“Serious irregularity means an irregularity of one or more of the following kinds which the court considers has caused or will cause substantial injustice to the applicant— (a) failure by the tribunal to comply with section 33 (general duty of tribunal); (b) the tribunal exceeding its powers (otherwise than by exceeding its substantive jurisdiction: see section 67); (c) failure by the tribunal to conduct the proceedings in accordance with the procedure agreed by the parties; (d) failure by the tribunal to deal with all the issues that were put to it; (e) any arbitral or other institution or person vested by the parties with powers in relation to the proceedings or the award exceeding its powers; (f) uncertainty or ambiguity as to the effect of the award; (g) the award being obtained by fraud or the award or the way in which it was procured being contrary to public policy; (h) failure to comply with the requirements as to the form of the award; or (i) any irregularity in the conduct of the proceedings or in the award which is admitted by the tribunal or by any arbitral or other institution or person vested by the parties with powers in relation to the proceedings or the award.” (a) failure by the tribunal to comply with section 33 (general duty of tribunal); (b) the tribunal exceeding its powers (otherwise than by exceeding its substantive jurisdiction: see section 67); (c) failure by the tribunal to conduct the proceedings in accordance with the procedure agreed by the parties; (d) failure by the tribunal to deal with all the issues that were put to it; (e) any arbitral or other institution or person vested by the parties with powers in relation to the proceedings or the award exceeding its powers; (f) uncertainty or ambiguity as to the effect of the award; (g) the award being obtained by fraud or the award or the way in which it was procured being contrary to public policy; (h) failure to comply with the requirements as to the form of the award; or (i) any irregularity in the conduct of the proceedings or in the award which is admitted by the tribunal or by any arbitral or other institution or person vested by the parties with powers in relation to the proceedings or the award.”
“1. Section 68 sets out a closed list of irregularities (which it is not open to the court to extend). 2. Section 68 reflects the internationally accepted view that the court should be able to correct serious failure to comply with the “due process” of arbitral proceedings: cf art. 34 of the Model Law. 3. A serious irregularity has to pass the test of causing “substantial injustice” before the court can act (s.68(2)). 4. The test of “substantial injustice” is intended to be applied by way of support for the arbitral process, not by way of interference with that process. Thus it is only in those cases where it can be said that what has happened is so far removed from what could reasonably be expected of the arbitral process, that the court will take action. 5. The test is not what would have happened had the matter been litigated. To apply such a test would be to ignore the fact that the parties have agreed to arbitrate not litigate. 6. Having chosen arbitration, the parties cannot complain of substantial injustice, unless what has happened cannot on any view be defended as an acceptable consequence of that choice. 7. Section 68 is designed as a longstop, only available in extreme cases, where the tribunal has gone so wrong in its conduct of the arbitration in one of the respects listed in s.68, that justice calls out for it to be corrected. 8. Section 68 must not be used as a means of circumventing the restrictions upon the court's power to intervene in arbitral proceedings. Further, the distinction between s.68 and s.69 must be maintained. In addition, the court's powers under s.70(4) should be borne in mind (see below).”
“The parties should endeavour to agree procedural directions for the remaining claims in dispute. If directions are not agreed the Claimant should submit its proposed directions by26 November 2013 and the Respondent should submit its proposed directions by3 December 2013 . The Tribunal will retain the9 December 2013 [date] to deal with outstanding procedural issues and any substantive issues which can be dealt with that day but 21 November is vacated. The Tribunal will have to weigh the availability of counsel against the need for these matters to be determined without undue delay. To the extent that matters cannot be determined on 9 December the Tribunal is not then available until10 February 2014 . The parties are asked to indicate the availability of their counsel after that date.”
“1 (1) U&M be released from the undertakings required to be given at the hearing on21st March 2013 … 3 (1) That U&M be awarded its costs of the Settlement Agreement Arbitration as a whole … and that KCM make an immediate interim payment on account of 60% … 4 (1) That KCM should immediately release/discharge the BES Guarantee … (3) That U&M is entitled to be reimbursed its legal costs including those incurred in Brazil and Zambia in respect of KCM’s wrongful attempt to draw down under the BES Guarantee. 5 (1) A declaration that KCM wrongfully terminated/repudiated the FW/HW contract by its letter dated25th January 2013 . (2) A declaration that the Zambian court orders dated 31st January and1st February 2013 were wrongfully sought and obtained by KCM. (3) A declaration that U&M is entitled to be paid the demobilisation fee due to it under clause 3.3(a) of the FW/HW contract … alternatively an interim payment. (4) A declaration that U&M is entitled to be paid the termination fee under clause 35.1.7 of the FW/HW contract … alternatively an interim payment. (5) A declaration that U&M is entitled to the transfer of the ownership in items of equipment referred to in clause 3.2.6 of the FW/HW contract. (6) A declaration that U&M is entitled to damages for the losses which it suffered by reason of KCM having wrongfully terminated/repudiated the FW/HW contract. 6 (1) An order that KCM should make an immediate interim payment with regard to the invoice claims which are identified, together with default interest accrued thereon down to7th November 2013 , in the schedule attached as PGH1 to the sixth witness statement of Peter Gordon Hirst. 7 (1) A declaration that KCM’s attempt to draw down under the Advance Payment Guarantee issued under the main contract was unlawful and in breach of contract. (2) An order that KCM should immediately release U&M from the Advance Payment Guarantee. (3) KCM should immediately release U&M from the Second Performance Guarantee issued pursuant to the Main Contract.”
“to order on a provisional basis, subject to final determination in an award, any relief which the Arbitral Tribunal would have power to grant in an award, including a provisional order for the payment of money or the disposition of property as between any parties.”
“Accordingly, could the Tribunal firstly please confirm that in relation to paragraphs 41 to 47 and subparagraph 85(viii) of the Second Award, it is final as to the matters set out in those paragraphs (at least in the absence of any timely responses from the Respondent)? Secondly, could the Tribunal also please confirm (as we and our client have assumed, and as it appears that the Claimant has also assumed) that the remaining parts of the Second Award are not intended to operate on a provisional basis (in the sense that the word “provisional” is used in section 39 of the Act), nor as mere procedural directions. (This applies in particular to those parts of the award that are expressed as orders or directions.) Thirdly (and this is linked to the second request above), could the Tribunal please confirm (as again both we and Clyde & Co have assumed) that the time limits indicated in subparagraphs 75(iii), (vii), (viii), (ix), (xi) and xv) of the Second Award are intended to be final, such that they may not be the subject of a request by the Respondent for an extension of time.”
“First, since the jurisdiction of an arbitrator is a jurisdiction to decide disputes, it follows that the power to make an award is a power to decide matters in dispute between the parties. An award, interim or final, can only be an award in respect of matters referred to the arbitrators for decision. It follows, therefore, that (in the absence of some special agreement between the parties) a submission of disputes to arbitration will not generally give the arbitrators the power to order that one party shall pay a sum to the other, unless the arbitrators decide that sum is due and owing. Arbitrators can decide, by way of interim award, that a minimum sum is payable by one party to the other, if they decide that that sum at least is due and owing; but they cannot generally order that one party should pay a minimum sum to another on account of claims, simply because on a rough look at the case it looks as though such a sum at least will prove to be payable, without actually deciding that sum is due and owing. So to order would result in a change in the parties' respective economic positions, without deciding any matter in dispute; generally speaking, arbitrators have no power to order such a change. The second point is this. An interim award can relate to any issue in the matters in dispute referred to the arbitrators; it may relate to an issue affecting the whole claim (e.g. the issue of liability, reserving the issue of quantum for a final award), or may relate to a part only of the claims or cross-claims submitted to them for decision. It follows that arbitrators, when making an interim award, must specify the issue, or the claim or part of a claim, which is the subject matter of the interim award.”