brought in England. But why, it may be asked, would any sensible businessmen have wished to agree to this? As Bingham LJ said in Ashville Investments Ltd v Elmer Contractors Ltd[1989] QB 488 , 517, one should be slow to attribute to reasonable parties an intention that there should in any foreseeable eventuality be two sets of proceedings. If the parties have confidence in their chosen jurisdiction for one purpose, why should they not have confidence in it for the other? Why, having chosen their jurisdiction for one purpose, should they leave the question which court is to have jurisdiction for the other purpose unspoken, with all the risks that this may give rise to? For them, everything is to be gained by avoiding litigation in two different jurisdictions. The same approach applies to the arbitration clause.”