“The terms and conditions of this proposal shall in all respects be construed and operated as a British contract and in accordance with English Law. If at any time any question, dispute, or difference whatsoever shall arise between the Seller and the Buyer in relation to, or in connection with the Goods, then every such case, dispute or difference whatsoever shall be submitted to arbitration in terms of the Arbitration Acts 1950-1979.”
“an application or appeal may not be brought if the applicant or appellant has not first exhausted: (a) Any available arbitral process of appeal or review, and (b) Any available recourse under section 57 (correction of award or additional award)”
“By no stretch of the imagination does the power in s 57(3) (a) to “correct an award so as to remove any clerical mistake or error arising from an accidental slip or omission to clarify or remove an ambiguity in the award” entitle a tribunal to reconsider its conclusion about the submissions of a party, especially where those submissions have been safely received and accurately recorded in the award. I would endorse the commentary on s 57(3) (a) and (b) in Mustill & Boyd on Commercial Arbitration (2nd Ed, Companion Volume 2001 at p 341) where it says: ‘Neither of these powers is intended to enable the arbitrator to change his mind on any matter which has been decided by the award, and attempts to use the section for this purpose should be firmly resisted. ”
“73. – Loss of right to object. (1) If a party to arbitral proceedings takes part, or continues to take part, in the proceedings without making, either forthwith or within such time as is allowed by the arbitration agreement or the tribunal or by any provision of this Part, any objection- (a) that the tribunal lack substantive jurisdiction, he may not raise that objection later, before the tribunal or the court, unless he shows that, at the time he took part or continued to take part in the proceedings, he did not know and could not with reasonable diligence have discovered the grounds for the objection.” (1) If a party to arbitral proceedings takes part, or continues to take part, in the proceedings without making, either forthwith or within such time as is allowed by the arbitration agreement or the tribunal or by any provision of this Part, any objection- (a) that the tribunal lack substantive jurisdiction, he may not raise that objection later, before the tribunal or the court, unless he shows that, at the time he took part or continued to take part in the proceedings, he did not know and could not with reasonable diligence have discovered the grounds for the objection.”
“3…..The email (of17 July 2012 ) was sent on the basis that ASES did not recognize my jurisdiction to arbitrate this matter and that it had not participated and was not then participating in the arbitration proceedings… … 28 Although ASES has chosen not to appear or be represented in the arbitration, I have sought to understand its objections to my jurisdiction as arbitrator in this dispute….”
“Arbitration and Law: Switzerland and/or Germany European Law , France, Germany or Swiss… France is not different from UK ….endless courts…Of course, we do not expect but you never know…”
“Saffet, Further to our discussions about the various ETI Maden Projects and our agreement in principle to cooperate with manufacturing licensed to ASES to allow DELKOR and ASES to penetrate this customers [sic] market and to reduce competitive efforts by other manufacturers. I enclose the form of agreement acceptable for DELKOR for this. I am continuing with preparation of the tender for ETI MADEN Bandırma Filter 2 expansion; and enclose our last correspondence on this project to identify the basis of this agreement and its intent. I also enclose a copy of the cooperation agreement in place for this specific project. I confirm that the ETI Bandirma second filter project is covered by this agreement. I request you to sign the enclosed and, return a copy by mail – we will accept a Signed and certified PDF if you have this facility. However, I have also couriered to you 2 off original documents for signature – you are required to return one copy by courier as well as any Email correspondence.”
“These are the documents that I took to the meeting (i.e the attachments from the above two emails from Richard Bond). The remaining appendices I also took to the meeting (the LML and the English version of the ETI Technical specification which had been sent to me by Baris on the 26 ( see paragraph 17 above). Saffet was given and saw all of these documents at the meeting including Delkor’s standard terms and conditions.”
“..the Contract that I had put together and used at that meeting with Saffet included all of the documents sent by Richard in his email of 28 July, as well as the revised and corrected front sheet entitled “Contract” (sent by Richard at 14.39). Saffet signed the front page of the Contract in front of me. Prior to this I had handed to Saffet on a memory stick each of the documents forming part of the Contract. These included the documents that Richard had emailed to me.”
“By this agreement between DELKOR and ASES we jointly confirm 1. Delkor shall commit to support ASES under the enclosed Licence Agreement for the ETI BOR Bandirma Project 2. ASES have Accepted, and DELKOR have also accepted to comply with the ETI BOR Technical Specifications for the project 3. ASES & DELKOR accept the Penalty clauses of the ETI Technical Specification, and DELKOR shall be responsible for ensuring they are achieved, or comply with the compensation under guarantee’s and the terms of the Licence Agreement. 4. Payment and Terms shall be- 5. Both parties shall make their best endeavours to meet the combined intent of both parties in this project”
“We confirm the following:- 1. “Delkor shall commit to support ASES under the enclosed Licence Agreement for the ETI BOR Bandirma Project. 2. ASES have accepted, and Delkor have also accepted to comply with the ETI BOR Technical specifications for the project. 3. ASES and Delkor accept the penalty clauses of the ETI Technical Specification and Delkor shall be responsible for ensuring they are achieved, or comply with the compensation under guarantees and the terms of the Licence Agreement. 4. Payment terms will be 25% with APG( APG received by ASES) 50% at the delivery against APG and APG valid until the good acceptance of ETI. Released against shipping information documents. 25% after final acceptance by ETI 5. Delkor will do everything in its power to get the goods to site before31 December 2011 , however at present we know that the pumps will be late and we will do our utmost to improve this”
“Under Swiss law, an individual agreement overrides a deviating provision contained in standard business terms. If no common intention can be established that the Parties simply forget to delete the reference to Delkor’s Standard Conditions Dated21 July 2012 contained in the Contract (which, based on the evidence, appears to be the case), then we are confronted with the case where the Parties individually agree on a neutral governing law but signed on the same occasion a contract that refers to standard business terms providing for arbitration under the Arbitration Act and English Law. The Swiss Federal Supreme Court holds that in such scenarios, the individual agreement prevails (Decision of the Swiss Federal Supreme Court DFC 93 II 325 et seq; 81 II 350: see also Decision of the Swiss Federal Supreme Court DFC 125 III 266 et seqq.)”
“There is no further debate that the Parties agreed that the arbitration agreement contained in the Limited Manufacturing Licence was applicable to the Contract and not the arbitration clause contained in the Standard Conditions Dated July 2012.”
“There remains important legal uncertainty related to such clauses and it cannot be excluded that other arbitral tribunals or other Swiss courts in different Cantons will arrive at the same conclusion and may not agree with the practical solutions suggested by some Swiss legal scholars.”