“…. I consider that the right course is to adopt the test of a good arguable case, in the sense of a case which is more than barely capable of serious argument, and yet not necessarily one which the judge believes to have a better than 50% chance of success.”
“It follows that the evidence, including the evidence on the second question [dissipation of assets] posed by the judge…., must be looked at as a whole. A “good arguable case” is no doubt the minimum which the plaintiff must show in order to cross what the judge correctly described as the “threshold” for the exercise of the jurisdiction. But at the end of the day the court must consider the evidence as a whole in deciding whether or not to exercise this statutory jurisdiction.”
“In our view the test is whether, on the assumption that the plaintiffs have shown at least “a good arguable case”, the court concludes, on the whole of the evidence then before it, that the refusal of a Mareva injunction would involve a real risk that a judgment or award in favour of the plaintiffs would remain unsatisfied.”
“…the court has to scrutinise with care whether what is alleged to have been dishonesty justifies the inference [of dissipation]. That is not, therefore, a judgment to the effect that a finding of dishonesty (or, in this case, an allegation of dishonesty) is insufficient to found the necessary inference. It is merely a welcome reminder that in order to draw that inference it is necessary to have regard to the particular allegations of dishonesty and to consider them with some care.”
“On that basis, it seems to us that it would have been right for the judge to take into account a finding of a good arguable case that Mr Malofeev had been engaged in a major fraud, and that he operated a complex web of companies in a number of jurisdictions, which enabled him to commit the fraud and would make it difficult for any judgment to be enforced. We would regard such factors as capable of providing powerful support for the case of a risk of dissipation.”
“……Thus, the conduct of the plaintiffs may be material, and the rights of any third parties who may be affected by the grant of an injunction may often also have to be borne in mind….. Further, it must always be remembered that if, or the extent that, the grant of a Mareva injunction inflicts hardship on the defendant, their legitimate interests must prevail over those of the plaintiffs, who seek to obtain security for a claim which may appear to be well-founded but which still remains to be established at the trial.”
“I will not continue the prohibitory injunction on the grounds that it has not been established, to the requisite standard, that there is a risk of any of these matters coming about which would justify the court intervening by making compulsory orders against the wishes of the respondents.”
“it is therefore incorrect to suggest that “first contact” and a meeting with me as COO may have been influential in deciding to work with [the Company] and that the relationship with MHT was initiated “higher up”.”
“We proposed Oneview because it could be developed by [MHT] more cheaply than the equivalent development of Oracle.”
“My colleagues within our IT team have advised me that typically, they would expect a margin of no more than 15% when a supplier is simply passing on sub-contractor costs. In all of the examples I found, [the Company’s] margin was significantly in excess of that, and for the cases I was able to trace through I calculated a potential overcharge total of over£136,000 as is set out in the table below.”
“However, it was [Mr Taylor] who was responsible for Oracle management and he was the individual to whom anyone went to with projects and he controlled them and advised the business as to what it should spend. It was clearly [Mr Taylor’s] intention to maximise expenditure wherever he could as he was receiving secret payments.”
“[The Company] then secured a contract with [MHT] to provide off-site support, by demonstrating to [MHT] that savings could be made. This agreement is set out in the Sub-Agreement dated28 June 2012 . The basis of this contract was to reduce the fixed costs of onsite consultants… in addition to doing 30 Oracle enhancements (known as CEMLIs, which stand for ‘Customisation, Extension, Modification, Localization, and Integration’). Each CEML was expected to take 3 days. By this Sub-Agreement, [the Company] agreed to replace its onsite consultants with the offshore service. This primarily involved the use of consultants and business associates in India and Europe. The decision to move offshore was made by Head of IT Colin Daysh and the executive committee. [Mr Taylor] did not attend the meetings where detailed discussions took place with myself , Martin Crosby and Colin Daysh.”
“74. …….all discussions about work where formal proposals were not required were carried out with [MHT’s] internal computer network, since [Company] staff were effectively a [MHT] resource pool. [MHT] Project Managers would have discussed the effort and scope of the work parcel with the appropriate members of IT, including [Company] consultants where necessary. If needed, they would have discussed with our Delivery Manager (Venkat [Mr Muthiah]). No formal proposals would have been given by [the Company] unless we were specifically asked for one. We worked very closely with [MHT] and, effectively, all [Company] staff were accountable to ][MHT] project managers. We worked with [MHT] in a flexible way. For example, we did not enforce/police the number of CEMLs being pushed to be delivered beyond what we agreed. 75. It should be noted that [the Company] did not create any proposals unless specifically requested by [MHT]. [MHT’s] internal IT department created all the projects, decided the priorities and set out the cost. In general, [the Company] followed MHT processes. [MHT] estimated how long it should take [the Company] but since our personnel were involved in agreeing the effort needed, there was generally no negotiation and prices were accepted by [the Company]. The only exceptions were when [the Company] were asked to provide specific proposals or where there was a disagreement about the appropriate cost.”
“…a PO might say that a particular work parcel was to take 8 days at£500 , giving a PO value of£4,000 . After we had completed the work, and the PO was receipted in full (see below), we invoiced for the sum set out in the PO. The calculation to produce the price of£4,000 was then irrelevant, as it was simply the mechanism by which the number was produced. These Pos set out fixed prices, and providing we did the work [MHT] did not dispute the amount of time actually spent on the particular work parcel. They always receipted the Pos on the basis of the fixed price, by which I mean the [MHT] personnel approved payment in the same sum set out in the PO. It is important to note that they receipted the Pos before the invoices were raised, so they knew that we would invoice for the same sum on the PO. For example, I refer to an email chain involving both [Mr Taylor]” and Mr Hatchman, which involved precisely this situation. The PO had allowed for a certain number of days for the ‘iproc’ project. We had spent more time on the project that the PO anticipated, but charged according to the PO.”
“I felt deceived and emotionally pressurised because I had expected invoices from independent sub-contractors. However, [Mr Taylor] kept pressurising me, saying that the work had been done and that Coronet was just a subcontractor. We paid an initial sum of£11,125 , and further sums of£7,000 and£3,000 when put under a great deal of pressure by Mr Taylor. No further sums were paid. There was no further payment to Coronet nor have we used Coronet as a sub-contractor in any further projects.”
“Please send me the invoice for Tanem’s system and I’ll get a PO raised. It won’t be signed off till Bernard returns as >£10K and we don’t want to get Guy involved with approvals.” [Tanem refers to Tanem Mehmet of MHT.] vi) As to Mr Ladhur’s example at Ladhur 5 [66] about how Oneview would allow MHT to see how much money it was spending on individual suppliers, Mr Hatchman consider this to have been a very basic task which in-house staff in the IT department were capable of performing. vii) As to Mr Ladhur’s assertion (see paragraph 140 above) that there were only a very small number of invoices which predated the corresponding PO and that this was because the Company knew that the Procurement Department at MHT was going to be disbanded in its current form, Mr Hatchman says that this is entirely at odds with emails exchanged between Mr Ladhur and Mr Robertson on31 August 2011 . I agree that this cannot have been the reason, but I will need to say more about the underlying allegation later. viii) Mr Hatchman refers to an email from Mr Ladhur to Mr Robertson in which he says this: “Keith, as discussed re streaming informatrix, having checked our timesheet informatrix have invested over 40 man days (at least 20k) on this. Inorder [sic] to recover this loss I propose you set up PO called process redesign for Monarch and one for Non Monarch, so that Informatrix can recover at least 50% of this loss.”” ix) That exchange is also important because it appears that Mr Ladhur is telling Mr Robertson, as an MHT employee, what POs he wishes to have set up in order to recover the cost of work done without prior approval. The email continues by stating what process must be followed in future: it was not “process mania” but an attempt “to regain control of a very uncomfortable position”
“But certainly in my experience, they were doing this virtually blind. [Mr Taylor] would specify a piece of work based on a perceived user need, he would go away to obtain quotes, and he would then recommend to the user what price to pay, usually to [the Company]. The purchase order raising and receipting process then simply became a mechanism to allow the resulting invoice to be paid and coded to the correct department. Within the list of names put forward by [Mr Ladhur] there are individuals who have already been identified by Metropolitan as corrupt, such as Bernard Tominey, incompetent individuals and others who would have been unlikely to ask too many questions if advised to raise a [Company] purchase order in order to get the work done.”
“Email needs 2 go out from bill to dev and cc Patrick for go ahead of isupplier Who’s the next victim jag”
“I stated that all suppliers who wanted to remain an approved supplier for Metropolitan were expected to complete this”
“Some while back there was a Oneview system created for Tanem (who managed Facilities at the time). I am assuming that this system has been inactive for a while and therefore there are no associated on-going supports costs.”
“The OBIEE tool required configuring the accommodate BI Apps such that the vanilla reports can be made available to the business. Basic configuration was implemented 18 months ago for Procurement which allowed a small subset of Procurement reports and KPIs to be populated for the purposes of a demo….. Some additional basic configuration was applied to OBIEE which allowed a subset of Payable and Receivables reports and KPUIs to be made available for a demo to Finance Department. Procurement and Finance Departments are keen for OBIEE to be implemented as it significantly enhances their reporting capabilities.”
“OBIEE/BI Apps were installed over 2 years ago….”
“The Claimant’s evidence demonstrates clear dishonesty on the part of the Defendants and [the Claimant] has produced real evidence that there is a risk of dissipation of assets by [Mr Ladhur] if the terms of the freezing order are not continued. No evidence has been put forward by Mr Ladhur to meet the evidence that the Claimant has put forward on this point.”