“...and it is quite clear that there is a dispute as to the amount of monies owed to your client. Our client has very serious concerns regarding the quality of the works carried out to the restaurant and in particular the delays caused by your client. We understand our respective clients have been in discussions and it was agreed that a final account would be provided - our client has yet to receive, or indeed agreed to a final account.”
“(a) A creditor's petition can only be presented by a creditor, and until a prospective petitioner is established as a creditor he is not entitled to present the petition and has no standing in the Companies Court: Mann v. Goldstein[1968] 1 WLR 1091 . (b) The company may challenge the petitioner's standing as a creditor by advancing in good faith a substantial dispute as to the entirety of the petition debt (or at least so much as will bring the indisputable part below£750 ). (c) A dispute will not be "substantial" if it has really no rational prospect of success: in Re A Company No.0012209[1992] 1 WLR 351 at 354B. (d) A dispute will not be put forward in good faith if the company is merely seeking to take for itself credit which it is not allowed under the contract: ibid. at 354F. (e) There is thus no rule of practice that the petition will be struck out merely because the company alleges that the debt is disputed. The true rule is that it is not the practice of the Companies Court to allow a winding up petition to be used for the purpose of deciding a substantial dispute raised on bona fide grounds, because the effect of presenting a winding up petition and advertising that petition is to put upon the company a pressure to pay (rather than to litigate) which is quite different in nature from the effect of an ordinary action: in Re A Company No.006685[1997] BCC 830 at 832F. (f) But the court will not allow this rule of practice itself to work injustice and will be alert to the risk that an unwilling debtor is raising a cloud of objections on affidavit in order to claim that a dispute exists which cannot be determined without cross-examination (ibid. at 841C). (g) The court will therefore be prepared to consider the evidence in detail even if, in performing that task, the court may be engaged in much the same exercise as would be required of a court facing an application for summary judgment: (ibid at 837B).”
“On such an appeal, as prescribed by s.16, it is for Arena to establish circumstances justifying the discharge or reduction of the assessments. If there is a real doubt as to the propriety of the assessments then the issues should be resolved by the Tribunal, not only because the Tribunal is the forum prescribed by Parliament, but also because it is not the function of the Companies Court in the exercise of its winding up jurisdiction to adjudicate in respect of a genuinely disputed debt. By contrast a company which is unable to pay its debts is not to be permitted to delay its winding up by advancing spurious excuses for non-payment of the petitioner's debt.”
“That practice,” he said, “it appears, has been established since the end of the last century. It was explained by Buckley LJ in Stonegate Securities v. Gregory[1980] 1 All ER 241 at 243-244 [1980 Ch 576 at 580, where, having adopted a passage from a judgment of Ungoed-Thomas J in Mann v. Goldstein, he said: ‘In my opinion, a petition founded on a debt which is disputed in good faith and on substantial grounds is dermurrable for the reason that the petitioner is not a creditor of the company within the meaning of s.224(1) at all, and the question is whether he is or is not a creditor of the company is not appropriate for adjudication in winding-up proceedings.’ So the dismissal of the petition in such a case is not, at any rate initially, a matter for the discretion of the court. It is founded on the petitioner’s inability to establish the locus standi to present a petition under what is now s.124(1) of the 1986 Act. The case of an undisputed debt with a genuine and serious cross-claim is different, in that the dismissal or staying of the petition can only be a matter for the discretion of the court, albeit that its exercise may have been narrowed by authority.”
“The works we agreed”
“Confirming yesterday’s discussions with yourself and Mr Ahmadi, the agreed contract value to the ground floor and mezzanine works...”
“A total contract value agreed with Mr Ahmadi of£615,828 .”
“Revised versions of the schedules would follow, including works to the basement,£39,692 , which was not discussed yesterday, but I assume this will take the form of a separate JCT intermediate contract and revised programmed duration is from14th May 2012 until28th August 2012 , based on yesterday’s agreed start date.”
“Please sign and witness page 19 and Thorntons then need to countersign and witness.”
“The contract was sent to the Company for signature on11th May 2012 . The contract was not in fact signed by the Company or the Respondent, but I am advised and verily believe that the Respondent’s works were carried out on the basis of such contract.”
“This exhibit to Mr Ahmadi’s statement” -- that is the draft of the contract prepared by Mr Dunn -- “is the first time anyone in ATCL has seen such a draft contract or that letter of11th May 2012 . That said, I acknowledge there was reference in the pre-contractual correspondence to an IFC contract and reference to such a form of contract was also made by JDAL in correspondence and site meetings. Nothing turns on the form of contract...”
“The concern I have, which I have voiced before, is that there is no agreed contract sum and breakdown of costs. There is no formal contract which sets out the programme, valuation payments and retention amounts etc. Therefore, both parties are at risk and the contractual arrangements are fluid. I cannot accept responsibility for this contractual situation, especially as I prepared a JCT contract at the outset, which set out all the contractual agreements.”
“28. The fourth argument advanced by Counsel for Angel was that unless I can specify an exact sum which is due from Angel to BG then I must grant an injunction to restrain further proceeding on the petition: and that I can only reach that exact sum by undertaking a line by line examination of each of the invoices rendered on the Corporate Account and the SME Account for the entire duration of the relationship between Angel and BG. Only in this way would the exact sum and its precise constitution be established, and only in this way could Angel know how much it had to pay and what liabilities were thereby discharged. 29. I do not accept this submission. On this application” -- which is was a similar application to that before me -- “the question is whether or not there is an indisputable debt owed by Angel to BG sufficient to support a winding up petition. There may be uncertainty about the precise sum: but the court at this stage is not concerned to determine what could be proved in a winding up. It is concerned to see that the petitioner is indisputably a creditor in a sum exceeding the statutory minimum and so entitled to present a winding-up petition. It will be for the parties to agree or make their own respective judgments about what cannot be disputed and what can properly be disputed (and the court will be alert to identify every case where the winding up process is being used to exert pressure to pay a debt that is bona fide disputed on substantial grounds rather than to litigate it). In Re A Company No.2340 (2001) Blackburne J held:- ‘At the end of the day the question is whether or not there is a debt owed by [the Debtor] to [the Creditor] over and above£750 , sufficient therefore in amount to support a winding up petition, which is not bona fide disputed on substantial grounds. In my judgment, there clearly is. Even making allowance for the various points which [Counsel] has raised, on any view further substantial sums are owing. In my judgment therefore, it cannot be said that if [the Creditor] were now to present a petition to wind up [the Debtor] it would be an abuse of process. True it is that there is a dispute as to the precise amount of the sum to which [the Creditor] is entitled but, on the evidence I have seen, I am satisfied that there is no genuine dispute… as to the existence of an indebtedness on the part of [the Debtor] to [the Creditor] amply sufficient in amount to support a winding up petition. I propose therefore to dismiss this application.’”
“My approach is the same.”
“If I ask the question "Is there a debt owed by Angel to BG over and above£750 which is not bona fide disputed on substantial grounds?" then I would answer that question in the affirmative. In my judgment there clearly is, even making the allowance for all of the points taken by Angel. I recognise that there is a dispute as to the precise amount, but on the evidence it seems to me plainly to exceed£750 and to be of the order of£100,000 .”
“In that time he again told us that he wanted to pay, but was not able to do so. He said that he would pay it in full, but could not afford to pay now (even though much of the work had been done months earlier) but would have to wait until the restaurant was performing better.”
“Mr Ahmadi again said that he could not afford to pay, but he would pay by instalments when the Company could afford it.”
“The restaurant venture was funded by the bank and myself in the sum of£3m .”
“from my own personal funds.”
“The director believes that the Company has sufficient capital funding and cashflow from trading, which commenced in spring 2013 to enable it to manage its creditors and commitments in the near future and to build cash surpluses in the longer term.”
“The prices for the works increased, because the specification changed and accordingly the scope of work changed.”
“The Respondent claims that I changed the initial quote from a steel balustrade to a brass and glass balustrade, which would also be curved. They claim that as a result of the changes, the price has increased. I can confirm I have never changed the design of the balustrade. It was always going to be curved brass with glass panelling. I was initially quoted£17,000 for this. By the time of the final count I was charged£42,750 .”
“...it was not until we were on site that Mr Ahmadi indicated he wanted to use some existing brasswork salvaged from a previous restaurant (see MG1 page 3) -- and that is supported by contemporaneous correspondence -- “and that he wanted glass panels instead of metal rails, including the curved sections which formed the majority. His material was unsuitable. We had to design and build a new staircase from scratch. Steel is stronger than glass and easier to work. Specialist firms are needed to produce suitable curved and toughened glass. Instead of a 38mm diameter brass envisaged for the handrail in the earlier drawings (where steel was to be used), we had to use a 51mm brass tube to provide the necessary structural stability to address the use of glass and the positioning of the uprights settled on by Mr Ahmadi. That led to a substantial increase in brass cost, and inevitable curved glass costs more than steel. It is clear that the design change ended up costing more, and taking longer.”
“Because the works could not proceed at anywhere near the programme for the reasons set out above, far less work could be done than anticipated, and as a result at the end of the 30 days a reduced valuation had to be issued for that period, following discussion with Mr Ahmadi who was acting arbitrarily as the Company QS (quantity surveyor). ... This forward valuation procedure forms the basis of Mr Ahmadi’s assertion that we were over-valuing. The combination of the advance valuations and the delayed programme made it inevitable that initial forward valuations would be over-estimates.”
“Agreed price£2,885 .”
“Vanity unit to male toilet, 5-bowl vanity unit with black lacquered front panel and marble top, approximate length 2,800mm,£2,885 .”
“Further to our recent meetings and discussions, please find attached the updated and revised schedule for the project. We have reviewed the project up to drawings received approximately 10 days ago and historical site developments. We have not fully reviewed the drawings issued at yesterday’s meeting. We took the decision to produce one schedule so that all parties are aware of the potential revised overall contract value.”
“1.68 meter long vanity unit in black granite with a 50mm down stand and 275mm high splash back. 150mm deep black granite shelf with 175mm up-stand behind. Four number lockable black paint lacquered doors below to house for a number of waste paper bins.”
“The Respondent did not complete the works it was contracted to undertake.” and then exhibits a set of photographs with narrative on the face of the photographs and says at paragraph 15: “By9th March 2013 the work was still not completed and I requested the Respondent to leave the site, which it did, save for two occasions when a painter attended the site, the Respondent has not returned to complete its works and indeed the Company has made arrangements to complete some of the work with other contractors.”
“Other than matters which I have already referred, namely the electrical installations, plumbing and preliminaries, is ventilation in the office, which he says the wall to the office has been constructed in a way that it does not incorporate the ventilation. There is no ventilation in the office and I can only really use it for very short periods.”
“Until that aspect was dealt with, and final drawings were prepared by Ventserve, and by the Company’s directly engaged kitchen installers (Universal) and JDAL, so that the services specification and loading was known, it was impossible to progress with first fix electrical or plumbing works.”
“AHS Steel were still not on site and were three weeks late on the programme. By 12th July it was recorded that the district surveyor for the City of London had reported concerns about the standard of workmanship with the steelwork to the architect. The client, that is Mr Ahmadi, had met the district surveyor, Mr Kamal Hamanaro yesterday and discussed steelwork. Mr Azad of AHS Limited had reported to the architect today that they are to remove steel frames already installed and reconstruct frames properly and AHS state that all steel, including the curved sections, are on order and within two weeks they will complete works. It is noted that AHS are already three or four weeks late on agreed programme.”
“I feel that as the designers we need to clarify that we had no part in appointing AHS as mezzanine steelwork contractors of this project. We have had no opportunity to assess their capabilities to perform on this project prior to their appointment and that we do not consider them to be competent to carry out their part of the contract.”
“In view of the programme and the time to be made up and the promises to perform I expected far more work to have been done by AHS than I saw. What I did see was better than last week’s work, but there are still problems to be corrected before they go too much further...”
“Whilst AHS Steel had improved works on site, concerns still remained about certain fixing and welding details, weekly site checks were necessary and further fixing details would be issued. ABP would not at that time certify the steelworks. It is noted that curved beams are on site and the Respondents reported that AHS were delaying works and there were not enough operatives on site.”
“I think that for all parties concerned we should monitor the situation for the steelwork. While it has been and is delaying the overall programme, we have to make sure the work is carried out correctly before further works progress in those areas.”
“How much delay do you believe AHS Steel have caused? Mr Ahmadi should know this, as he may claim costs against them for these delays.”
“There was now a problem with the curved stairway sections delivered to site and Mr Woods himself said that he had briefly touched on the programme and he was concerned regarding the overall programme for the project, but with constant changes and delays in steelwork etc, in some respects it is better we have not manufactured all the joinery items, until it became clear on the design and dimensions. As you are aware, even up to late last week design changes have been made.”
“At this time Thornton have to give Mr Ahmadi an updated programme based on current conditions. Thornton did table a revised programme on 25th July, but since then further advice drawings have been issued, due to client changes.”
“The Respondent also states that they were delayed as a result of the other contractors that were brought in. I cannot understand how this can be said, particularly when items such as the kitchen installation were ready and delivered in August 2012. It was in the basement and sat there until the Respondent was ready to accept it for installation.”