“Article XII 1. Any dispute between one Contracting Party and an investor of the other Contracting Party, relating to a claim by the investor that a measure taken or not taken by the former Contracting Party is in breach of this Agreement, and that the investor or an enterprise owned or controlled directly or indirectly by the investor has incurred loss or damage by reason of, or arising out of, that breach, shall, to the extent possible, be settled amicably between them. 2. If a dispute has not been settled amicably within a period of six months from the date on which it was initiated, it may be submitted by the investor to arbitration in accordance with paragraph (4). For the purposes of this paragraph; a dispute is considered to be initiated when the investor of one Contracting Party has delivered notice in writing to the other Contracting Party alleging that a measure taken or not taken by the latter Contracting Party is in breach of this Agreement, and that the investor or an enterprise owned or controlled directly or indirectly by the investor has incurred loss or damage by reason of, or arising out of, that breach. 3. …………. 4. The dispute may, by the investor concerned, be submitted to arbitration under: (a) The International Centre for the Settlement of Investment Disputes (ICSID), established pursuant to the Convention on the Settlement of Investment Disputes between States and Nationals of other States, opened for signature at Washington 18 March, 1965 (ICSID Convention), provided that both the disputing Contracting Party and the Contracting Party of the investor are parties to the ICSID Convention; or (b) the Additional Facility Rules of ICSID, provided that either the disputing Contracting Party or the Contracting Party of the investor, but not both, is a party to the ICSID Convention; or In case neither of the procedures mentioned above is available, the investor may submit the dispute to an international arbitrator or ad hoc arbitration tribunal established under the Arbitration Rules of the United Nations Commission on International Trade Law (UNCITRAL). 5. Each Contracting Party hereby gives its unconditional consent to the submission of a dispute to international arbitration in accordance with the provisions of this Article. 6. (a) The consent given under paragraph (5), together with either the consent given under paragraph (3), or the consents given under paragraph (12), shall satisfy the requirements for: (i) written consent of the parties to a dispute for purposes of Chapter II (Jurisdiction of the Centre) of the ICSID Convention and for purposes of the Additional Facility Rules; and (ii) an “agreement in writing” for purposes of Article II of the United Nations Convention for the Recognition and Enforcement of Foreign Arbitral Awards, done at New York, June 10, 1958 (“New York Convention”). (b) The venue for any arbitration under this Article shall be such so as to ensure enforceability under the New York Convention, and claims submitted to arbitration shall be considered to arise out of a commercial relationship or transaction for the purposes of Article 1 of that Convention.”
“Article 31. GENERAL RULE OF INTERPRETATION 1. A treaty shall be interpreted in good faith in accordance with the ordinary meaning to be given to the terms of the treaty in their context and in the light of its object and purpose. 2. The context for the purpose of the interpretation of a treaty shall comprise, in addition to the text, including its preamble and annexes: (a) Any agreement relating to the treaty which was made between all the parties in connexion with the conclusion of the treaty; (b) Any instrument which was made by one or more parties in connexion with the conclusion of the treaty and accepted by the other parties as an instrument related to the treaty. 3. There shall be taken into account, together with the context: (a) Any subsequent agreement between the parties regarding the interpretation of the treaty or the application of its provisions; (b) Any subsequent practice in the application of the treaty which establishes the agreement of the parties regarding its interpretation; (c) Any relevant rules of international law applicable in the relations between the parties. 4. A special meaning shall be given to a term if it is established that the parties so intended. Article 32. SUPPLEMENTARY MEANS OF INTERPRETATION Recourse may be had to supplementary means of interpretation, including the preparatory work of the treaty and the circumstances of its conclusion, in order to confirm the meaning resulting from the application of article 31, or to determine the meaning when the interpretation according to article 31: (a) Leaves the meaning ambiguous or obscure; or (b) Leads to a result which is manifestly absurd or unreasonable.”
“The doctrine generally considers that investment infers: contributions, a certain duration of performance of the contract and a participation in the risks of the transaction …..In reading the Convention’s preamble, one may add the contribution to the economic development of the host State of the investment as an additional condition.”
“(1) Any writ or other document required to be served for instituting proceedings against a State shall be served by being transmitted through the Foreign and Commonwealth Office to the Ministry of Foreign Affairs of the State and service shall be deemed to have been effected when the writ or document is received at the Ministry. (2) Any time for entering an appearance (whether prescribed by rules of court or otherwise) shall begin to run two months after the date on which the writ or document is received as aforesaid. (3) A state which appears in proceedings cannot thereafter object that subsection (1) above has not been complied with in the case of those proceedings. (4) No judgment in default of appearance shall be given against a State except on proof that subsection (1) above has been complied with and that the time for entering an appearance as extended by subsection (2) above has expired. (5) A copy of any judgment given against a State in default of appearance shall be transmitted through the Foreign and Commonwealth Office to the Ministry of Foreign Affairs of that State and any time for applying to have the judgment set aside (whether prescribed by rules of court or otherwise) shall begin to run two months after the date on which the copy of the judgment is received at the Ministry. (6) Subsection (1) above does not prevent the service of a writ or other document in any manner to which the State has agreed and subsections (2) and (4) above do not apply where service is effected in any such manner. (7) This section shall not be construed as applying to procedures against a State by way of counter-claim or to an action in rem; and subsection (1) above shall not be construed as affecting any rules of court whereby leave is required for the service of process outside the jurisdiction.”
“It is true that the Chief Land Registrar by his order was not insisting on an originating summons and that any other appropriate originating process could have been used, although in my judgment the originating summons was the correct form; see RSC Ord 5 r.3. But whatever originating process was chosen, it must have been envisaged that the city council would be instituting proceedings as plaintiff and the only other known interested party, the Iranian Government, would be defendant, and that by analogy with rule 300 of theLand Registration Rules 1925 the Iranian Government would be served with the proceedings, so that it could participate in the hearing before the court. It seems to me therefore that the wording of the opening words ofsection 12(1) of the State Immunity Act 1978 is satisfied in the present case. ”
“An application for the registration of a judgment against a state under the 1920 Act must be made by the issue and service of a claim form.”
“Specifically, the Defendant agreed in writing to submit any dispute which may arise to arbitration…”
“an English court, even if it had a discretion so to do, ought not to do something which, in effect, would be to substitute its own decision for the arbitrator’s decision on a matter within the arbitrator’s jurisdiction.”