“This sample was of a sheet material [approximately] 5mm thick with a density of approximately 390Kg/m³. The sheet was manufactured from a mixture of particles and chrysotile fibres and had been painted on one face. The sample provided was extremely weak and readily crumbled releasing asbestos fibres. If the material which the sample represents is of similar strength it will be easily damaged causing the release of asbestos fibres. It is recommended this material be replaced by an asbestos free substitute. Any work on this material should be in accordance with the Control of Asbestos at Work Regulations.”
“The main objective of this project is to safely rewire and replace light fittings and provide protection from Asbestos fibres during these works to all operatives and employees of British Steel. In the approach to this project 3 options are available: 1. Total Removal of the Asbestos containing ceiling on an occupied phased programme and replace with new lights and ceiling. 2. To allow ACM to remain and replace wiring/lights under controlled conditions. 3. Item 1 with a vacated building. We strongly recommend option 1 for the following reasons: (We also believe this would be the local authorities view once they are informed) a. The extensive logistics, specialist equipment and disruption would have to be repeated if the material were disturbed or refurbishment carried out at some future date. b. Employee awareness of the project, post announcement, will cause concern over any ‘dust’ found in the future. c. Due Diligence statement for any future sale would have to include a statement. d. Annual inspection checks and labelling of ACM will have to be carried out together with supporting documentation, which will be audited by the local authorities. e. Maintenance procedures will be difficult and all maintenance staff should be trained on handling the material and health monitored.”
“This contract is placed generally as your proposal 5076/1 option one. For the total removal of asbestos containing ceiling with encapsulation and labelling of over-spray, replacement suspended ceilings, complete rewire of lighting and power circuits and replacement recessed lighting to category 2 standard. All electrical work to comply with the IEE wiring regulations 16th edition 1991.”
“I was present on site when the operatives were working to the original method (cutting out the Expamet ceiling) and I remember very clearly that from the very start of the job it was apparent that the proposed method was not workable. It had been anticipated that the ceiling would cut and break relatively easily, but it did not. This meant that a very high level of heavy cutting was necessary. This caused high noise levels in parts of the building that remained in use as offices. British Steel [was] not happy with this.”
“8. Manually scrape asbestos decorative coating from ceiling. 9. Ensure all material is removed, including overspray. 10. Spray with ET10 encapsulating material on surface of ceiling, light boxes and suspect areas.”
“… The following points were made by S. Allen:- An “interesting” week had passed with some considerable problems encountered. The ceiling was found not be plaster on mesh with reinforcing rods but was a structure of 6ft x 3ft concrete panels, bolted together, suspended to ceiling and then over sprayed. This was therefore considered a structural slab on where the asbestos had been sprayed. This had caused some major problems which were:- A major change in the method of removal which caused excessive vibration on the floor and ceiling above and below due to the need to use power tools to remove and cut the slabs into easy to handle pieces. A major concern was the vibration on the ceiling of the floor below. Air testing facilities had been stretched to the limit. All readings on the floors below or anywhere had shown no significant figures. (Highest was 17, normal ambient is 8). Graham Taylor confirmed along with Steve Allen that given this exceptionally “heavy” method of removing the ceiling structure they were concerned primarily with the possible high risk of some part of a ceiling falling in an inhabited office – “a disaster waiting to happen”
“It was agreed that it was a reasonable decision to change the method from dismantling the entire “Expamet” ceiling to scraping and sealing with encapsulant considering the issues encountered on site.”
“The upper void has essentially been used as a cable tray to support the heavy fire cables. The very act of installing these cables (when pulled through the light wells) has abraded the encapsulated edges of the Expamet causing debris to drop on to the secondary suspended ceiling. The cables will have also pulled asbestos overspray from the upper void, creating the debris now seen on the secondary suspended ceiling. Virtually all visible debris lying on the upper surface of the secondary suspended ceiling tiles [is] immediately below the light wells and does not extend more than a 200mm beyond. In my view all of the debris on the suspended ceiling has been caused by these uncontrolled cable projects.”
“It was agreed that debris on the back of new suspended ceiling was likely to have occurred as a result of the uncontrolled works (with regard to asbestos considerations) within the void (specifically running cables in the upper void and pulling them through to the lower).”
“What I viewed was a job that appeared to have been properly undertaken. Those parts of the expamet ceiling that I was able to view were visibly clear of the sprayed asbestos coating, and the surface of the ceiling was encapsulated. The areas in the void above the expamet ceiling, around the lightwells, had also been encapsulated. I did observe some debris on the top of the secondary suspended ceiling. These (sic) debris were predominantly beneath the lightwells, and were of a size and composition that lead me to believe that they had come from the upper void, or possibly from the edges of the expamet ceiling, where the lightwells had been cut-out. The debris had clearly not come from the surface of the expamet ceiling which was a relatively smooth, stable and hard surface. I can readily accept that debris originating from the upper void might contain asbestos. There was certainly oversprayed asbestos within the voids. I have returned to the site on several occasions since my initial inspection, and my view has not changed. The surface of the ceiling has been thoroughly cleaned, and what residues remain have been encapsulated. There is clearly overspray which has penetrated through the numerous lightwell openings and settled on to the void above. This has also been encapsulated.”
“From my inspection in March 2009 I saw no evidence that an encapsulant with the appearance of an emulsion was applied in 1997. The majority of the surfaces that I inspected did not have a visible sealant encapsulating the remaining asbestos.” “Given what I saw in March 2009, I believe that Woods failed to complete its work to the standard that one would have expected competent professional asbestos removers in 1997. Woods’ work left asbestos in exposed and friable condition and asbestos on the surface of the expamet ceiling. If Woods applied any ET10, it did not do so properly or in sufficient quantities as I could not detect any evidence of any encapsulant in March 2009.”
“… the First Defendant and/or the Third Defendant each was in breach of its duty of care in tort in failing to exercise reasonable skill and care in removing the ACMs from the Building and in damaging the Building by leaving ACMs in a disturbed and loose condition.”
“The First Defendant failed to carry out a thorough visible inspection to ensure that all visible traces of asbestos debris was removed from the Expamet ceilings.”
“In addition, the court shall determine the following issue (if necessary): if the Claimant is entitled to damages in respect of remedial work, what remedial work would it have been reasonable for the Claimant to undertake on the basis of the case advanced by the Claimant and the Defendants prior to18 May 2009 provided that the determination of this issue shall be without prejudice to such case as the Claimant or Defendants may advance at the quantum stage.”