"Shipping to be arranged by the client who will provide Todaysure Matthews Ltd. with advanced notice in line with TML's programme of works (attached)"
"This meeting of7th June 2014 was set up to clarify, among other things, TSM's scope of works, in particular the shipping of the equipment. At the meeting it was confirmed by Mr. Boylan that the installation of the incinerators was not part of TSM's scope and would be carried out by a subcontractor engaged by MWS under the supervision of TSM. There was no ambiguity in my mind with regards to the shipping of the equipment. This was withdrawn from TSM's scope and it was agreed that it was MWS's responsibility to pack and collect from the source of the manufacture and deliver the equipment to the project site"
"As there is an air of nervousness brewing, can you confirm what is the situation with release of these overdue monies? Is there a problem? Can you give me an update?"