"Where a local planning authority considers it necessary or expedient for any actual or apprehended breach of planning control to be restrained by injunction they may apply to the court for an injunction whether or not they have exercised or are proposing to exercise any of their other powers under this part."
"The use of any land for any purpose for not more than 28 days in total for any calendar year, of which not more than 14 days in total may be for the purpose referred to in paragraph B.2, and the provision on the land of any moveable structure for the purposes of the permitted use. "
"(b) motor car and motor-cycle racing including trials of speed and practising for these activities." 5. The defendants invited my attention to a decision of a planning inspector dated15 July 2003 in relation to lands north of Donnington Park race circuit, Castle Donnington, Leicestershire. The decision is not of course binding, but is informative as to the application of the GPDO in analogous circumstances. The relevant paragraphs of the decision are in the following terms: "18. The enforcement notice specifically refers to use for motorcross racing, testing and practising in excess of 14 days in each calendar year. Of relevance to this is the fact that, under the provisions of Schedule 2, part 4, class B of the Town and Country Planning general permitted development order 1995 (GPDO), the temporary use of land is permitted for any purpose for not more than 28 days in any calendar year, of which not more than 14 days in total may be for the purposes of the holding of a market, or for motor car and motorcycle racing including trials of speed, and practising for these activities. Advice issued by the Officer of the Deputy Prime Minister indicates that the effect of the GPDO is to permit the use of land of up to 14 days per year for competitive motorsports events (in other words race events, including associated formal race practice sessions). Other temporary use of land for non-competitive motoring activity (including informal practising or training) would be permitted, together with any other temporary uses of the land, for up to 28 days in total in any calendar year. 19. In my view this distinction is highly significant. It plainly points to the materially different character, in land use terms, of motor racing activities, which are likely to generate a substantially more intensive use of land, with higher levels of noise, greater concentrations of people and greater levels of vehicular traffic movement to and from the site, compared to other forms of recreational vehicular use of land, whether or not organised on a commercial basis, which are considered to be sufficiently low key to be permissible as a temporary use of land, under the terms of the GPDO, for up to 28 days in any calendar year."
"The council considers that events witnessed in 2005 involve motorcycle racing trials of speed and/or practising for these activities and accordingly the use of Down Farm for motocross can only be undertaken for 14 days in a calendar year …"