“2. (1) In consideration of the payment of the said sum of£150,000 hereinbefore referred to KCC covenants that it shall use the said sum for the purpose of carrying out highway improvements to the said junction between London Road and Station Road and for no other purpose. (2) The said improvements shall comprise either a new roundabout, an improvement traffic signal layout, or such other improvements as KCC may in its reasonable discretion determine. (3) KCC shall use all reasonable endeavours to commence such improvements by the31st December 1994 but shall not be liable to Everards for any failure so to do. (4) Upon commencing such works KCC will use its best endeavours to complete the same with all due diligence”
"Thirdly, I am concerned that the Council does not start any work which might backfire on us in the future. If I do not pursue a cautious approach I could see the situation where I complete work on the Station Road link without any work starting on Blue Water Park. I would then be left with two dual carriageway cul-de-sacs paid for with government grant which was for a complete link. The government would rightly question the use to which their grant had been put. The Council would be at the very least highly embarrassed and at the worst required either to complete the project out of their own funds or to refund the grant."
"You will be aware that some work has started at Station Road. This is a small advance contract doing some drainage works and removing unsuitable material. Shortly after Christmas the diversion to statutory undertakers apparatus will commence, followed in the early spring by the main roadworks contract for the roundabout on the A226, the dualling of Station Road and the roundabout north of the railway line." (e) Mr. Farmer's letter to Mr. McCreary of Bluewater Park which referred to "works starting on Phase 1 of STDR"