“The Tribunal has considerable sympathy with Mr Kluger (and his company, the Claimant) in the difficult position in which he found himself at the time of the Gazprom reorganisation. With respect to all of the Claimant’s causes of action, the Tribunal notes that it was in no instance convinced that it was but for the Respondent’s actions that the Claimant lost its contracts. The Tribunal find that it appears from the evidence that this was the Gazprom Group’s unilateral decision. This finding of the lack of causation infects all of the claims in this arbitration. The Tribunal considers that, in those circumstances, if the Claimant has any claim it is a claim against SVP or GP or GE [each a Gazprom company] and not against the Respondent.”
“This is a mandatory provision. The policy in favour of party autonomy does not permit derogation from the provisions of section 68. A number of preliminary observations about section 68 are pertinent. First, unlike the position under the old law, intervention under section 68 is only permissible after an award has been made. Secondly, the requirement is a serious irregularity. It is a new concept in English arbitration law. Plainly a high threshold must be satisfied. Thirdly, it must be established that the irregularity caused or will cause substantial injustice to the applicant. This is designed to eliminate technical and unmeritorious challenges. It is also a new requirement in English arbitration law.
“In reply to your enquiry, we hereby inform you that the following volumes of stable condensate were refined at the Sosnogorsk GPP in 2007: in 2007 approx. 315 thousand tonnes refined and in 2008 approx 290 thousand tonnes. Gas condensate is refined according the established contracts. The designed capacity of the Plant allows for the refining of up to 950 thousand tonnes of stable condensate annually.”
“Under the Purchase Agreement with [Double K] and the September 2007 contract with [Neste] together, [Gazprom] was contractually bound to supply at a total rate of around 27,666 metric tons per month for the three months October to December 2007, plus or minus 10%. In 2008, the total monthly rates under both contracts would have been around 25,000 metric tons per month, and the total to be delivered during the year, 300,000 metric tons, subject to a possible deviation under each agreements of plus or minus 10%. Thus the total to be supplied in 2008, if [Gazprom] took advantage of a deviation of minus 10%, would have been around 270,000 metric tons. It appears that both in the last quarter of 2007, and during 2008, [Gazprom] could have met this required supply on the basis of the figures set out above.”
“35. When I advised my own contact within Severgazprom of the results of the arbitration, they were shocked that the statement by Gazprom Pererabotka had been accepted and relied on. 36. In the beginning of July 2009, I travelled to Russia to meet my contacts at Severgazprom to explain what had happened. My contacts did not believe that the false numbers provided by Gazprom Pererabotka were taken at face value by the Arbitral Tribunal. 37. I again requested evidence of production volumes and quantities allocated for export. This time, they agreed to provide documents from Severgazprom archives for 2006 and 2007 when Severgazprom was still in charge of sales and exports showing that the statement by Gazprom Pererabotka which the Arbitral Tribunal had relied on was false. 38. These documents confirmed the figures previously supplied by Kortes relying on the official Russian customs declaration. 39. They also showed that the statement of Gazprom Pererabotka relied on by the Arbitral Tribunal was intended to deceive the Arbitral Tribunal. 40. My sources within Severgazprom requested that I not mention their names as this is a highly sensitive matter within Gazprom and I must respect their wishes given the situation in Russia.”
“If this wording referred to the fraud of anyone that was involved in the arbitral process, whether or not the fraud was committed with the knowledge of the relevant party to the arbitration, then that would give unsuccessful parties carte blanche to apply to the court to set aside or remit an award. The unsuccessful party need only assert (for example) that a witness of the successful party had committed perjury (even without the knowledge of the successful party) and the award had as a result been in the favour of that party. It could then be asserted that the award had been ‘obtained by fraud’, resulting in ‘substantial injustice’; therefore the award must be set aside or remitted.”
“Mr Shackleton’s assertion that Neste knew or ought to have known [the statement] was false is pure unsupported assertion. Neste did not know it was false and had no reason to think it was. On the contrary, the GP statement fitted into a body of evidence that supported Neste’s case and belief, that the Sosnogorsk Plant had the ability to produce in excess of 270,000mt/year”
“… it is clear that the Tribunal, in realising that it was unjustified in refusing Double K’s request to order Neste to make the witnesses available, has sought in its Award to claim that it was unable to make such an order because of party agreement to the contrary. Given that there was, however, no such agreement (or any possible basis on which the Tribunal could genuinely believed there to have been any agreement) the Tribunal’s attempts to justify its decision ex post facto only further expose the clear and serious irregularity committed by the Tribunal.”
“Claimant’s position remains that there is no basis on which negative inferences may be drawn from any failure to produce this material which would be considered “privileged” if the correspondence had taken place in England, and is equally “privileged” under functionally equivalent legal norms and practice in civil law jurisdiction, including Russia (as set out in earlier correspondence). In light however, of the Tribunal’s indication that negative inferences may nonetheless be drawn from the non-production by Claimant of privileged settlement correspondence with Gazprom, Claimant has reviewed its position … Accordingly please find attached the correspondence between Double K and Gazprom concerning settlement of disputes between them including as to amounts withheld by Double K and resumption of deliveries by Gazprom under the Purchase Agreement following the conclusion of the direct contracts for the supply of VGC between Gazprom Export and Neste. In producing this documentation, Claimant does not concede that the documents are not subject to privilege nor does it waive privilege in any way in relation to any of the documents. It remains the Claimant’s position that these documents may not be relied on by the Arbitral Tribunal and they are produced solely to dispel the allegations made by the Respondent concerning attempts to settle and to avoid negative inferences”
“At a meeting held on9 September 2008 , Gazprom Pererabotka claimed that it had sufficient capacity to make deliveries to Double K under the Purchase Agreement notwithstanding its direct contracts with Neste on 28 September and11 December 2007 for the same monthly quantities of VGC. This was a mere bluff, as it had been confirmed to Double K by Russian Federation Custom reports (via Kortes) that there was not enough VGC available for export to supply both Double K and Neste. Indeed this is clear from the fact that even as at today Gazprom has only ever exported enough VGC to be able to supply one export contract (around 150,000mt of VGC per year) now supplied to Austrofin. Provided that the parent company Gazprom JSC was willing to guarantee future supply to Double K under the Purchase Agreement, this was not a concern. In any event, as it now turns out, it is clear that Gazprom’s claims were made as part of a careful plan to engineer a position to terminate the Purchase Agreement in Russian Courts (and avoid claims by Double K) by suggesting that it was prepared to resume deliveries. In addition, Gazprom Pererabotka asserted that, contrary to its earlier letter of2 August 2007 , future supply contracts for VGC were to be completed between Double K and Gazprom Pererabotka (not Gazprom Export).”
“The Claimant asks the Tribunal to infer ‘that there clearly are export restrictions on VGC’”