“191.3.1 Stevens & Bolton will contend that in the events which happened the delay in the development of the Tooting Property has led to Barrowfen securing an increased Gross Development Value for the Tooting Property in the order of a£20m increase for which Barrowfen must give credit. 191.3.1.2 Further or alternatively, Barrowfen must give credit for an increase in the Gross Development Value pursuant to the appropriate figures in paragraph 8.0.11 of the29 January 2021 report of Peter Clarke FRiCS for the events as found by the Court. 191.3.1.3 In the premises, it is denied that Barrowfen has made any loss and/or averred that it has made a profit. (a) S&B’s primary position is that set out in paragraph 182-190 of its Amended Defence, namely that Prashant and Suresh wished to “exit” their investment through a sale of the Tooting Property undeveloped with the benefit of planning permission at all material times. The profit made by the development in fact is in the sum of£15,891,884 (b) The measure of loss claimed is in any event denied and/or is misconceived. (c) Further or alternatively, the profit which would have been made by the hypothetical development is in the sum of£6,479,353 . 191.3.1.4 It is in any event, denied that any loss sustained by Barrowfen, which is denied, was caused by Stevens & Bolton or is loss for which Stevens & Bolton is responsible.”
“a) whether to allow an amendment is a matter for the discretion of the court. In exercising that discretion, the overriding objective is of the greatest importance. Applications always involve the court striking a balance between injustice to the applicant if the amendment is refused, and injustice to the opposing party and other litigants in general, if the amendment is permitted; b) where a very late application to amend is made the correct approach is not that the amendments ought, in general, to be allowed so that the real dispute between the parties can be adjudicated upon. Rather, a heavy burden lies on a party seeking a very late amendment to show the strength of the new case and why justice to him, his opponent and other court users requires him to be able to pursue it. The risk to a trial date may mean that the lateness of the application to amend will of itself cause the balance to be loaded heavily against the grant of permission; c) a very late amendment is one made when the trial date has been fixed and where permitting the amendments would cause the trial date to be lost. Parties and the court have a legitimate expectation that trial fixtures will be kept; d) lateness is not an absolute, but a relative concept. It depends on a review of the nature of the proposed amendment, the quality of the explanation for its timing, and a fair appreciation of the consequences in terms of work wasted and consequential work to be done; e) gone are the days when it was sufficient for the amending party to argue that no prejudice had been suffered, save as to costs. In the modern era it is more readily recognised that the payment of costs may not be adequate compensation; f) it is incumbent on a party seeking the indulgence of the court to be allowed to raise a late claim to provide a good explanation for the delay; g) a much stricter view is taken nowadays of non-compliance with the CPR and directions of the Court. The achievement of justice means something different now. Parties can no longer expect indulgence if they fail to comply with their procedural obligations because those obligations not only serve the purpose of ensuring that they conduct the litigation proportionately in order to ensure their own costs are kept within proportionate bounds but also the wider public interest of ensuring that other litigants can obtain justice efficiently and proportionately, and that the courts enable them to do so.”
“This court has recently had to deal with collateral benefits in a context not far removed from the present one. The general rule is that where the claimant has received some benefit attributable to the events which caused his loss, it must be taken into account in assessing damages, unless it is collateral. In Swynson Ltd v Lowick Rose LLP[2017] 2 WLR 1161 at [11] it was held that as a general rule "collateral benefits are those whose receipt arose independently of the circumstances giving rise to the loss." Leaving aside purely benevolent benefits, the paradigm cases are benefits under distinct agreements for which the claimant has given consideration independent of the relevant legal relationship with the defendant, for example insurance receipts or disability benefits under contributory pension schemes. These are not necessarily the only circumstances in which a benefit arising from a breach of duty will be treated as collateral, for there may be analogous cases which do not exactly fit into the traditional categories. But they are a valuable guide to the kind of benefits that may properly be left out of account on this basis.”
"The essential question is whether there is a sufficiently close link between the two and not whether they are similar in nature. The relevant link is causation. The benefit to be brought into account must have been caused either by the breach of the charterparty or by a successful act of mitigation much."
"First the relevant question is whether the negligence which caused the loss also caused the profit, in the sense that the latter was part of the continuous transaction of which the former was the inception. The second question is primarily one of fact."