“The Non-Domestic Renewable Heat Incentive (RHI) is a government environmental programme that provides financial incentives to increase the uptake of renewable heat by businesses, the public sector and non-profit organisations. Eligible installations receive quarterly payments over 20 years based on the amount of heat generated. The scheme covers England, Scotland, and Wales. … Businesses, public sector and non-profit organisations can apply if equipment was installed in England, Scotland or Wales on or after15 July 2009 (or later in some cases). Your installation must meet certain requirements. …”
“The Renewable Heat Incentive (RHI) will only support useful heat. It is not practical to provide an exhaustive list of all the acceptable heat uses which will be eligible. Instead, we can outline the broad principles of what we want to support: • The utilisation of useful heat; • The heat must be supplied to meet an economically justifiable heating requirement i.e. a heat load that would otherwise be met by an alternative form of heating e.g. a gas boiler; • This heat load should be an existing or new heating requirement i.e. not created artificially, purely to claim the RHI; and • Acceptable heat uses are space, water and process heating where the heat is used in fully enclosed structures.”
“RHI support will be paid on the basis of multiplying the kWhth of metered renewable heat by the relevant tariff. Having considered the concerns with heat metering – cost of meters and a possible perverse incentive to over-generate (useless) heat in order to maximise support – we now believe that these are manageable in most cases. Commercial considerations should reduce the risk of a perverse incentive to waste heat and the large-scale RHI tariffs should, in the majority of cases, be lower than the cost of corresponding input fuels (such as the cost of the biomass fuel), avoiding a perverse incentive to generate more heat than needed. … We do, however, believe that the risk of a perverse incentive to over-generate remains in the small-commercial and medium– commercial biomass segment of the tariffs. Due to the complexity of building occupancy and usage, it is not feasible to establish a suitable methodology for estimating (“deeming”) heat demand in these sectors. So, in the absence of a procedure for carrying out deeming assessments, we have adopted the suggestion raised by some stakeholders of linking the amount of energy that will be compensated with the full tariff each year to the capacity of the installation. We will apply a higher ‘tier 1’ tariff followed by a lower ‘tier 2’ tariff.”
“I have looked at the boiler house for your offices and it is feasible to develop a biomass system to supply heat. The other two workshops, I will have to revisit on Tuesday [22 September] to survey and will get a quotation back to you.”
“I have spoken with our engineer who says the size of the boilers is 3m btu [British Thermal Units] each …”
“Thank you for considering JBP Industries Ltd for the supply of your biomass heating system. We are pleased to enclose our proposal based on our combined heating solutions for your consideration.”
“Having discussed your requirements in detail and information gathered from our survey and the drawings provided we outline here our energy solution that best suits your requirements. 1.1 Heating requirements Requirement ▪ It is proposed to install a new Fröling biomass heating system to generate heat on site to heat 3 separate industrial units. ▪ The new biomass heating system and heat distribution network is to provide for the great majority of the heating requirements for the site in order to reduce fossil fuelled heating costs and CO2 emissions and provide a sensible economic investment under the RHI. ▪ The system is to be fuelled from wood chip or pellets purchased and delivered to site, to support clean combustion. ▪ The existing fossil fuel boilers currently installed within the Main factory unit will be removed from the boiler room to make way for the new biomass system. The warehouse space heaters will stay as a back-up heat supply if required & the offices / day care centre old gas boilers will be removed. These properties will be connected by heat mains from the central boiler house which will provide the primary heat supply to each industrial unit. Heat loads ▪ The system is required to heat a number of properties, with loads estimated by JBP Industries Ltd as follows: ▪ We estimate the total design heat load as follows ▪ Main Factory c.1000 kw this is based on the existing gas boilers that are 850kw each ▪ Warehouse c. 250kw system utilising warm air ducting for the heating providing a constant background heat ▪ Offices / day care centre c.100kw load looking at the old systems and the size of the properties to heat 1.2 Boiler and thermal store sizing ▪ To ensure that the great majority of the heating load is met by the biomass boiler and to minimise start/stop cycles and ensure high seasonal boiler efficiency under variable loads we propose the installation of an (sic) 20,000 litre thermal store for the main factory, 5000 litres for the warehouse & 3000 litres for the offices / day care centre. ▪ This combination of automatic biomass boiler plant and thermal storage is expected to provide for 90%+ of the annual heating requirements under normal conditions. Please note that prior to detailed design JBP Industries Ltd provides no warranty as to the extent to which the boiler plant proposed will meet the heating requirements of the site or the level of fuel consumption that may be expected. 1.3 Installation outline Energy Centre ▪ Our proposal is based upon 1 x 1000kw system made up of two 500kw Froling TM boilers, 1 x 250kw Froling TX boiler & 1 x 100kw system Froling T4 ▪ The boiler and thermal store will be installed within the existing boiler room (large industrial unit) new energy centre for the other two buildings ▪ Wood chip / pellets will be stored in an adjacent purpose built fuel pellet silo and connected directly to the boiler plant.”
“RHI Non Domestic scheme payments Assumes 9 hr/day at peak demand and a 1MW boiler The current tariff for Biomass medium scale systems is 5.14p/kW as agreed by DEC The total project cost is estimated to be£586,517 therefore we would estimate an average return on investment of 5.76 years. The RHI payments are assured for 20 years under current scheme rules. Once approved you are contracted at that rate for the life of the scheme.”
“I have attached a breakdown for the Biomass systems for the three Hydro buildings at the Stradey Business Centre. Please see attached, the figures show a payback for the scheme in under five and a half years.”
“Having discussed your requirements in detail and information gathered from our survey and the drawings provided we outline here our energy solution that best suits your requirements. 1.1 Heating requirements Requirement ▪ It is proposed to install a new Froling biomass heating system to generate heat on site to heat 2 large but separateindustrial units (Hydro & the opposite unit) ▪ The new biomass heating system and heat distribution network is to provide for the great majority of the heating requirements for the site in order to reduce fossil fuelled heating costs and CO2 emissions and provide a sensible economic investment under the RHI. ▪ The system is to be fuelled from wood chip or pellets purchased and delivered to site, to support clean combustion. ▪ The existing fossil fuel boilers currently installed within the Main factory unit will be removed from the boiler room to make way for the new biomass system. The warehouse space heaters will stay as a back-up heat supply if required & the offices / day care centre old gas boilers will be removed. These properties will be connected by heat mains from the central boiler house which will provide the primary heat supply to each industrial unit. Heat loads ▪ The system is required to heat a number of properties, with loads estimated by JBP Industries Ltd as follows: ▪ We estimate the total design heat load as follows ▪ Hydro Factory & opposite unit c.998 kw this is based on theexisting gas boilers that are 330kw each total 660kw andnew unit approximately 300kw 1.2 Boiler and thermal store sizing ▪ To ensure that the great majority of the heating load is met by the biomass boiler and to minimise start/stop cycles and ensure high seasonal boiler efficiency under variable loads we propose the installation of a 30,000 litre thermal store forthe main factory. ▪ This combination of automatic biomass boiler plant and thermal storage is expected to provide 90%+ of the annual heating requirements under normal conditions. 1.3 Installation outline Energy Centre ▪ Our proposal is based upon 1 x 998kw system made up oftwo 499kw Froling TM boilers ▪ The boiler and thermal store will be installed within the existing boiler room (large industrial unit) new energy centre for the other two buildings ▪ Wood chip / pellets will be stored in an adjacent purpose built fuel pellet silo and connected directly to the boiler plant.”
“RHI Non Domestic scheme payments Assumes 9 hr/day at peak demand and a 998kw boiler The current tariff for Biomass medium scale systems is 5.14p/kW as agreed by DEC The total project cost is estimated to be£364,620 therefore we would estimate an average return on investment of 2.5 years. The RHI payments are assured for 20 years under current scheme rules. Once approved you are contracted at that rate for the life of the scheme.”
“Warning: This tool and all estimates are provided by JBP Industries Ltd without any warranty or guarantees. The user employs this tool at their own risk. Fossil fuel prices are indicative only and are highly variable in practice; always check competing fuel prices.”
“Please note that this is very much an estimate and at this stage no historic fuel use and cost data is available to support boiler utilisation level assumption in particular. As such this estimate is for information Biosol Renewables UK Ltd / JBP Industries cannot provide guarantee as to the accuracy of these estimates and accept no financial liability for any error in this respect. These figures are based on the minimum usage with the boilers running at a 20% full load factor. This can double or even treble dependant (sic) on running demand and system requirements We strongly advise a third party assessment is made as part of your due diligence for the project.”
“We would typically expect the programme of works to be approximately as follows. 1. Biomass system design: 2 weeks, from order confirmation 2. Manufacture boiler: 5-7 weeks, TM 500 from design sign off 3. Manufacture Boiler 4-6 weeks, TX 250 from design sign off 4. Freight: 1-2 weeks, dependant (sic) on customs clearance 5. Planning: usually 4-6 weeks, client to make application 6. Construction of Energy Centre: 4-6 weeks, dependant on design 7. Boiler and fuel feed site assembly: 2 weeks, per unit from possession of clear site 8. Pipe and chimney installation: 3-4 weeks, per unit subject to contractor timings 9. Heat mains and interface works: TBC concurrent with energy centre 10. Electrical installation: 3 weeks, following completion of pipe work 11. Commissioning: 7 days, following completion of all other works Following order confirmation a full contract programme will be developed and agreed with the client.”
“1 unit at 250kW boiler for offices will give a minimum return of£52,075 taking into account fuel costs. 22 units at 500kW boiler for commercial units will give a return of£102,504.90 [I remark: this is the figure for each boiler] taking into account fuel costs. 1. unit at 998kW boiler for industrial unit will give a return of£204,598.52 taking into account fuel costs. [I remark: each of these figures represents the total of RHI payments less the total projected fuel costs.] This project will give a return based on above figures of£2,511,785.00 inclusive of fuel costs. If Gas is used as a fuel in any of these commercial units i.e. NHS buildings or other associated buildings the returns would be for example the NHS Building:£255,688.90 . Over the 20 year period there will be a return of£50,235,700.00 for a capital expenditure of£3,560,000 inclusive of fuel costs.”
“We need to push on the financials for biomass plant asap—let’s discuss Thursday at the board meeting.”
“All looks positive. We should be in a position by the end of next week to place an order. My understanding is six weeks lead time.”
“I have put in a call to graham to see what he has done on the system re pricing and getting other quotes.”
“500kw boiler x 1314 [burn hours] x 5.18p [tier 1 RHI payments] =£34,032.60 500kw x 7440 [burn hours] x 2.24p [tier 2 RHI payments] =£83,328.00 These returns would be doubled for a megawatt boiler system and with cheaper fuel then returns would also increase.”
“[T]hese [returns] are solely based on the 1314 burn hours tier 1 of which equates to 3.5 hours heating per day. It therefore allows for a further 7440 burn hours at tier 2 = 2.24p which could give a greater return especially from let out units. i.e. NHS and other units that would use heating 24/7 would be a massive income.”
“We would typically expect the programme of works to be approximately as follows. 1. Biomass system design: 2 weeks, from order confirmation 2. Manufacture boiler: 5-7 weeks, TM 500 from design sign off 3. Freight: 1-2 weeks, dependant (sic) on customs clearance 4. Planning: usually 4-6 weeks, client to make application 5. Removal of existing redundant system: 2-3 weeks, dependant on working site hrs 6. Boiler and fuel feed site assembly: 2 weeks, per unit from possession of clear site 7. Pipe and chimney installation: 3-4 weeks, per unit subject to contractor timings 8. Heat mains and interface works: TBC concurrent with energy centre [This item previously tied in with the earlier item 6, ‘Construction of Energy Centre’, which was now omitted from the schedule.] 9. Electrical installation: 3 weeks, following completion of pipe work 10. Commissioning: 7 days, following completion of all other works Following order confirmation a full contract programme will be developed and agreed with the client.”
“You quoted labour and materials to extract the boilers and generators.”
“the decommissioning was removed from the contract and R&A where (sic) supposed to carry out that works, as stated in good faith Biosol have stepped in to carry out the decommissioning works …”
“Decommissioning of the original boiler in April 2016 is£25,000 (has not been paid). Taken out of original quotation.”
“Having discussed your requirements in detail and information gathered from our survey and the drawings provided we outline here our energy solution that best suits your requirements. 1.1 Heating requirements Requirement ▪ It is proposed to install new Froling biomass heating system to generate heat on site to heat large but separate industrial units (as highlighted) ▪ The new biomass heating system and heat distribution network is to provide the heating requirements for the site in order to reduce fossil fuelled heating costs and CO2 emissions and provide a sensible economic investment under the RHI. ▪ The system is fuelled from wood chip or pellets purchased and delivered to site, to support clean combustion. ▪ The existing fossil fuel boilers currently installed (sic). [It seems that text such as that contained in corresponding positions within earlier Proposals has been omitted by mistake.] The warehouse space heaters will stay as a back-up heat supply if required & the offices / day care centre old gas boilers will be removed. These properties will be connected by heat mains from a plant room which will provide the primary heat supply to each industrial unit. Heat loads ▪ The system is required to heat individual properties, with loads estimated by JBP Industries Ltd as follows: ▪ We estimate the total design heat load as follows ▪ Factory units c.500 kw this is based on the load required to heat the units to a constant temperature regulated by customer. 1.2 Boiler and thermal store sizing ▪ To ensure that the heating load is met by the biomass boiler and to minimise start/stop cycles and ensure high seasonal boiler efficiency under variable loads we propose the installation of a 10,000 litre thermal store per unit. ▪ This combination of automatic biomass boiler plant and thermal storage is expected to provide 90%+ of the annual heating requirements under normal conditions. 1.3 Installation outline Energy Centre ▪ Our proposal is based upon 22 x 500kw system made up of Froling TM boilers. ▪ The boiler and thermal store will be installed within containerised units. ▪ Wood chip / pellets will be stored in an adjacent purpose built fuel pellet silo and connected directly to the boiler plant.”
“Joint Venture Biosol renewables UK LTD and R and Aproperties It is proposed that an agreement is entered that the maintenance and contract for running the proposed site is conducted by Biosol Renewables and as a result Biosol renewable (sic) will subsidise the cost of the supply of wood chip due to RHI subsidised production and pass this saving onto R and A properties (sic) in exchange for an agreed term of contract. The following proposed statement of return is an indication of the returns achievable if the running of the proposed site is efficient and effectively run using all available resources. In addition, supply of heat to currently unheated units could be charged at the current rate of 4.25p which will enhance the main returns. In addition under the Energy act (sic) 2011 which comes into force in April 2018, commercially let properties will have to achieve a minimum performance standard (MEPS) in order to be let ...”
“Over a twenty year period there is a potential return of£42,845,547.40 from installing 22 x 500kw boilers and 1 x 250[kw] boiler. This does not account for savings on gas.”
“Biosol Renewables UK Ltd have agreed a project to install 10 Biomass systems at R&A Properties. First two Boilers installed and commissioned by22/06/2017 (sic). A meeting between both parties to discuss the development of a further 8 Boilers and the financial outcome of the project, details as follows. Discussed and agreed 1. R&A Properties would receive a minimum RHI return of£650,000 per annum from the installation of 10 biomass systems. 2. Biosol to manage the site would receive£120,000 for Fuel and maintenance of all 10 biomass projects. 3. All 10 Boilers to be installed and commissioned by31st March 2017 . 4. The Mapping of the site was discussed and Boilers locations agreed. Points 1, 2, 3 and 4 agreed with Neil Bundock and Nigel Lovering / David Pickering. Kind regards Neil Bundock”
“amendment as discussed”
“Currently we have received delivery of 3 (three) SWEBO ECOFIRE 499 KW Boilers and we need to understand for the employment of labour implemented by BIOSOL to deliver this project by the31st March 2017 , that this project is signed off as soon as possible so we don’t have any delays in reaching these targets. Can we understand that this project can be signed off with Premier asset finance as soon as possible please. Serial Numbers: For SWEBO ECOFIRE 499 KW Boilers on Site … [three serial numbers were set out] 1. Purchase the next 3 (three) Boilers 2. Maintain cash flow for the project. On site tomorrow to discuss 9am.”
“We have installed at your property a multiple 500kw Biomass renewable energy system. In consideration of our installing the renewable energy system under the specific term of doing so, you agree that for a period of 3 years from the date of completion of the installation you will and will procure that any successors in title will:- 1. Require and allow us to carry out all maintenance and any necessary repairs to the said Biomass renewable energy system at such intervals and at such cost as we shall advise for a period of 3 years. 2. Not permit anyone other than us to undertake maintenance or repairs to the Biomass renewable energy system. 3. Purchase from us all wood chip required to supply a 500kw boiler for the purposes of maintaining its output at maximum capacity for a period of 3 years where applicable. 4. Not to purchase or acquire by any means wood chip or other fuel from any source other than us. This letter agreement may be amended only by written agreement signed by or on behalf [of] you and us. This letter agreement is governed by English law and the English Courts will have jurisdiction in the event of any dispute. Please sign the enclosed copy of this letter to signify your acceptance of the terms.”
“as a whole this is not a problem, however it has become apparent that members of your staff are accessing the running of the systems of the boilers and this now renders the warranty to the boilers void.”
“The TM 500 boiler has been approved for use with Grade A and Grade B waste wood, which generally do not contain glues and plastic. Should you require further details as to the specification of Grade A and Grade B wood, please refer to the British Standard document BSI PAS 111 (see attached link) …”
“Sorry but I will have to cancel my wood chip order.”
“All boilers were down this morning with numerous complaints from tenants, we have fuel here but it appears that they were not filled enough on Friday. Also, the pile of contaminated wood chip in building 65 and under the canopy needs to be removed as we have had an inspector visit and he has said that it cannot touch the virgin wood chip. Please advise.”
“Apologies for delay, and not aware that boilers were down this morning. Will establish cause and get back to you. With regards Grade A fuel in 65 I will find out and arrange for it to be moved.”
“I have described the wood waste as ‘contaminated’ due to there being evidence that it contains metal, glass and plastic debris throughout. The material may have been processed in accordance with the PAS111 code however it is not suitable for use in your biomass boilers. Firstly it is likely to result in damage to the boilers and secondly you would require an environmental permit to burn the material, which you do not have. … If you wish to remove the material from site, which I strongly recommend, it would have to be removed as a waste and therefore would have to be transported in accordance with the regulations … I have tried to find a route for you to pass the material on but as yet have been unsuccessful. My suggested use for animal bedding is unlikely to be an option due to the contaminants. The material could be screened to remove metal but this still leaves glass, plastic and any other non-metallic contaminant which are likely to mean the material is not suitable. If I hear of any potential outlets in the near future I will let you know.”
“I will forward to Nigel [Lovering] today the name address and BSL[Biomass Suppliers List] numbers of the suppliers of the Grade A fuel in 65 as discussed.”
“Thank you for our earlier conversation and the clarity that you have shed on the current situation. Just to confirm that fuel supplied to R and A properties has been procured from legitimate vendors accredited by Ofgem on the Biomass suppliers list, reference numbers … To add as per conversation the internal wood chip will be removed from site over the forthcoming weeks and delivered to Western Wood energy Biomass 1 at Margam for use. The wood chip housed externally in the lean to will be collected by ourselves and conveyed by tractor and trailer to my home address for use for animal bedding on the farm.”
“I appreciate that you have relevant paperwork and certificates for the material, but as explained, the whole accreditation and grading protocols are under review at national UK level due to inconsistencies in the interpretation of the regulations by various stakeholders.”
“The boilers have been operating on fuel that they are not designed for nor are permitted to use as per the Environment Agency guidelines and manufacturer’s instructions. There is a good likelihood that significant wear or damage has occurred to them as a result of the incorrect fuel used and in addition to that warranties will have been invalidated if no written consent has been provided directly from the manufacturer for allowance of that fuel.”
“Due to the current financial situation we are unable to supply you with the priority response that you have become accustomed to.”
“Finally, it perhaps goes without saying that our client terminates is (sic) contractual relations with your client immediately. Our client has lost all confidence in your client. It is clear that the installed system is not of a satisfactory quality and it appears self-evident that your client is not capable of remediation.”
“Where the seller sells goods in the course of a business and the buyer, expressly or by implication, makes known— (a) to the seller … any particular purpose for which the goods are being bought, there is an implied term that the goods supplied under the contract are reasonably fit for that purpose, whether or not that is a purpose for which such goods are commonly supplied, except where the circumstances show that the buyer does not rely, or that it is unreasonable for him to rely, on the skill or judgment of the seller …”
“(4) Subsection (5) below applies where, under a relevant contract for the transfer of goods, the transferor transfers the property in goods in the course of a business and the transferee, expressly or by implication, makes known— (a) to the transferor … any particular purpose for which the goods are being acquired. (5) In that case there is … an implied condition that the goods supplied under the contract are reasonably fit for that purpose, whether or not that is a purpose for which such goods are commonly supplied.”
“The most commonly used measure of biomass boiler efficiency is the direct efficiency, defined as: Direct efficiency = Heat output from the biomass boiler ÷ Energy input to the biomass boiler”
“The performance of a biomass heating system can be measured by its efficiency in converting the energy stored in wood fuel into useful heat at the point of use. The point of use is defined as the place where the heat enters the heating system - generally in an existing plant room and often at the end of large runs of district heating pipes. The three main measurable factors that determine the efficiency of biomass-fired systems are: • Boiler/combustion related losses • Plant room losses • Outside the plant room losses (including district heating networks).”
“The capital cost of a biomass boiler system is, typically, ten times that of a fossil fuelled boiler system. Furthermore, the low turndown ratio of biomass boilers, typically between 2:1 and 3.5:1, means that most biomass systems will be significantly mismatched with respect to summer loads. Hence, it is very important not to oversize a biomass boiler system.”
“A crucial trade-off is that between the capital cost of a biomass boiler and thermal storage against the annual percentage of energy obtainable from biomass.”
“All of the biomass systems installed are oversized for the application in which they have been installed. The effect of oversizing is to cause cycling, where the boiler must turn on and off frequently rather than operating for continuous periods. Such frequent cycling causes damage to the boilers” (defence and counterclaim, para 40(1)). R&A say that the term in question was implied bysection 13 of the Supply of Goods and Services Act 1982 : “In a relevant contract for the supply of a service where the supplier is acting in the course of a business, there is an implied term that the supplier will carry out the service with reasonable care and skill.”
“[The purpose of the document is] to enable the competent performance-in-use of a wide variety of biomass boiler installations by providing a detailed design process and technical guidance. It is based on many years’ worth of accumulated experience in the field by some of the UK’s most experienced biomass heating system designers, and from detailed analysis of biomass systems in use. It has been written to … [h]elp designers select the most appropriate biomass system for a given application.”
“Buffer vessel: Used to improve biomass system efficiency by capturing residual heat from a biomass boiler on shutdown, and to provide start and stop signals to automatic ignition boilers to ensure efficient and stable boiler operation” “Thermal store: Used to enable a relatively small boiler to provide a large proportion of the annual energy demand from biomass. Typically a thermal store is much larger than a buffer vessel and often incorporates the functions of a buffer vessel within it. A thermal store also provides start and stop signals to automatic ignition boilers to ensure efficient and stable boiler operation.”
“A biomass boiler configured with a buffer vessel is unable to meet a load greater than the output of the boiler. If the system pump was to be sized for a duty greater than the biomass boiler output, once the buffer vessel has been depleted flow temperature dilution will occur. The buffer vessel would fill with water at system return temperature and cooler water from the buffer vessel would mix with the flow from the biomass boiler resulting in a reduced system flow temperature. When using a biomass boiler and buffer vessel configuration, either the biomass boiler must be sized to provide 100% of the load (a practice not advocated in this Applications Manual) or an auxiliary, usually fossil fuel, boiler is required to meet loads greater than can be supplied by the biomass boiler alone.” “The use of thermal stores is strongly recommended. Thermal stores: allow biomass boilers to operate continuously for long periods; improve the operating efficiency and utilisation factor of biomass boilers; can incorporate a buffer vessel at the bottom of a thermal store if the biomass boiler ‘stop’ temperature sensor is appropriately positioned; enable a biomass boiler to be reduced in size while meeting up to 100% of the load from biomass at external temperatures down to the design winter temperature.”
“The capital cost of a biomass boiler system is, typically, ten times that of a fossil fuelled boiler system. Furthermore, the low turndown ratio of biomass boilers, typically between 2:1 and 3.5:1, means that most biomass systems will be significantly mismatched with respect to summer loads. Hence, it is very important not to oversize a biomass boiler system. The key principle of sizing a biomass boiler and thermal store combination is to design the system using a small boiler in relation to the peak load while operating it continuously, and hence at high efficiency, to charge a thermal store: energy is stored overnight to meet peak loads the following day. The extent to which the boiler size can be reduced in relation to peak load is wholly dependent on the shape and duration of the daily load profile. A thermal store, in combination with a biomass boiler, should be designed to meet the desired percentage of energy from biomass (when an auxiliary boiler is incorporated) or 100% of the annual energy requirement if a biomass system only is to be installed. A thermal store collects energy from the biomass boiler when the demand from the load is less than the boiler’s output and releases it, in combination with the biomass boiler, when the load demand is greater than the boiler’s output it served as a peak lopping and load smoothing device.”
“It is self-evident that a small biomass boiler in combination with a large thermal store could meet the demand shown in figure 6.1 (operating overnight to charge the thermal store) while there is little scope for using a thermal store with the relatively flat profile of a continuously heated building which would require a boiler sized at the average load of the profile in Figure 6.2.”
“For a system using a thermal store a biomass boiler rated at 30% of the peak load is likely to be able to supply 95% or more of the annual energy from biomass”
“[F]or many typical existing buildings, a biomass boiler rated at 30% of peak load with a thermal store and auxiliary boiler(s) is probably not too far from the optimum solution and should achieve efficient biomass boiler operation and enable the system to be effectively controlled.”
“imperfect knowledge of the building as built and consequent use of assumptions (e.g. thermal/optical properties of materials, build quality and associated leakage, equipment used and their characteristics, etc.)”
“Design margins are intended to make provision for uncertainties inherent in determining peak heating demand. … Where design margins are included to allow for such uncertainties, these are often cumulative. In addition, plant and equipment will inevitably be selected as ‘the next size up’. This can result in unnecessary oversizing and as a consequence: increased capital costs; increased plant space requirements; reduced efficiency and increased running costs. In their investigation of oversizing of HVAC systems in existing buildings in the UK, BSRIA (Crozier, 2000) found that 80% of heating systems were oversized, some by as much as 400%, with oversizing by 50% to 100% common. Design margins must therefore be used with caution. Nevertheless, the designer must be able to deal appropriately with the risk of heating systems not performing as required. A key uncertainty in the determination of peak heating demand is building performance, particularly for refurbishment projects. This applies to both U-values and infiltration rates. In many cases when dealing with existing buildings, there will be little or no documentary evidence of U-values. The actual U-values will depend upon the standard of construction and this can vary throughout the building. In particular, insulation may be partially missing or damaged. … Where there are uncertainties regarding design criteria and future requirements, these should be agreed with the client and the implications made clear in terms of risk and increased costs. The agreed design criteria should then be used to determine heating demand. … CIBSE made the following recommendations in their research paper: • design margins should not be added unless there are valid design reasons • where design margins are added, they should be clearly identified within the calculations • where appropriate, design margins should be approved by the client • avoid cumulative design margins • specify assumptions made as part of the design • specify the operating limits of the design” uncertainties inherent in determining peak heating demand. … • design margins should not be added unless there are valid design reasons • where design margins are added, they should be clearly identified within the calculations • where appropriate, design margins should be approved by the client • avoid cumulative design margins • specify assumptions made as part of the design • specify the operating limits of the design”
“In non-domestic buildings, it is common practice to install multiple heat generators. It is also common practice to provide additional capacity to allow for breakdown or maintenance. … The choice of how much, if any, additional capacity to install depends upon the estimated risk of sufficient heat not being available and the seriousness of the consequences. In reality, the calculated peak heating demand rarely occurs as: for most of the time, actual outdoors temperatures are greater than the design value; there are likely to be some internal heat gains; design margins may have been incorporated. As a result, for most of the heating season full heating capacity will not be required to achieve indoor design temperature. The consequences of failing to achieve indoor design temperature will depend upon the building use and the degree of underheating. … Multiple heat generators, properly controlled, can lead to improvements in overall seasonal efficiency. In some cases, it may be advantageous to install different sizes of heat generator, particularly if the heating load during summer or weekends perhaps is very small so that the smallest of the heat generators can meet demand at such times. … The choice of how many heat generators and of what output ideally requires a careful assessment by the designer of risk, capital costs and energy savings.”
“36. It is known in the biomass industry that for biomass installations to work effectively they should not be oversized. In simple terms an oversized biomass boiler has a maximum heat output that is much greater than the maximum heat demand. To work effectively biomass boiler[s] should be undersized, that is to say their heat output should be equal to or slightly less than the maximum heat demand. This is because unlike traditional heating technologies biomass boilers are designed to run for long periods and at high output[,] only turning on and off infrequently. At full output a continuously running biomass boiler is at its most efficient, it is much less efficient during periods of start-up and shut down. These startup and shut down periods are mechanically intensive. Excessive start-ups and shutdowns will decrease the efficiency, increase pollutant emissions and increase wear and tear on the firing system and ancillary equipment. These in turn can create error faults … This is why most biomass boilers include accumulators (thermal stores) to increase thermal mass to reduce cycling.” “38. … Whereas a gas or oil heating boiler will turn on and off frequently without much impact, a biomass boiler can’t turn on and off quickly due to the mass of fuel required to be ignited or burnt out. Gas boilers typically take less than 15 seconds to start up and shut down. Therefore, to operate as designed biomass boilers must run for extended periods with very few shutdowns. If they are oversized they will switch on and off quickly in an operation called boiler cycling.” “39. … [A]ll boilers cycle to a degree but the skill of the biomass system designer is to minimise this cycling. This is done by correctly matching the boiler to the heating load.”
“RHI income depends on measured heat use and not on installed boiler capacity and so there would not be benefit to R&A Properties from installation of more boiler capacity than needed to meet heat demand. Supply of boilers beyond the needed capacity contributes to cost of installation without a commensurate benefit to the purchaser.”
“Increasing biomass boiler size will not increase annual demand and will therefore not increase the annual RHI income.”
“There is no risk to oversizing oil or gas boilers. There is a large risk to oversizing biomass boilers. Therefore you should make your own best estimate as to what you think the heat loss coefficient of that building should be, built up from first principles, and not add the 20% uncertainty factor that Mr Crawford does, but then reduce that by an appropriate factor to 70% or 80% or whatever the client might find suitable; and then either the client accepts the modest amount of underheating, or you use a back-up gas boiler for those few days a year where the biomass boiler maybe can’t quite fulfil its requirements.”
“Q. The advice given in this document is that where you have a continuously heat-heated building, you will require a boiler size at the average load of the profile, correct? A. If you were going to heat the premises entirely with biomass and you were going to pay the additional capital cost, yes. … Q. So you reject the advice given by CIBSE in section 6.1, do you? A. I would much prefer to interpret that in terms of page 507, Step 6. And I would also say that … there should be a gas boiler there or an oil boiler there, if so required, to make up the additional shortfall on those very days. … Because biomass boilers are typically 10 times per kilowatt more expensive than oil or gas boilers, I would have recommended … maybe a 50 % biomass boiler and t o retain one of the existing gas boilers. I could have then worked my biomass boiler hard, burnt 99-95% of the energy on the biomass boiler, and retained the gas boiler as back-up when the biomass boiler stops and for topping up on the coldest days.”
“What I’m contending is that that ‘if’ is not reasonable. … [T]here are risks associated with oversizing oil or gas boilers. Therefore biomass boilers should not be sized to provide 100% of the load. They should be undersized using a support oil or gas boiler, if you’re really fussed about those few days that it’s cold and/or if the biomass is going to break down.”
“Q. So, your theoretical boiler would be rated at 275 kilowatts. A. Yeah. Well, you’d pick the next one up that was available, yes: 275 kilowatts, yes. Q. And my point is, Mr Crowther, that if you look at the amount of heat that was generated by the boilers for those buildings in certain quarters, it simply would not be possible to generate the same amount of heat with a 275 kilowatt boiler. Is that a calculation you have considered making? A. No, because the whole premise of my, of the report, was that the internal temperature should be at 15 degrees Centigrade or in this instance, 21 degrees Centigrade. The boilers were operated in accordance with, if you like, with the normal sort of strategy that would be expected to provide tenants with minimum cost and with genuine fuel effi – and with building, and with total concept fuel efficiency. Q. I see. And as you say, that is the assumption that underpins your report? A. Yes.”
“Q. Now, would you agree that it would appear that the boilers at Stradey Park had been used in a way to maximise the payments that the defendants receive under the Renewable Heat Incentive? A. I really do not know sufficient about the facts of what is going on on that site to be able to comment – to answer that. I cannot sit here under oath and answer that question. Q. Was it something you have considered, Mr Crowther? Bearing in mind that you are under oath as you say. A. I must have considered it because it is something we have frequently come across as part of the 67 boiler houses that we inspected for BEIS. Q. And what is it you frequently come across? A. That site owners contrive to overheat their buildings to maximise RHI payments. Q. And having seen those figures that we saw this morning in respect of the NHS building, that is what has happened here, is it not, Mr Crowther? A. I, I have been hired as an expert witness here to comment on the technical aspects of the design that I have seen it. I really do not know what the particular designs and operating strategy of those boilers are. I do know what they are using building 3 for. I really – under oath I cannot answer that question. But clearly I have thought of it and I am aware of it. Q. You are being rather reticent, are you not, Mr Crowther? You have considered this and you have formed the view that the boilers were the size to maximise the financial returns, have you not? A. I have seen that done on other sites. I have got no evidence that that has been done at R&A Properties. I do not think that is directly relevant to the issue in hand, that I thought was the oversize – was the optimum sizing of these boilers for their original and declared historical use. I still believe that smaller boilers would have performed better when fed with the correct woodchip etc. The current operational sense of those boilers is, I think, outwith the original remit given me to by the court.”
“Q. Well, Mr Crowther, one thing that I suggest you do know is that the faults are not attributable to oversizing, correct? A. No, sorry - oh, no, they’re not directly related to oversizing, correct. Q. No, that’s all that I was asking you, Mr Crowther, because your report says evidence of oversizing can be seen in the fault logs and I’m suggesting that’s not correct. A. OK. Q. Do you agree? A. I would – oversizing leads to more cycling, leads to overheating. But I agree that it’s a more complicated chain than I wrote down in here, yes. Q. Well, no, Mr Crowther, we’re not going to – that’s not quite right because you haven’t calculated the actual performance of the boilers (we’ve established that) and so you don’t know whether or not they are oversized for their actual use, do you? A. Yes, I agree, yes.”
“The first step in the design process is to assess the likely heat loss from a building the design winter day. This is achieved by using the building dimensions to work out surface areas of the various components (roof, walls, floor, rooflights, doors etc). To those areas are then applied what are known as U-values and the difference in temperature between the external environment and internal environment. The U-values vary from component to component and define the rate at which heat passes through the component in the direction of the temperature gradient (i.e. inside to outside). … By definition all of the figures used in this calculation contain a margin of error for a number of reasons. The final result therefore contains the summation of these errors. Therefore, to mitigate this risk, as with the design of any system, a margin [also referred to as a ‘margin of uncertainty’] is added. … In-house, we use margins of 15-20% (i.e. multiplication factors of 1.15 – 1.2) depending on how reliable we perceive the input data to be. …” “[T]he occupancy profile of most buildings includes the fact that the heating is switched off when the building is unoccupied and the heating switched back on at a predetermined time period before the occupants are due to arrive. During the period following switch-on, the instantaneous demand from the heating system can be much higher than the demand required to keep the building warm once it is already up to temperature (i.e. the steady state losses). This additional demand is called the Cold Start Margin … Failure to include this value will result in the building taking a long time to heat up and therefore not meet the design criteria. … I have proposed the use of a Cold Start Margin of 1.2, which is at the conservative end of the range advised [by CIBSE AM:15]. Using a larger margin would result in an even higher buffer vessel volume.” “Once the steady state heat loss (including margin for uncertainty) and cold start margin have been established, the optimum boiler capacity and buffer vessel combination can be determined. For any combination of boiler capacity and buffer vessel volume to be successful, they must be able to provide both the start-up demand and the steady state demand for the duration of the occupied period. Failure to meet either will result in the heating system being undersized for the building. Too small a boiler can result in too larger a buffer vessel volume and vice versa. Furthermore, there is not an infinite range of boiler capacities or buffer vessel volumes available and therefore the choices made for each are constrained by what products the market has to offer. … [T]he optimum boiler/buffer combination must be selected pragmatically.”
“If the buildings prove to be continuously heated then his [Mr Crawford’s] opinion must change and the Cold Start Margin [be] removed from his analysis. For the avoidance of doubt, the Cold Start Margin is largely, but not completely, built into the buffer vessels rather than the capacity of the boiler itself in biomass heating systems.”
“Mr Crowther appears to believe that the undersized boiler, whilst it may operate more efficiently as a result, adequately discharges the client’s requirements for a heating system. However, for this to be true, one would require to impose one of the two following caveats: 1) Either the client must contractually sign up to an undersized heating system inevitably leading to underheated buildings during the winter period; or 2) [One must] Provide a supplementary gas- or oil-fired boiler to make up the deliberate shortfall.”
“More so recently, but, yes, in my background.”
“The reason to apply the discount is that the money spent on bringing the boiler up from 80% (or lower percentage) of peak load to 100% of peak load is not well spent. At best, it will provide a marginal benefit (i.e. ensuring the property is not under-heated for those short periods when the temperature is at its lowest). If this were a problem, which usually it would not be, it would be best solved by the installation of a small, cheap, supplemental fossil-fuel boiler.”
“The extent to which the boiler size can be reduced in relation to peak load is wholly dependent on the shape and duration of the daily load profile. A thermal store, in combination with a biomass boiler, should be designed to meet the desired percentage of energy from biomass (when an auxiliary boiler is incorporated) or 100% of the annual energy requirement if a biomass system only is to be installed.” “[T]here is little scope for using a thermal store with the relatively flat profile of a continuously heated building which would require a boiler sized at the average load of the profile in Figure 6.2.” “If 100% of the annual energy is required from biomass, the boiler/thermal store must be able to supply 100% of the energy on the design winter day.”
“The Partners’ essential complaint is that they bought more boilers than they needed. The number of boilers they needed was 6. The best evidence of that is that, having taken advice, the Partners have decommissioned 4 of the boilers Biosol sold to them.”
“For example, there is no credible analysis of relative capital costs or the impact of RHI.”
“Generally such an installation (on site work) should take 6 to 10 weeks depending upon the building work, electrics and cutting into the existing system.”
“Points of agreement It is agreed that installing multiple boilers simultaneously with overlapping work fronts makes it very difficult to ascertain whether the design, installation and commissioning period for any given boiler was appropriate or not. Points of disagreement Mr Crowther: Mr Crowther still believes some H&V contractors could have scheduled the work in a parallel rather than sequential fashion and achieved faster installation rates. Mr Crawford: Mr Crowther agreed to having insufficient information regarding actual work fronts during the construction period in order to determine whether any were carried out in parallel or any additional items could have been carried out in parallel. Therefore, it is not clear upon which basis Mr Crowther claims that the construction could have been shorter.”
“In early 2017 [the date in fact was November 2016: see above] Biosol instructed me to re-commission boilers 1 and 2 in order that they could burn the contaminated fuel that it was supplying into the boilers. The contaminated fuel was not burning properly in the boilers and was causing them to break down. I attended at the site and recommissioned boilers 1 and 2 to burn the contaminated fuel that Biosol was supplying.”
“I acknowledge that a small portion of the fuel delivered to R&A from [KPS] was not of the standard required. However, this was stored away from the fuel being used in the boilers and fenced off. The issue of a substandard load from Brighton was brought up with the supplier and the issue was swiftly rectified. The supplier agreed not to charge for the substandard fuel.”
“The balance of the contract price must be paid within 7 days of completion of the work. If you do not pay us within the time without good reason, we reserve the right to charge you interest at 1.5% per month on the amount still due to us.”
“31. The real question when a contractual provision is challenged as a penalty is whether it is penal, not whether it is a pre-estimate of loss. These are not natural opposites or mutually exclusive categories. A damages clause may be neither or both. The fact that the clause is not a pre-estimate of loss does not therefore, at any rate without more, mean that it is penal. To describe it as a deterrent (or, to use the Latin equivalent, in terrorem)does not add anything. A deterrent provision in a contract is simply one species of provision designed to influence the conduct of the party potentially affected. It is no different in this respect from a contractual inducement. Neither is it inherently penal or contrary to the policy of the law. The question whether it is enforceable should depend on whether the means by which the contracting party’s conduct is to be influenced are ‘unconscionable’ or (which will usually amount to the same thing) “extravagant” by reference to some norm. 32. The true test is whether the impugned provision is a secondary obligation which imposes a detriment on the contract-breaker out of all proportion to any legitimate interest of the innocent party in the enforcement of the primary obligation. The innocent party can have no proper interest in simply punishing the defaulter. His interest is in performance or in some appropriate alternative to performance. In the case of a straightforward damages clause, that interest will rarely extend beyond compensation for the breach, and we therefore expect that Lord Dunedin’s four tests would usually be perfectly adequate to determine its validity. But compensation is not necessarily the only legitimate interest that the innocent party may have in the performance of the defaulter’s primary obligations.” obligations.”
“The penalty rule is an interference with freedom of contract. It undermines the certainty which parties are entitled to expect of the law. Diplock LJ was neither the first nor the last to observe that ‘The court should not be astute to descry a “penalty clause”’: Robophone at p. 1447. As Lord Woolf said, speaking for the Privy Council in Philips Hong Kong Ltd v Attorney General of Hong Kong(1993) 61 BLR 41 , 59, ‘the court has to be careful not to set too stringent a standard and bear in mind that what the parties have agreed should normally be upheld’, not least because ‘[a]ny other approach will lead to undesirable uncertainty especially in commercial contracts’”
“Where two interpretations of an instrument are equally plausible, upon one of which the instrument is valid, and upon the other of which it is invalid, the court should lean towards that interpretation which validates the instrument.”
“All covenants in restraint of trade are prima facie unenforceable at common law and are enforceable only if they are reasonable with reference to the interest of the parties concerned and of the public. Unless the unreasonable part can be severed by the removal of either part or the whole of the covenant in question, its inclusion renders the covenant or the entire contract unenforceable.”
“Often, in reported cases, we find that instead of segregating two questions, (i) whether the contract is in restraint of trade, (ii) whether, if so, it is 'reasonable', the courts have fused the two by asking whether the contract is in 'undue restraint of trade' or by a compound finding that it is not satisfied that this contract is really in restraint of trade at all but, if it is, it is reasonable. A well-known text-book describes contracts in restraint of trade as those which 'unreasonably restrict' the rights of a person to carry on his trade or profession. There is no need to regret these tendencies: indeed, to do so, when consideration of this subject has passed through such notable minds from Lord Macclesfield onwards, would indicate a failure to understand its nature. The common law has often (if sometimes unconsciously) thrived on ambiguity and it would be mistaken, even if it were possible, to try to crystallise the rules of this, or any, aspect of public policy into neat propositions. The doctrine of restraint of trade is one to be applied to factual situations with a broad and flexible rule of reason.” 341. And in Proactive Sports Management Arden LJ said at [59]: “[I]n practice, I find that the line between the two stages identified by Jonathan Parker J [in Panayiotou] is not clear cut, and that the analysis has to be an iterative one between them. In particular, the matters that might be raised under the second stage might also be relevant to the question whether the doctrine of restraint of trade is engaged at all.”
“[R]estraints of trade and interference with individual liberty of action may be justified by the special circumstances of a particular case. It is a sufficient justification, and indeed it is the only justification, if the restriction is reasonable – reasonable. that is, in reference to the interests of the parties concerned and reasonable in reference to the interests of the public, so framed and so guarded as to afford adequate protection to the party in whose favour it is imposed, while at the same time it is in no way injurious to the public.”
“The onus is on the party asserting the contract to show the reasonableness of the restraint. That rule was laid down in the Nordenfelt case and in Herbert Morris Ltd v Saxelby. When the court sees its way clearly, no question of onus arises. In a doubtful case where the court does not see its way clearly and the question of onus does arise, there may be a danger in preferring the guidance of a general rule, founded on grounds of public policy many generations ago, to the guidance given by free and competent parties contracting at arm's length in the management of their own affairs. Therefore, when free and competent parties agree and the background provides some commercial justification on both sides for their bargain, and there is no injury to the community, I think that the onus should be easily discharged. Public policy, like other unruly horses, is apt to change its stance, and public policy is the ultimate basis of the courts' reluctance to enforce restraints. Although the decided cases are almost invariably based on unreasonableness between the parties, it is ultimately on the ground of public policy that the court will decline to enforce a restraint as being unreasonable between the parties. And a doctrine based on the general commercial good must always bear in mind the changing face of commerce. There is not, as some cases seem to suggest, a separation between what is reasonable on grounds of public policy and what is reasonable as between the parties. There is one broad question: is it in the interests of the community that this restraint should, as between the parties, be held to be reasonable and enforceable?”
“Purchase from [Biosol] all wood chip required to supply a 500kw boiler for the purpose of maintaining its output at maximum capacity for a period of 3 years where applicable.”