“Purchaser’s Default. In the event Purchaser fails to accept delivery of the Aircraft and pay the Purchase Price to Seller in violation of the terms and conditions of this Agreement, and provided Seller is not then in breach or default in timely performing its written obligations hereunder, Seller shall have the right, after ten (10) Business Days’ prior written notice from Seller of such breach or default and Purchaser’s failure to cure (or commence curing) the same with such 10-day period, to terminate this Agreement by written notice to Purchaser and the Escrow Agent. If Seller elects to terminate this Agreement pursuant to this Section 7.4.2, the Escrow Agent shall pay the Deposit to Seller as liquidated damages (and Seller and Purchaser shall promptly give written instructions to the Escrow Agent to that effect), and this Agreement shall be of no further force or effect. Seller acknowledges and represents that the liquidated damages amount provided for in this Section 7.4.2 is a reasonable estimate of the damages that would be incurred by Seller in the event Purchaser defaults on Purchaser’s obligations under this Agreement. Seller’s right to receive the Deposit as liquidated damages, shall be cumulative and not alternative, and shall be the sole remedy available to Seller in the event Purchaser defaults on Purchaser’s obligations under this Agreement (other than a default under this Article 7.4.2); and Seller waives any other remedies that may be available to Seller, at law or in equity, as a consequence thereof.”
“Force Majeure. Neither party shall be liable to the other as a result of any failure of, or delay in the performance of, its obligations hereunder, for the period that such failure or delay is due to: Acts of God or the public enemy; war, insurrection or riots; fires; governmental actions; strikes or labor disputes; inability to obtain aircraft materials, accessories, equipment or parts from vendors; or any other cause beyond Seller’s reasonable control. Upon the occurrence of any such event, the time required for performance by such party of its obligations arising under this Agreement, shall be extended by a period equal to the duration of such event.”
“1. Though the parties to a contract who use the words “penalty” or “liquidated damages” may prima facie be supposed to mean what they say, yet the expression used is not conclusive. The Court must find out whether the payment stipulated is in truth a penalty or liquidated damages…. 2. The essence of a penalty is a payment of money stipulated as in terrorem of the offending party; the essence of liquidated damages is a genuine covenanted pre-estimate of damage ( Clydebank Engineering and Shipbuilding Co. v. Don Jose Ramos Yzquierdo y Castaneda[1905] AC 6 ). 4. The question whether a sum stipulated is penalty or liquidated damages is a question of construction to be decided upon the terms and inherent circumstances of each particular contract, judged of as at the time of the making of the contract, not as at the time of the breach ( Public Works Commissioner v. Hills[1906] AC 368 , 376 and Webster v. Bosanquet[1912] AC 394 ). 4. To assist this task of construction various tests have been suggested, which if applicable to the case under consideration may prove helpful, or even conclusive. Such are: (a) It will be held to be penalty if the sum stipulated for is extravagant and unconscionable in amount in comparison with the greatest loss that could conceivably be proved to have followed from the breach. (Illustration given by Lord Halsbury in Clydebank Case[1905] AC 6 , 17. (b) It will be held to be a penalty if the breach consists only in not paying a sum of money, and the sum stipulated is a sum greater than the sum which ought to have been paid (Kemble v. Farren [1829] 6 Bing. 141, 148)…. (c) There is a presumption (but no more) that it is penalty when “a single lump sum is made payable by way of compensation, on the occurrence of one or more or all of several events, some of which may occasion serious and others but trifling damage” ( Lord Watson in Lord Elphinstone v. Monkland Iron and Coal Co. [1886] 11 App. Cas. 332, 342). On the other hand: (d) It is no obstacle to the sum stipulated being a genuine pre-estimate of damage, that the consequences of the breach are such as to make precise pre-estimation almost an impossibility. On the contrary, that is just the situation when it is probable that pre-estimated damage was the true bargain between the parties…”
“ … It does not at all follow that the supplier is entitled to rely upon an increase in the market price in comparison to the contract price as a force majeure circumstance. ……... This conclusion is consistent with a line of cases, both on force majeure clauses and on frustration, ….., to the effect that the fact that a contract has become expensive to perform, even dramatically more expensive, is not a ground to relieve a party on the grounds of force majeure or frustration. I take as an example Tennants (Lancashire) Ltd v CS Wilson & Co Ltd[1917] AC 495 , a force majeure case where Lord Loreburn observed at page 510: “The argument that a man can be excused from performance of his contract when it becomes "commercially impossible" seems to me to be a dangerous contention which ought not to be admitted unless the parties plainly contracted to that effect.””
“act of God or the public enemy; war; insurrection or riots; fires; governmental actions; strikes or labour disputes; inability to obtain the aircraft materials, accessories, equipment or parts from the vendors”
“By “hindering” delivery is meant interposing obstacles which it would be really difficult to overcome. I do not consider that even a great rise of price hinders delivery. If that had been intended different language would have been used, and I cannot regard shortage of cash or inability to buy at a remunerative price as a contingency beyond the sellers’ control.”
“Frustration of a contract takes place when there supervenes an event (without default of either party and for which the contract makes no sufficient provision) which so significantly changes the nature (not merely the expense or onerousness) of the outstanding contractual rights and/or obligations from what the parties could reasonably have contemplated at the time of its execution that it would be unjust to hold them to the literal sense of its stipulations in the new circumstances; in such case the law declares both parties to be discharged from further performance.”
“Equity looks on that as done which ought to be done”