“4.3 If the Asset Manager proposes to replace the Key Person, the Asset Manager agrees to provide reasonable notice to (and within twenty (20) Business Days) and to consult with the MidCo [the Defendant] on the progress of any endeavours to find a replacement, and if the Asset Manager intends to seek the consent of the MidCo to any individual as a proposed replacement to the Key Person, it will provide appropriate information about such individual, including a curriculum vitae and references and the Asset Manager agrees that if the Key Person is to be replaced it will hire a replacement Key Person within six (6) months of notifying the MidCo of the proposed change. 4.4 If the MidCo does not approve (such approval not to be unreasonably withheld or delayed) a replacement suggested by the Asset Manager, the Key Person has ceased to perform the Services and the Asset Manager does not obtain a replacement by the expiry of six (6) months (or such longer period as may be agreed by the MidCo), the Midco may serve a notice terminating this Agreement.”
“Atlas has breached the Agreement including by failing to provide adequate Key Person services properly or at all, failing to procure that Jonathon Ivory fulfils the role of Key Person, failing to consult on and procure and appoint an adequate replacement within the timescales permitted or at all. As a result this letter is to notify you, Jonathon and Atlas Residential Solutions Management UK Ltd., that we have elected to terminate the Agreement with immediate effect.”
“however from a capital partner management perspective should be Jon’s successor. Hugh nor myself would be appropriate given distance and time zones.”
“The discussion centred around who from Atlas would be replacing Mr. Ivory as Key Person. I informed Mr. Black that Mr. Ivory’s expertise was in acquisitions and that, now the funding was secured, I would be taking over as Key Person as I had done for two other projects which Atlas managed in England at the time. Mr. Black asked about my qualifications and what role I had on the other two projects; I shared these with him. We then discussed my onboarding plan for Anaconda Cut for the next thirty minutes or so; in particular, how I foresaw leasing up the property. Mr. Black asked various general questions and appeared to be satisfied with my answers. He raised no objection to me assuming the role of Key Person. ”
“I cannot remember the precise words that I used but the purpose of the discussions and their substance was as set out at paragraphs 16 and 17 of my first witness statement.”
“Yes, because all the questions that were asked of me pertain to the Anaconda Cut project. There was no discussion of who was overseeing capital markets, who was overseeing acquisitions, who was overseeing the administration function of the managing director of the London office. Those questions were not gone into. But the focus of the conversation was focused on how soon are we going to be ready to let the units, how soon are we going to finish the fit-out, how soon are we getting facilities done, how is marketing going, and all those items are part of what the key man is to oversee or execute as part of the agreement….”
“I tried to make it as clear as possible on Friday the onboarding team point is myself, then Georgie. Hugh is focussed on existing assets and will transition to AC post handover.”
“We again discussed the role of Key Person. The conversation covered much the same topics as the telephone conversation on11 January 2019 . Mr. Black confirmed that Europa and Greengate were content for me to assume the role of Key Person in place of Mr. Ivory.”
“The words key person were not mentioned, but who was taking over Jon’s role, that was what was mentioned as pertains to this project.”
“We learnt earlier this week that our Greengate Key Man, Jonathon Ivory, resigned earlier this week. We have spent some time this week with the operational team and it seems that Jonathon is not particularly involved with the lease up or operations ……………..We would rather not change JV partner at this critical time of lease up (PC is forecast for the end of Feb/mid March) but we are reviewing ways that we can defer our key man clause until a later date to keep our options open. …………Atlas are proposing to replace him within 6 weeks.”
“We need to send a key person replacement notice under the management agreement with Europa. It is the only basis on which they can seek to terminate the agreement. So want to make you the key man if that is OK.”
“We would rather not change JV partner at this critical time of lease up (PC is forecast for the end of Feb/mid March) but we are reviewing ways that we can defer our key man clause until a later date to keep our options open.”
“We should also reflect on whether we should still be working with Atlas. What are the termination and key man provisions in the AM agreement ?”
“We can terminate if we don’t approve their replacement………….Our proposal is to delay the confirmation of the key man until we have made substantial progress on the leasing. We are just in the process of launching the building so it couldn’t be a worse time to change manager. We have been impressed with the operations teams so far ……..”
“Would you like me to attend next week’s progress meeting ? Per our mgmt. agreement it is a requirement for the key man to attend but am conscious that you may prefer that I do not (my last day is the following day).”
“HA [Mr. Adams] noted that Jonathon Ivory, who is a Key Man, recently left Atlas to join Henley Investment Management. No substitute Key Man has been put forward by Atlas. HA noted that this should not impact on leasing and that the local leasing team is being productive and responsive. HA provided an update on leasing, noting that the leasing velocity and rental levels are above business plan.”
“This presents an opportunity for Europa to take control of the asset and run the operations in house, whilst keeping the local team in place to ensure leasing momentum is maintained and continuity with the existing tenants.”
“Atlas have six months from the resignation of a key man to recommend a new person for the role, which Europa have the right to decline. To date, no new key man has been put forward by Atlas to Europa and therefore, in line with the Asset Management Agreement (“AMA”), this enables Greengate Sarl to terminate the AMA agreement on the six-month anniversary of the departure of the key man. The estimate of this date is the 8th July.”
“It seems he is taking over for me on AC. If so I need to know so I can transition stuff to him.”
“We need to send a key person replacement notice under the management agreement with Europe. It is the only basis which they can seek to terminate the agreement. So want to make you the key man if that is OK.”
“Atlas has breached the Agreement including by failing to provide adequate Key Person services properly or at all, failing to procure that Jonathon Ivory fulfils the role of Key Person, failing to consult on and procure and appoint an adequate replacement within the timescales permitted or at all. As a result this letter is to notify you, Jonathon and Atlas Residential Solutions Management UK Ltd., that we have elected to terminate the Agreement with immediate effect. ”