“23.1 As and when it is necessary for [Sobrena’s] employees…to go on the premises of [Acergy], [Sobrena] agrees too assume full responsibility for the proper and safe conduct of employees to comply with all statutory requirements, site rules, Health, Safety and Environmental rules and regulations. 24.1 [Sobrena] shall not claim any lien or attachment on any part of the Works or on any property of [Acergy] in possession of [Sobrena] at the Worksite. 25.1 This contract and any dispute of claim arising out of or in connection with it … shall be governed by and construed in accordance with the laws of England 27.1 Save to the extent of any indemnity provided under the Contract and liquidated damages, each party waives any claims against the other party and its Group for, and shall be responsible for, and shall indemnify and hold harmless the other party and its Group for any special, indirect, incidental or consequential damages… ”
“[Acergy] operations may be on going at the same time as [Sobrena] operations. [Acergy] therefore requires collaboration and good communication between the 2 Safety Management Systems that therefore will exist on site….An office will be required for the single point of issue for the two Permit to Work systems will be required (sic) to be supplied by [Sobrena]. ”
“1.1 …This site HSES Focus level has been established following [Acergy] Group procedure … and means that [Sobrena] is not working on a site managed by [Acergy] but HSES is of significant importance. 2. [Sobrena] shall be responsible for the health and safety of those personnel employed on work areas that are under their direct control whether they are direct employees .. or visitors. 3.1 [Sobrena] shall .. be fully responsible for compliance with: Relevant local, national and international laws and regulations 3.2 … [Sobrena] shall demonstrate that fit for purpose Safe Working Procedures are in place for the scope of the work, such as but not limited to: …Fire protection. 4.1 [Sobrena] shall document a … plan which shall bridge [Sobrena’s] HSES management system to the project HSES requirements...”
“EU-EI Coordination The Master [Sobrena’s head of EI] is responsible for the coordination of the measures he has decided and the measures set up by [Ship Manager] Inspection in common Before the beginning of any works a common inspection must take place concerning the work areas the fittings which stand there and the equipment that may be handed over. During this inspection the Master … defines the zone of intervention, marks out the limits of areas which can be dangerous … and indicates the passageways”
“Notwithstanding transfer of title, the risk of loss or damage of the Works shall remain with [Sobrena] as set out in Article 10.3”
“Except in case of death or personal injury caused by SOBRENA’s negligence, Sobrena’s liability under connection with a Contract, whether arising in contract, tort, negligence, breach of statutory duty or otherwise, shall not exceed an amount equal to EURO 30,000,000 (thirty millions Euros) during the calendar year in which the event or cause out of which liabilities arise. Where, in any one calendar day, there is more than one event or cause giving rise to liability on the part of SOBRENA, SOBRENA’s aggregate liability in respect of all such events or cause shall be limited to Euro 30,000,000 (thirty millions Euros) for the event occurring during that calendar year. Buyer shall be responsible and hold Supplier Group harmless from and against liabilities above such amount.”
“The master will retain the overall responsibility for the security and safety of the Vessel”
“All Work shall be conducted in accordance with French Legislation”