“Any dispute or difference between the parties as to any matter under or in connection with this contract shall be submitted for the determination of an expert (‘the expert’) and the following provisions of this clause (28) shall apply to any submission and to any other matter required to be dealt with by the expert.”
“The expert’s determination is to be conclusive and binding on the parties save in the case of manifest error or omission.”
“The parties are to instruct the expert to issue the decision within 30 working days of his appointment.”
“The parties agreed by consent on an order for directions. The directions were: “(a) initial written submissions, simultaneously exchanged,25 November 2024 ; “(b) submissions in reply, simultaneously exchanged,12 December 2024 ; “(c) opening notes,15 January 2025 ; “(d) one-day hearing in London,17 January 2025 ; “(e) agreed list of issues,24 January 2025 ; “(f) closing submissions,31 January 2025 ; “(g) expert’s decision,14 February 2025 .”
“Each party engaged their own experts and witnesses, including: (Claimant) Mr Timothy Howard, expert geologist of Leap Environmental Limited, Mr David Cotterell, expert valuer of Savills, London; (Respondents) Michael Reeve, expert geologist of SLR Consulting Limited, Mr Tim Mitford-Slade, expert valuer, Mr Toby Hill of Sheerness(?) Recycling.”
“The hearing was held on17 January 2024 , whereby the parties were given an equal opportunity to represent their cases. There was no examination-in-chief or cross-examination of the experts and/or witnesses. I, as expert, raised questions with the parties’ counsel, experts and witnesses.”
“‘Completion Date’: The date which is 10 working days from and excluding the unconditional date. “‘Condition Precedent’: The satisfaction of: (1) the earthworks condition; and (2) the EA condition. “‘EA Condition’”: The surrender of the EA permit in accordance with the requirements of the Environment Agency and providing sufficient evidence of same to the buyer. “‘Earthworks’: The infilling and engineering works to create the development platform in accordance with the specification at Annex A to the earthworks levels.
“The seller and the contractor shall instruct the employer’s agent to give to the buyer not less than 10 working days an inspection notice of each of the dates upon which he intends to inspect the earthworks with a view to issuing the practical completion statement.”
“The buyer and the buyer’s surveyor shall be entitled to accompany the employer’s agent on each such inspection and the seller and the contractor shall instruct the employer’s agent to allow the buyer and the buyer’s surveyor to make representations at such inspection as to why, in the view of the buyer or the buyer’s surveyor, the practical completion certificate should not be issued and the buyer shall confirm the representations in writing to the seller within five working days of the inspection and the seller will procure that the employer’s agent shall have due regard to the same, but the issue or non-issue of the practical completion certificate will be in the sole professional discretion of the employer’s agent.”
“Subject to the foregoing provisions of this clause having been observed by the seller, the practical completion statement will be conclusive evidence binding on the parties hereto, save in the case of manifest error of the practical completion statement, that the earthworks have been practically completed for the purpose of this contract.”
“Obviously, there is difficulty with the word ‘manifest’. What may be ‘manifest’ to one judicial officer may fail to persuade another. The criterion cannot be the swiftness of mind of the sharpest intellect. Nor can it be the perception of one whose whole career has been devoted to examining and reflecting upon building contracts. An objective, not a subjective, test for what is ‘manifest’ is contemplated. But the word will not go away. Against the background of its history in this context it requires swift and easy persuasion and rapid recognition of the suggested error”.”
“Where two parties to a contract have agreed that an expert shall be tasked with determining a question of importance to them and that they will be bound by the determination, the starting point is that they will be held to their agreement as long as the expert has not departed from his instructions and absent fraud or bad faith: Jones & Ors v Sherwood Computer Services plc[1992] 1 WLR 277 , CA.”
“A person sitting in a judicial capacity decides matters on the basis of submissions and evidence put before him, whereas the expert, subject to the express provisions of his remit, is entitled to carry out his own investigations, form his own opinion and come to his own conclusion regardless of any submissions or evidence adduced by the parties themselves.”
“… my consideration of these materials cannot amount to impermissible ‘extensive’ investigation: it is, rather, investigation of the type that the parties must be taken to have agreed could take place in the event that one of them challenged the outcome of a reasoned expert determination on the basis that it contained a manifest error. It is also relevant, in my judgment, that there was no possible remedy for an aggrieved party other than by challenging a determination on the ground of manifest error or fraud: a fairly thorough examination of the expert's determination is consistent with the fact that this would be the one and only chance of avoiding its consequences if they were indeed affected by error.”
“Accordingly, rather than express myself in terms which I consider unhelpful in the context of a challenge to a reasoned determination involving a question of contractual interpretation, in my judgment it is safer to focus on the Van der Merwe guidance read together the Veba guidance: to be ‘manifest’, errors must be so obvious and obviously capable of affecting the determination as to admit of no difference of opinion.”
“In my judgment, the errors I have identified are such as are unlikely to admit any difference of opinion: the reasoning above involves applying the words of the Agreement and doing the mathematics, not exercising fine judgment in relation to a difficult argument regarding construction. In that respect, I reject a contention made in E20's written evidence for these proceedings that the Agreement was ‘poorly drafted and ambiguous’ and that the expert had reached a reasonable construction; in my judgment, the provisions of the Agreement which I have had to consider are admirably clear.”
“Fundamental to the construction of this clause is a proper and full understanding of what ‘practical completion date’ means against the contextual background of the earthworks when read against the contract as a whole, having regard to the audience it was aimed at.”
“Tellingly, when quoting the relevant terms of the contract at paragraph 155 of his determination, the expert did not refer to the definition of ‘practical completion date’. Had he done so, his error would have been apparent to him.” difficult to understand in the light of the above paragraph and subsequent reasoning of the expert. The expert noted the parties’ agreement that the earthwork condition requires the “occurrence” of the practical completion date. (My emphasis). At paragraphs 122 to 124, the expert set out the position regarding practical completion, including the practical completion date. He then stated, at paragraph 125: “There is no definition of practical completion and therefore the common law ordinary meaning shall apply. I agree with the respondents’ submission as to what constitutes practical completion. The ordinary common law meaning of ‘practical completion’ requires the work to have reached a state of readiness for use free from any known omission or defects which are not merely trivial.”
“The contract does not expressly require any particular or standard form of certification to be used. The format of the practical completion statement was left to the certifier. Accordingly, the certifier cannot be criticised for formatting of the practical completion statement providing prima facie it can be understood from the instrument when the practical completion date occurred. I find that, objectively viewed, the practical completion statement adequately expresses the occurrence of the practical completion date.”
“Commissioners Road Quarry, Strood, Kent”
“It is against this contextual background that I agree with the respondents that, at the time of contracting, the buyer was not concerned with having a practical completion statement per se before practical completion was conclusive, but rather an assurance that the earthworks have been completed in accordance with the earthworks specification.”
“In other words, the absence of a practical completion date would simply mean that there was no ‘conclusive’ evidence of a practical completion date. It did not mean that the practical completion date had not occurred in fact.”
“The issue of a practical completion statement is a component of the condition precedent. Therefore, these preconditions for the giving of such a statement are themselves elements of the condition precedent. Therefore, strict compliance with those preconditions is required.”
“In short, the fundamental essence of the condition precedent is the occurrence of practical completion itself, not the issue of the certificate.”
“Satisfaction of the earthworks condition does not depend upon the date upon which the practical completion statement was issued. It is the evidential means by which the practical completion date is conclusively evidenced.”
“The parties have decided in this case they will replace the murky and disputable question of whether the practical completion has or has not been achieved by a given date with a manifest mechanism which is the production of a written document, a written statement that practical completion has occurred. Such a statement is produced and if it states a date and says that is the practical completion date then that tells you when the practical -- sorry, I beg your pardon -- when the condition precedent of this limb of the condition precedent is satisfied.”
“… in an attempt to elevate the issue of the practical completion statement to the status of the condition precedent and suggests whether or not the works were practically completed is irrelevant. In our submission, the condition precedent is the occurrence of the practical completion date itself”
“So, in short, we submit this a typical conclusive evidence clause and I have relied on some authority in my written submissions as well, but we submit that the earthworks condition will be satisfied on the occurrence of the practical completion date, not the issue of a certificate. The distinction is fundamental to this case because, as I will explain in a bit more detail, it means that the practical completion statement can be issued after a longstop date to evidence the satisfaction of the earthworks condition at an earlier date and time.”
“Oversights and blunders so obviously capable of affecting the determination to admit of no different of opinion.”
“However, if the employer’s agent did not intend to make any inspection of the earthworks then this clause becomes superfluous and redundant.”
“Clauses 7.14 and 7.15 were, on their proper construction, complied with.”