“An Unacceptable Planning Condition is a condition or requirement in a Planning Permission or Planning Agreement which has the effect of: …. 2. limiting the Planning Permission to a set period of time ... 10. Imposing an obligation 10.1 which cannot be compiled with without the agreement of a competent Authority or third-party (including without limitation one requiring the construction of highway or drainage works) or 10.2 which prevents the commencement of the carrying out of and/or the use or occupation of the whole of any part of the Development unless and until a condition has been complied with which cannot be satisfied without the agreement of a competent Authority or third-party and which cannot in the reasonable opinion of a reasonable developer be obtained on terms or at a cost or within a timescale acceptable to a reasonable developer 11 in the reasonable opinion of a reasonable developer delaying commencement of the carrying out or completion of the whole or any part of the Development beyond the date on which such carrying out or completion would have occurred in the absence of such condition 12 any other condition in the reasonable opinion of the reasonable developer in any other way restricting the carrying out of and/or the use or occupation of the whole or any part of the Development or requires the incurring of expenditure which would be likely to have a materially detrimental effect on the financial viability or the investment value of the Development”
“The language used by the parties will often have more than one potential meaning. I would accept the submission made on behalf of the appellants that the exercise of construction is essentially one unitary exercise in which the court must consider the language used and ascertain what a reasonable person, that is a person who has all the background knowledge which would reasonably have been available to the parties in the situation in which they were at the time of the contract, would have understood the parties to have meant. In doing so, the court must have regard to all the relevant surrounding circumstances. If there are two possible constructions, the court is entitled to prefer the construction which is consistent with business common sense and to reject the other.”
“limiting the planning permission to a set period of time”
“any other condition in the reasonable opinion of the reasonable developer in any other way restricting the carrying out of and/or the use or occupation of the whole or any part of the Development or requires the incurring of expenditure which would be likely to have a materially detrimental effect on the financial viability or the investment value of the Development”
“The [claimant] is a captive company. The board – I am not sure I should be saying this – is largely a paper board. It isn’t a real board of directors. There weren’t discussions by the board of that company.”
"I think the pattern of these offers clearly leaves us with a dilemma in that the premium for conditional money being offered from a reputable source is substantial. I have discussed this briefly with Jim [Banks] and our gut reaction is that the Taylor Woodrow offer is worthy of further detailed consideration with specific emphasis on the deliverability of their scheme from a planning perspective, the validity of certain of their assumptions and the prospects for overage which is mentioned on a summary basis. I will make no further comment at this stage but await with interest your own observations of the way forward"
"The difference between conditional bids and unconditional is sufficient in my view, supported by Rapleys, to merit further investigation of the conditional bid of£4.8 million particularly as this is from Taylor Woodrow who are both a professional outfit and good for the money. The object of the further scrutiny is to establish the feasibility/deliverability of their project. This will however delay the process and receipt of sale proceeds. If a quick sale is required with the money being paid this year then this is not the deal to go for. My recommendation is to pursue the conditional offer. Please let me know if you do wish me to pursue the unconditional route."
"23. By the time Goodman Derrick was instructed by Rentokil to act as its legal adviser in relation to the sale of Garland Road and the related transactions to which I refer below, I considered Simon Catt to be an integral part of the Rentokil team. He was Rentokil's most known and trusted external adviser for property matters. He understood that Rentokil required that its legal advice be given in a commercial context. His advice was not limited to narrow legal issues. 24. My way of working with Simon Catt was always the same. He was someone to whom I could readily delegate the sale or purchase of property in the knowledge that he would revert to me on significant issues that I needed to consider in the context of a broader commercial deal. Simon knew and understood the extent to which I relied on him. I do not believe it would have occurred to him that in respect of the Garland Road sale, we would work on any basis other than "
“…different clients have different, as you see, perceived abilities, strengths, intellects. If, for example, one was selling land for residential development by a farmer, one would approach it completely differently to selling land for residential development by an international PLC where the team of representatives assisting me in the transaction included an intelligent in-house solicitor and a team of planning consultants and a team of experienced commercial agents. There is a massive range between those.”
“If I had a drafting problem, I would, as I did throughout…if issues of drafting arose I would liaise with two people on this transaction, and those were Mr Brown, in some instances, and Mr Steele on others.”
“…Mark and I had a lengthy discussion re this sale…and agreed various changes/expansions of provisions…”
"…subsequently I looked to Mr Brown for all instructions in relation to this transactions save as to merely factual matters and physical characteristics of the Site which fell within the knowledge and expertise of Mr Peace. Mr Brown at all times throughout was fully engaged with the transaction, and I always had the impression that it was a high priority for him. I did not get the impression at any time that he was too busy on other matters to give it its full attention. It was clear to me from his comments on an input into the draft documentation and correspondence that was circulated to him, that he read it carefully, and his instructions in relation to it were always well-informed and clearly given on the basis of an evident full understanding of its legal and commercial import."
“The ambit of the test [was] a matter for negotiation. And in this case the debate arose around the issue of whether the test should be in the reasonable opinion of the buyer, as posited by the Cameron McKenna drafting, or the reasonable opinion of a reasonable developer.”
"An Unacceptable Planning Condition is a condition or requirement in a Planning Permission or Planning Agreement but which one that has the effect of: (i) making the Planning Permission personal to the applicant or (ii) granting a temporary Planning Permission or (iii) limiting the occupation and/or use of all or any material part of the Residential Part of the Tower to any designated occupier or class of occupiers save in respect of Affordable Housing (iv) requiring the payment of expenditure of money or other consideration by way of planning gain all on works outside the Property which infringe the test of reasonableness of such obligations from time to time laid down by the Department of the Environment by circular or otherwise or preventing development or change of use without the agreement or co-operation of an independent third-party or public authority which cannot be obtained on terms or at a cost all within a time that is reasonable in the circumstances except where the Surveys prepared to bear such cost"
"…included discussion of the planning application process, chances of success and the risks of failure, and a line by line read through, discussion and negotiation of all of the provisions of the draft sale contract, using for this purpose the18 August 2006 revision…. Each participant had and referred to a copy, and discussion was detailed including suggestions for an agreement in principle of proposed amendments and in some cases exact wording for them. Mr Brown and Mr Steele sat beside me at the meeting and both participated fully in this process. The meeting lasted all morning, [the evidence suggests about 3 hours]. Every definition and clause which either party had concerns about was considered in turn."
"Mr Brown and I argued on behalf of the claimant that as drawn by Cameron McKenna it was too wide. It, under several of the categories of Adverse Conditions, applied a subjective "in the reasonable opinion of the Buyer" test. This, it was acknowledged by all the participants at the meeting, gave TW almost unlimited discretion as to whether any particular condition in a planning permission was acceptable to it, and last given the conditionality of completion of the sale, made the sale contract a virtual option."
"12. Mr Kendrick says that Rider C was discussed at the meeting on11 September 2006 and that he and I argued that it was too widely drawn. I have absolutely no recollection that Rider C was discussed at that meeting, still less that I was involved in the discussion. I am as certain as I can be that this never happened. As stated above, I do not believe that I ever had a copy of Rider C, nor did I understand what it said. There is no mention of it in my notes of the meeting ...; and I would not have regarded this as my role, nor would I have been competent, to discuss drafting points on Rider C. 13. I have absolutely no recollection of anyone saying at the meeting that Rider C made the sale contract into a virtual option. I am as certain as I can be that this was never said. If it had been, I would certainly have made a note of it and reported it to Rentokil's board. I would also have made it very clear at the meeting that this is not the basis on which Rentokil had gone into the negotiations and that, if this was indeed the case, there would be no contract with TW and that the negotiations have been a total waste of time."
“…I am pretty sure that I did not see Rider C at that meeting. In fact, I would not say I was absolutely sure, but to the best of my recollection I did not see Rider C at that meeting. “ He then became more concrete in his answers on this issue adding that he did not believe that Rider C was discussed at the meeting. He is wrong on both counts as the correct reading of a manuscript attendance note of the meeting made by Mr Steele, referred to below, shows. Mr Kendrick told me, and I accept, that he had a specific recollection of this meeting and in relation to Rider C he said “[Mr Brown] could see what I pointed out and understand what I pointed out, and I believe he did understand the difference between “reasonable opinion of the buyer” and “reasonable opinion of a reasonable developer” but there was no detailed discussion of Rider C, line by line, as there had been in respect of the other parts of the draft contract, instead “There was enough discussion to raise the key issue of the objectionability to me and thus to my client of the objective test that had appeared there and that we would want to contest it.”
"... my suggested deletions are of those provisions where such expenditure or obligation is, to some extent envisaged or in the case of item 13 because it is far too general nature. Elsewhere I have merely contested the "reasonable opinion of the Buyer" tests, as this usurped objectivity and the jurisdiction of the dispute resolution regime in the body of the contract."
"I return Rider C approved as further amended. A couple of comments: -- 1 although my clients will accept the need for some objectivity it is important that the planning conditions are assessed from the point of view of a reasonable developer and I have used this as the benchmark. 2 Paragraphs 10 and 11 are not dealt with elsewhere in the contract. They are important to my clients. To take an example in relation to paragraph 10, if a planning condition required an additional emergency exit route over Carpetright’s land this would have to be an onerous condition. 3 Paragraph 13 must also be reinstated. We cannot be certain what types of conditions the planning authority may seek to impose. On the basis that it refers to things which are "materially" detrimental I would not have thought this a problem to your clients."
"in the course of that discussion, Mr Brown understood that there would always be risk with conditions of this sort and that there would remain the potential risk of Taylor Wimpey trying to manipulate planning conditions in a planning permission should they seek to escape from their obligations under the agreement and that at least should ensure that the planning application contains sufficient allowance for planning gain to protect against planning conditions for planning game being used in that way” Mr Kendrick produced an attendance note of this conversation in which he says that he accurately recorded the conversation with his client and the instructions which he was given: “[Attending Gareth Brown] discussing [Cameron McKenna’s] amendment to Adverse Conditions, per his letter 15.9.06. Agree reasonable developer test generally. Also prepared to agree cl.10 so long as [sure or sue] – Rapleys that adequate provision in [application] for planning permission for planning gain. Same with cl.11 re Council – and if adjoining owner or someone else imposes a ransom v. unlikely – then that is a risk we must take. We will insist on reasonable developer test throughout in Cl.13” Mr Kendrick says, in respect of the “sure/sue” dispute, that the word in question is "sure"
"his concern as to that paragraph was that as to "planning gain" ... Rapleys should ensure, in their consideration and approval of TW's proposed planning application, that the application included sufficient offering of planning gain to make this paragraph unlikely to be of effect."
"I think we are substantially there"
"The purpose of this letter is to give you a brief summary of the key provisions of the contract, to allow an understanding of particularly the timings, as to matters such as conditionality and completion. 1 The purchase price is£4,388,000 plus possible adjustments. The first of these is by reference to what are called the "
“…discharged my duty to report on the key provisions of the contract that, in my mind at the time, presented severe risk of the transaction not completing... At the time that this letter was written, I considered, particularly as regards schedule 1, that I’d got the best in terms of negotiation that I could achieve. And I felt it was time to hand…the issue of the progressing the planning application over to Rapleys, and I didn’t feel the need to elaborate beyond the structure around that in this letter.”
"just to confirm that I have been through the contract and I find everything in order"
“…it gave me comfort. Colin was happy with it. Colin had been involved throughout, and it was his deal in terms of the commercial nature of the deal.”
“… I am not at all inclined to agree to any further extension. I know what Mark says regarding the fact that the contract in (sic) still conditional and they could try to weasel out of it in some other way if they really did want to but I don't see any advantage in simply conceding the point. What benefit do I obtain by doing so? Nothing as far as I can see Colin, I suggest that you do nothing at the moment given that they are meeting with their experts to discuss the rainwater harvesting system on Wednesday. If chased, say you cannot get instructions as I am unavailable (always a good and credible lie) but explore in enthusiastic Lee the possibility of them going down the rainwater harvesting route. Later this week, and only in response to further query from them we will tell them that we are not giving them the easy get out. This contract has taken months to negotiate, they were happy when they signed it and now, like us, they will have to live with it." Mr Brown was asked to explain what that email meant and he said: “Well, they signed a contract. We signed a contract. And the terms of the contract were quite clear. They knew what they were signing, and we knew what we were signing, we thought, and they would – well, we would have to live with it. That is the deal that has been done.”
"All In view of the softening of the market generally and recent difficulties that Taylor Wimpey appear to be in, please be particularly alive to the possibility of some slowing of their activity. Please let me know if this is, or becomes apparent. At the moment it seems as if they are still proceeding but I'm always waiting for the call from them wishing to renegotiate."
"Your thoughts are well founded and we are of course alive to the possibility that they will try and f*ck up the planning appeal…….. you will have detected that Hannah and Robert have been keeping a very close eye on what they and their consultants are up to but that is as much as can be done at this stage. If they did come back to "renegotiate"
“I am always a bit nervous of the unacceptable planning condition provisions in any contract but everything points towards there being very little “wriggle room” for TW on the basis of this consent”
“…immediate impression [was] that it raises far fewer points of construction or purely legal matters then we had assumed. The matters of waiver and good faith may still arise but, other than in relation to the silly three year time limit points, the main area of debate seems to be the more factually based issue as to what a reasonable developer might think as to extra costs and delays. In this context the extent of TW's acceptance of the conditions will be very relevant as to what a reasonable developer would expect ... It also seems to me that the position disclosed by the CM letter makes it much more difficult for TW to argue that the agreement is ipso facto determined by their mere assertion that the conditions are unacceptable.”
“Exchange of evidence took place on 15 July and confirmed our view that the arbitration would turn on whether the arbitrator applied a literal or commercial construction of the agreement.”
"I wish to say that in my experience it would be most unusual for a developer promoting a scheme, such as this for the Property, to have failed to anticipate the imposition of conditions one, six, 11, and 19 of the appeal decision. I regard them as entirely reasonable and commonplace and it was my impression that the respondents did likewise”., Ms Cash, who was Mr Clarke’s assistant, gave evidence in the form of a witness statement about her part in the transaction before concluding: "
"When Goodman Derrick were still acting for Rentokil, Brian Ash QC advised that the prospects of success at arbitration were better than 50%. Without waiving privilege and subsequent legal advice, I can confirm that we did not subsequently receive any legal advice which significantly altered the prospects of success. There was no set piece written advice on merits of subsequent to make Brown being instructed. There was a very large amount of communications between Rentokil and Mayer Brown and it is difficult to isolate those which amounted to specific advice on merits, but I certainly do not recall the prospects of success being materially different at any point in time. If anything, on balance, my recollection is that Rentokil's case got slightly better once we had seen TW's evidence as the issues were narrowed. The merits of these issues did not change; rather, there were fewer issues to be determined. On balance we thought we would win the arbitration itself."
"I understand that Rentokil's solicitors will seek to delete this subparagraph and replace it with the following, in order to avoid an unnecessary argument about waiver of privilege. I confirm that I approve the amendment: "the prospects of success in the arbitration: when Goodman Derrick were still acting for Rentokil, Brian Ash QC advised that the prospects of success at arbitration were better than 50%. I thought that, on balance, we would win the arbitration itself and that remained my view throughout."
“ If in the exercise of a reasonable professional judgement a solicitor is or should be alerted to risks which might elude even an intelligent layman, then plainly it is his duty to advise the client of these risks or explore the matter further.”
“…where the Plaintiffs' loss depends upon the actions of an independent third party, it is necessary to consider as a matter of law what it is necessary to establish as a matter of causation, and where causation ends and quantification of damage begins. 1. What has to be proved to establish a causal link between the negligence of the Defendants and the loss sustained by the Plaintiffs depends in the first instance on whether the negligence consists on some positive act or misfeasance, or an omission or non feasance. In the former case, the question of causation is one of historical fact. The Court has to determine on the balance of probability whether the defendant's act, for example the careless driving, caused the plaintiff's loss consisting of his broken leg. Once established on balance of probability, that fact is taken as true and the plaintiff recovers his damage in full. There is no discount because the judge considers that the balance is only just tipped in favour of the plaintiff; and the plaintiff gets nothing if he fails to establish that it is more likely than not that the accident resulted in the injury. Questions of quantification of the plaintiff's loss, however, may depend upon future uncertain events. For example, whether and to what extent he will suffer osteoarthritis, whether he will continue to earn at the same rate until retirement, whether, but for the accident, he might have been promoted. It is trite law that these questions are not decided on a balance of probability, but rather on the court's assessment, often expressed in percentage terms, of the risk eventuating or the prospect of promotion, which it should be noted depends in part at least on the hypothetical acts of a third party, namely the plaintiff's employer. 2. If the defendant's negligence consists of an omission, for example to provide proper equipment, given proper instructions or advice, causation depends, not upon a question of historical fact, but on the answer to the hypothetical question, what would the plaintiff have done if the equipment had been provided or the instruction or advice given. This can only be a matter of inference to be determined from all the circumstances. The plaintiff's own evidence that he would have acted to obtain the benefit or avoid the risk, while important, may not be believed by the judge, especially if there is compelling evidence that he would not. In the ordinary way, where the action required of the plaintiff is clearly for his benefit, the court has little difficulty in concluding that he would have taken it. But in many cases the risk is not obvious and the precaution may be tedious or uncomfortable, for example the need to use eardefenders in noisy surroundings or breathing apparatus in dusty ones. It is unfortunately not unknown for workmen persistently not to wear them even if they are available and known to be so. A striking example of this is the case of McWilliams v. Sir William Arrol & Co. Ltd.[1962] 1 WLR 295 HL; the employers failed in breach of their statutory duty to provide a safety belt for the deceased steel erector. But his widow failed in her claim under the Fatal Accidents Act, because there was compelling evidence that, even if it had been provided, he would not have worn it. Although the question is a hypothetical one, it is well established that the plaintiff must prove on balance of probability that he would have taken action to obtain the benefit or avoid the risk. But again, if he does establish that, there is no discount because the balance is only just tipped in his favour. In the present case the Plaintiffs had to prove that, if they had been given the right advice, they would have sought to negotiate with Gillow to obtain protection. The Judge held that they would have done so. I accept Mr Jackson's submission that since this is a matter of inference, this Court will more readily interfere with a trial judge's findings than if it was one of primary fact. But even so, this finding depends to a considerable extent on the Judge's assessment of Mr Harker and Mr Moore, both of whom he saw and heard give evidence for a considerable time. Moreover, in my judgment there was ample evidence to support the Judge's conclusion. Mr Jackson's attack on this finding was, as I have explained, something of an afterthought and not, I think, undertaken with great enthusiasm. I am quite unable to accede to it. 3. In many cases the plaintiff's loss depends on the hypothetical action of a third party, either in addition to action by the plaintiff, as in this case, or independently of it. In such a case does the plaintiff have to prove on balance of probability, as Mr Jackson submits, that the third party would have acted so as to confer the benefit or avoid the risk to the plaintiff, or can the plaintiff succeed provided he shows that he had a substantial chance rather than a speculative one, the evaluation of the substantial chance being a question of quantification of damages? Although there is not a great deal of authority, and none in the Court of Appeal, relating to solicitors failing to give advice which is directly in point, I have no doubt that Mr Jackson's submission is wrong and the second alternative is correct.”