“in any event, from what date is it to be paid and what are the principles relevant to its determination”
“Issues not to be determined at this stage 12. The amount of interest on any damages payable to either party (i.e. claims that fall outside the accounting regime of Article 10.3), should any such claim find favour with you. 13. The amount of interest due to the Yard on the unpaid 8th and 9th instalments of the price under the Shipbuilding Contract. 14. The amount of interest due on the ESP 16,200,404 that the Buyer’s accept should be added to the 8th instalment of the contract price as the agreed cost of modifications to the vessel. 15. The amount of the Buyer’s claim in respect of financing charges, should that claim find favour with you. 16. The amount of any interest unders.49 of the Arbitration Act 1996 . 17. The precise financial consequences of any finding arising out of point 2 above, that the Yard did not properly perform its obligations under Article 10.3 of the Shipbuilding Contract.”
“32. Paragraph 29.3 of the Re-amended Defence and Counterclaim asserts that [the Yard is] obliged to give credit for, under point 29.3.4, the interest due to the Buyers in respect of the period between the date on which the Builders should have received the proceeds of sale of the vessel, or did in fact receive the proceeds, and the date when the money was actually received by the Buyers. 33. The closing submissions of the Buyers said, in paragraphs 101 and 102: ‘101(2) However, on the Yard’s case, it owed the Buyer US$ 20 million from12 July 2001 . 101(3) Thus the proper course was for the Yard to account for the US$ 20 million it owed, not fail to account at all on the basis that it might be liable for a greater sum. 102. No other explanation has been advanced for the Yard’s refusal to pay this money until about11 December 2001 . The financing charges referred to in paragraph 34.2 of the Buyers’ Re-amended Defence and Counterclaim are said to be the loss borne by the Buyers because they did not receive the$20 million in the period from12 July 2001 to11 December 2001 . I hold that interest for that period should be charged to [the Yard] under Article 10.3 of the Contract. I am asked to say what are the principles relevant to the determination of this amount. I cannot answer that; but if I am allowed to say so, I would choose the rate of LIBOR plus 1.25% which was charged to the Buyers by their bank, and not compound interest. … 42. Interest for the period of five months on$ 20 million should be charged to [the Yard] under Article 10.3 of the Contract (paragraphs 32-33).”
“4. Paragraph 32 of my Sixth Award has the heading “The Buyers financing charges”
‘However, on the Yard’s case, it owed the Buyers$20m from12 July 2001 .’ 5. The Buyers maintain that interest should have been awarded on the larger principal amount than the$20 million which I adopted in paragraphs 33 and 42(H) of the Sixth Award. They say that the principal amount, on my findings, ‘was closer to US$ 24,500,000 ’ than the [Yard’s] figure of$20.3 million . This would make a difference, I am told, of some$80,000 . The Buyer’s said that I was not asked to calculate the principal amount for this purpose, but to put the parties in a position where they could calculate. All I was required to do, the Buyer’s say, was to state the period and the rate for interest. It is said to be common ground, now, that the amount owing to the Buyer’s is$24 million ; but I do not rely on that figure, as I was not required to reach it. 6. I can readily believe that I was not required to calculate the principal amount which would emerge from the paragraphs 42(A) to (H) in the Sixth Award. I did not attempt to do that. On the other hand I was told, under the heading of the Buyers’ financial charges, that the [Yard] admitted liability for interest on$20 million . I could see no harm in declaring that sum to be due. 7. An Addendum was requested by solicitors for the Buyers, by a letter dated17th June 2005 , undersection 57 of the Arbitration Act 1996 . Two points were raised. The first related to the figure of$480,000 in paragraph 42(A) of the Sixth Award, and is not relevant to the present problem. 8. The second point is relevant. It concerned the interest awarded on$20 million for the period from 12th July to11th December 2001 . The Buyers argued that it should have started to run from17th January 2001 . In the Addendum dated5th August 2005 I rejected that argument. But what is or may be significant is that no request was made for reconsideration of the principal amount on which interest was awarded. It was not said that anything other than$20 million should be treated as the principal. Paragraph 9 of the Addendum stated that paragraphs 32 and 33 of the Sixth Award should not be altered. 9. Watson, Farley & Williams wrote on 31st October that I was expressly asked not to decide the amount of the Buyer’s claim in respect of financing charges, in Holmans’ letter of13th May 2005 (which reflected the parties’ agreement as to which issues fell to be decided). It seems to me that there was some ambiguity between paragraphs 10 and 12 of the letter. It may be that I regarded it as saying that I should not decide the rate of interest – hence the apologetic ‘if I am allowed to say so’ in paragraph 33 of the Sixth Award. Four days later, on 17th May, I wrote that the award was likely to be forthcoming the following week.” 10. I now accept that it was an error on my part to quantify the so-called financing charges. But I cannot accept that, as the Buyers have argued, I was using the$20 million as shorthand instead of the actual amount owing. The figure I wrote was what I intended to write. But I should have added that other sums due to the Buyers should in due course be awarded interest at LIBOR plus 1.25% for the period from 12th January to11th December 2001 . 11. I believe that I could and would have altered the Sixth Award if the error had been pointed out in time. But it was not. Power to amend paragraphs 33 and 42H of the Sixth Award rests now only with the High Court.” [emphasis added] ‘However, on the Yard’s case, it owed the Buyers$20m from12 July 2001 .’
“22. … to justify intervention under section 68, the serious irregularity must give rise to ‘substantial injustice’. Not all irregularities will justify the court’s intervention: some real and substantial injustice must result. Mr Croall relied upon dicta of Thomas J in Hussman v Al Ameen[2000] Lloyd’s Rep 83 at paragraphs 49 and 50. 23. This position reflects the policy behind the Act as set out in the Departmental Advisory Committee on Arbitration Law, Report on the Arbitration Bill. Paragraph 58 of the Report (cited and relied upon in Hussman v Al Ameen and Petroships Pte Ltd v Petect Trading and Investment Corporation, The Petro Ranger 2001] 2 Lloyd’s Rep 348) provides: ‘The court does not have a general supervisory jurisdiction over arbitrations. We have listed the specific cases where a challenge can be made under this clause. The test of “[substantial] injustice” is intended to be applied by way of support for the arbitral process, not be way of interference with that process. Thus it is only in those cases where it can be said that what has happened is so far removed from what could reasonably be expected of the arbitral process that we would expect the court to take action. The test is not what would have happened had the matter been litigated. To apply such a test would be to ignore the fact that the parties have agreed to arbitrate, not litigate. Having chosen arbitration, the parties cannot validly complain of substantial injustice unless what has happened cannot on any view be defended as an acceptable consequence of that choice.’ 24. In Groundshire v VHQ[2001] BLR 395 the court considered further the meaning substantial injustice at page 400. HHJ Bowsher stated: ‘29. The 1996 Act was intended to change the law. It was not merely a codifying statute. The court may be required in some circumstances to enforce or not to disturb an arbitrator’s decision, even when the court disagrees with that decision in law or in fact. 30. So also under the 1996 Act the court may be required to enforce or decline to disturb an arbitrator’s decision even when the court discerns an element of unfairness. 31. Both sections 68 and 24 of the Act justify action by the court only when substantial injustice has been or will be caused to the applicant, not when a substantial injustice may be caused to the applicant. It follows that even unfairness does not of itself and without more vitiate an arbitral award. 32. It is more important to look at the decisions that the courts made after the 1996 Act came into force than to consider earlier decisions. 33. For example, counsel for GS relied on Interbulk Limited v Aiden Shipping Co Ltd, The Vimeira[1984] 2 Lloyd’s Rep 66 , before the Act. In that case, at page 76, Lord Justice Ackner said: “Where there is a breach of natural justice as a general proposition it is not for the courts to speculate what would have been the result if the principles of fairness had been applied. I adopt, with respect, the words of Mr Justice Megarry in John v Rees[1969] 2 All ER 274 at page 309 where he said: ‘As everybody who has anything to do with the law well knows, the path of the law is strewn with examples of open and shut cases which, somehow, were not; of unanswerable charges which, in the event, were completely answered; of inexplicable conduct which was fully explained; of fixed and unalterable determinations that, by discussion, suffered a change.’” 34. Though entirely attractive as a general proposition, that is no longer the law as a result of the 1996 Act. The Act does not require the court to speculate what would have been the result if the principles of fairness had been applied, but the Act requires that the court is only to interfere if the court considers, not speculates, that the irregularity or unfairness has caused or will cause substantial injustice to the applicant. … 38. The policy of the 1996 Act is to make it more difficult to question the decisions of arbitrators, not to make challenges easier. 39. The word “substantial” appears in many contexts in our law. One simply cannot take a definition of the word from one context and apply it without question to another totally different context. I reject totally [counsel’s] submission as to the meaning of the word “substantial”
“Where there is a breach of natural justice as a general proposition it is not for the courts to speculate what would have been the result if the principles of fairness had been applied. I adopt, with respect, the words of Mr Justice Megarry in John v Rees[1969] 2 All ER 274 at page 309 where he said: ‘As everybody who has anything to do with the law well knows, the path of the law is strewn with examples of open and shut cases which, somehow, were not; of unanswerable charges which, in the event, were completely answered; of inexplicable conduct which was fully explained; of fixed and unalterable determinations that, by discussion, suffered a change.’” 34. Though entirely attractive as a general proposition, that is no longer the law as a result of the 1996 Act. The Act does not require the court to speculate what would have been the result if the principles of fairness had been applied, but the Act requires that the court is only to interfere if the court considers, not speculates, that the irregularity or unfairness has caused or will cause substantial injustice to the applicant. … 38. The policy of the 1996 Act is to make it more difficult to question the decisions of arbitrators, not to make challenges easier. 39. The word “substantial” appears in many contexts in our law. One simply cannot take a definition of the word from one context and apply it without question to another totally different context. I reject totally [counsel’s] submission as to the meaning of the word “substantial”