“The Order places an obligation on electricity and gas suppliers who have 50,000 or more domestic customers and on electricity generators who have generated 10TWh/yr or more of electricity in specified years to achieve a carbon emissions reduction obligation. The obligation must be achieved by promoting particular types of (energy efficiency) actions to domestic energy users in areas of low income. The Order is administered and enforced by the Office for Gas and Electricity Markets (Ofgem).”
“20.—(1) The carbon emissions reduction obligation of one generator or supplier (“person A”) may be treated as achieved in whole or part by qualifying action completed by a generator or a supplier (“person B”) (“a transfer”). (2) A transfer only has effect if approved by the Authority (3) To obtain approval, persons A and B must— (a)apply for approval in writing to the Authority by31st December 2012 ; and (b)provide to the Authority such information, including the number and type of qualifying actions in question, as the Authority may reasonably require. (4) The Authority must not approve a transfer where it has reasonable grounds to believe that, if the transfer were approved, the carbon emissions reduction obligation placed on person B will not be achieved. (5) If the Authority decides not to approve a transfer under paragraph (4) it must notify persons A and B of the reasons for that decision. (6) The completed qualifying action under a transfer does not count towards the carbon emissions reduction obligation of person B.”
“21.—(1) A generator or a supplier (“transferor”) may trade up to 100% of its carbon emissions reduction obligation with any generator or supplier (“transferee”) (“a trade”). (2) A trade only has effect if— (a)approved by the Authority; and (b)made between1st March 2010 and30th September 2012 . (3) To obtain approval, a transferor and transferee must— (a)apply for approval in writing; and (b)provide to the Authority such information, including the amount of the carbon emissions reduction obligation to be traded, as the Authority may reasonably require. (4) Upon receiving an application under paragraph (3), the Authority must determine whether or not it approves a trade. …”
“26.—(1) The Authority must determine whether generators and suppliers have achieved their carbon emissions reduction obligation and notify them of that determination not later than30th April 2013 . (2) Not later than1st May 2013 the Authority must submit to the Secretary of State a final report setting out whether— (a)each generator and supplier has complied with its carbon emissions reduction obligation; (b)generators and suppliers have achieved the carbon emissions reduction targets in article 3(2); and (c)the overall carbon emissions reduction target under this Order was achieved.”
“27. A requirement placed on generators and suppliers under this Order is a relevant requirement for the purpose of— (a)Part I of the Electricity Act 1989 ; and (b)Part I of the Gas Act 1986 .”
“59 The overall target for the CESP obligation will be specified in the legislation in terms of a carbon points score of a proposed 19.25 million lifetime tonnes of CO2 (equivalent to 12.5% of the original CERT target). The overall carbon points target will be split between supply and generation companies, giving each obligated company an individual carbon points target. It is important to note that 19.25m will be a notional carbon savings figures. The real carbon savings delivered are likely to be around 2.9MtCO2.”
““area of low income” means an area which appears in the document approved by the Secretary of State entitled “Communities: Areas of Low Income” which is published on30th June 2009 and the ISBN of which is 9780108508417(1); “carbon emissions reduction obligation” means the reduction in carbon emissions that a generator or a supplier must achieve under this Order in its obligation period; “lifetime tonnes of carbon dioxide” means the amount of carbon dioxide that is expected to be saved over the lifetime of the measures to be promoted under this Order; “overall carbon emissions reduction target” means the target for the promotion of reduction in carbon emissions stated in article 3(1) and referred to in section 103(1) and (1A) of theUtilities Act 2000 ”
“Targeting low-income households: the cost of measures 4.84 While it is important that CESP offers measures to those who are unable to pay for them, the scheme should not be inflexible or designed in a way that prevents the cost-effective delivery of measures. The Government therefore proposes (in line with CERT) not to prescribe what suppliers and generators can charge for measures. It will not insist that measures are offered free of charge. Nor will it penalise companies who are able to leverage in other sources of finance to help with the cost of measures although, as noted earlier, this is expected to be rare. 4.85 This approach seems to strike the right balance between reaching those households most in need and allowing suppliers and generators to deliver schemes in the most cost-effective way. The design of the programme, however, will mean that suppliers and generators are likely to offer the vast majority of measures free, or at very low cost. This is because: ** CESP targets areas in the lowest decile of the income domain, so the majority of people targeted are likely to be unable to contribute to the cost of measures ** The scoring incentives for working on an intensive basis in these areas means that it will not be in the suppliers’ and generators’ interest to ‘cherry pick’ people who are able to pay for measures. ** The whole-house approach will mean that most measures offered will be relatively costly, making it less likely that people would be able to contribute to the cost.” ** CESP targets areas in the lowest decile of the income domain, so the majority of people targeted are likely to be unable to contribute to the cost of measures ** The scoring incentives for working on an intensive basis in these areas means that it will not be in the suppliers’ and generators’ interest to ‘cherry pick’ people who are able to pay for measures. ** The whole-house approach will mean that most measures offered will be relatively costly, making it less likely that people would be able to contribute to the cost.” 17. Size and number of projects 4.92. The Government estimates that CESP will consist of 50 to 100 projects, delivering energy efficiency measures to roughly 90,000 homes across Great Britain. The Energy Efficiency Partnership for Homes (EEPH) has conducted research into the spread of energy efficiency community schemes.”
“Kevin and I met with Ofgem today to explain the … combination [that included Teesside and the Claimant] and to discuss with them our thoughts on how best to combine the joint obligations. The meeting was positive and I’m more upbeat after the meeting than I would otherwise have been. Ofgem have confirmed that we can capture synergy benefits from joining the obligations, we can effect these through inter-book trades between the licensed entities, this position was uncertain previously. As a result of this ability to true up internally, on a very rough rule of thumb basis I estimate that the potential delivery risk resulting from [the Contract, ie the contract with the Defendant] can be reduced from -200k t/CO2 to -100k t/CO2. …”
“13 Assuming that we are able to proceed as planned with BG, there is a straightforward notification process required to turn-down the delivered volumes from [the Defendant]. [The Defendant has] indicated that there is no commercial incentive to them to deliver volumes at the current contract price; hence a reduction would be mutually beneficial.”
“Contracted with a second alternative contractor (Contractor 2) for it to provide 118,414 tCO2 at a total contract price of£6,808,805 .”
"Q. This gives the impression, doesn't it, that there was a contract with an independent contractor to pay£57.50 per tonne, doesn't it? A. Yes. Q. There was no such contract, was there? A. At this time the contract had not been agreed and signed, that's true. Q. There was no contract, was there? It didn't exist. A. At this time the contract didn't exist, that's right. Q. Contractor 2 didn't exist. There was no contractor 2, was there? This gives a completely misleading impression, doesn't it? A. Well, timing-wise the contract was not in place, but clearly the company had set out its intention to go down that route, and that's presumably what the letter was intended to -- Q. This is some sort of -- I'm not sure that one can even call it a reference, but some sort of distorted reference to the internal trade with Teesside at cost price, is it? A. It's a reference to the trades between Teesside and [the Claimant], that's right. Q. Because there was no written contract, you had to create one, didn't you? A. Sorry, please could you clarify? Q. Because there was no contract, as I think you have accepted, you had to create a contract. A. There was a contract put together soon after this, that's right."
“5.1 By no later than31 March 2012 [the Claimant and the Defendant] shall review the CESP Points obtained by [the Defendant] on behalf of [the Claimant], and the Measures then being Delivered, each in relation to the likely Overall CESP target. 5.2 Following such review if [the Claimant] reasonably believes that [the Defendant] is unlikely meet the Overall CESP Target by30 October 2012 [the Claimant] shall have the right to either trade, transfer to another CESP obligated party, or contract its outstanding CESP Points to a third party. Subject to Clause 5.4 the reasonable cost of trading, transferring or contracting away such CESP Points shall be met by [the Defendant] from its own funds. 5.3. Should the Budget be expended without the Overall CESP Target having been met [the Defendant] will meet, from its own funds, the reasonable cost of Delivering further Measures in accordance with the terms of this Agreement in order to ensure that the Overall CESP Target is achieved.”
“25.5. Subject to Clauses 25.1 and 25.2, and without prejudice to the Contractor’s obligations to pay any amounts properly due to [the Claimant] under this Agreement, [the Defendant] will not be liable to [the Claimant] for: … 25.5.3 any fine or other financial penalty imposed upon or levied against [the Claimant] by any Regulatory Body. … 25.8 Subject to Clause 25.3 above [the Defendant] will not incur any liability in relation to any fine or charge incurred by or charged to [the Claimant] by Ofgem or the government as a result of the Overall CESP Target or any other target or requirement in respect of the number of CESP Points to be achieved by [the Claimant] not being met.”
“[I]t is 2017 [now] and that Tower Hamlets scheme has still not been completed. And that is despite all the money that has been around through British Gas and other people. The schemes were incredibly difficult to make happen. It is not just about money.”
“Where they have not delivered, we have the right to contract elsewhere and recharge them the additional cost. However it is becoming clear that volume is simply not available, and we retain compliance exposure on the relevant generation licensees”
“Over and above the legislation and administration of CESP there is also significant lack of demand for the programme, compounded by the absence of funds by local partners and in some cases the lengthy and bureaucratic processes, such as procurement rules required in order to agree and run projects.”
"We initially tried the same tactics that everyone else was using, ie speaking to local authorities, to social housing and registered providers, and we fell into the same sort of issues, I think, that were faced by everyone else, where schemes were being outbid and schemes were falling away. That was our experience. So we decided that we couldn’t deal with that particular audience, so we started to approach private landlords who owned multiples of houses, presenting them with the CESP offer, which gained some immediate traction, and subsequently we decided that you will of our activities would be at private landlords and private residents, who could make decisions for themselves without a long winded discussion process as to whether this work was going to go ahead. … Acrobat Carbon Services has significant direct market capability. It understands data sets very well and it understands how to communicate with domestic home owners. So we employed a series of direct marketing techniques, we mailed the houses, we set up local pop up shops in the locations that are mentioned, we created branding, radio campaigns, we operated on the streets, knocking on doors, we got involved with the communities, the churches, the public houses, the big superstores, that type of thing, and we effectively stayed on the location until we achieved the required number of signups."
“22.—(1) Generators and suppliers must notify the Authority not later than31st January 2013 of— (a)the overall number and type of qualifying actions which they have completed; (b)the number and type of qualifying actions provided at particular premises; (c)the number of qualifying actions provided in a particular area of low income. (2) On receipt of that notification, the Authority must determine the reduction in carbon emissions to be attributed to those actions.”