“If the tribunal is satisfied that there has been inordinate and inexcusable delay on the part of the claimant in pursuing his claim and that the delay— (a) gives rise, or is likely to give rise, to a substantial risk that it is not possible to have a fair resolution of the issues in that claim, or (b) has caused, or is likely to cause, serious prejudice to the respondent, the tribunal may make an award dismissing the claim.” the tribunal may make an award dismissing the claim.”
“Serious prejudice is, however, a different matter. We are satisfied that the delay has already resulted in a significant increase in costs in defending the claim. Hyundai have also been obliged to put up substantial security for Island View’s claim in terms of a cash deposit. We consider that this case ought properly to have come before us for a decision in 2013, or perhaps 2014 at the latest. As we suspect that Hyundai would not have been threatened with an arrest of one of their ships prior to their financial difficulties of 2016, we are therefore satisfied that there is a clear causal link between the delay and the substantial financial prejudice Hyundai have incurred in providing Island View with security for their claim. Island View’s demand also came at a most inconvenient time for Hyundai, when they were restructuring their fleet and reorganising their financial affairs. The mere threat of the arrest of one of their ships exposed Hyundai to further prejudice as it might have had a disastrous effect on their restructuring programme. As we are satisfied that the inordinate and inexcusable delay has already caused serious prejudice to Hyundai, we have decided to exercise the power given to us by Section 41(3) of the Act and dismiss Island View’s claim. We further award Hyundai their costs associated with this application and the costs of the arbitration.”
“To comply with its duty to act fairly unders. 33(1) of the Arbitration Act 1996 , the tribunal should give the parties an opportunity to deal with any issue which will be relied on by it as the basis for its findings. The parties are entitled to assume that the tribunal will base its decision solely on the evidence and argument presented by them prior to the making of the award. If the tribunal is minded to decide the dispute on some other basis, the tribunal must give notice of it to the parties to enable them to address the point. Particular care is needed where the arbitration is proceeding on a documents-only basis or where the opportunity for oral submissions is limited. That said, a tribunal does not have to refer back to the parties its analysis or findings based on the evidence or argument before it, so long as the parties have had an opportunity to address all the ‘essential building blocks’ in the tribunal’s conclusion. Indeed, the tribunal is entitled to derive an alternative case from the parties’ submissions as the basis for its award, so long as an opportunity is given to address the essential issues which led the tribunal to those conclusions…”
“If an arbitrator is impressed by a point that has never been raised by either side, then it is his duty to put it to them so that they have an opportunity to comment. If he feels that the proper approach is one that has not been explored or advanced in evidence or submission, then again it is his duty to give the parties a chance to comment…It is not right that his decision should be based on specific matters which the parties have never had the chance to deal with. Nor is it right that a party should first learn of adverse points in a decision against him. That is contrary both to the substance of justice and to its appearance.”
“Further, whatever prejudice would be suffered by Charterers [i.e. in having the claim dismissed] is overwhelmed by the prejudice which would be suffered by [Hyundai], in: (a) Having to defend this very stale claim, notwithstanding the likely diminution in value of the evidence (see above); and (b) The need to maintain a bond in the amount of US1,600,000 issued by Aspen Insurance UK Limited as security for the Charterers’ claim (pages 43-44), the necessary continuation of which is wasteful of [Hyundai’s] resources as [Hyundai] have had to deposit US$580,000 in cash with Aspen Insurance UK Limited and have to pay a bond fee of US$23,000 per year to maintain the security.”
“It is always important to keep in mind the distinction between a lack of opportunity to deal with a case and a failure to recognise or take such opportunity. It is commonplace in judicial decisions on points of construction that a judge may fashion his or her reasoning and analysis from the material upon which argument has been addressed without it necessarily being in terms which reflect those fully expressed by the winning party. There is not perceived to be, and is not, anything which is unfair in taking such a course. It is enough if the point is "in play" or "in the arena" in the proceedings, even if it is not precisely articulated. To use the language of Tomlinson J, as he then was, in ABB AG v Hochtief Airport[2006] 2 Lloyd's Rep 1 at [72], a party will usually have had a sufficient opportunity if the "essential building blocks" of the tribunal's analysis and reasoning were in play in relation to an issue, even where the argument was not articulated in the way adopted by the tribunal. Ultimately the question which arises under s. 33(a), whether there has been a reasonable opportunity to present or meet a case, is one of fairness and will always be one of fact and degree which is sensitive to the specific circumstances of each individual case. That applies to points of construction as much as to other points in dispute.”