“ 1.5 "the Completion Date" means28 July 2006 subject to completion of works (if any) set out in an agreed snagging list prepared by14 July 2006 to the satisfaction of the buyer ”
“ Our clients have inspected the site and found that it is far from finished and not yet in a state where it is appropriate to prepare a final snagging list. Our client's estimate is that the building will not be ready until the end of August. While this will be reviewed, you should appreciate that the state of the building affects the completion date fixed by clause 1.5 of the contract. In particular, we are advised that the courtyard needs to be levelled and paved, the fountain installed, the electrical provision for the building has yet to be installed, floors remain to be laid. Nevertheless, our clients have instructed [us] to pass on to you their enclosed cheque for£100,000 being a further payment on account, which you are authorised to pass on to your clients. ”
“… your client has an amended the original drawings and plans and has insisted on extras, which have delayed their development. I enclose for you a list of extras which your client insisted upon. We feel as it is your clients insistences (sic) extra items are being carried out, it is unfair for you to penalise our client and extend the completion date to August. ”
“ further to the above matter which has been delayed since this time last year, we have been advised by our client that the property is now ready for your clients to attend and carry out a snagging list. Could you please arrange for your clients to contact has direct so that this matter can now proceed towards completion. ”
"… following our telephone conversation of15 June 2007 in order to ascertain what progress has been made to carry out the work that we had previously agreed was required, I was pleased to be advised that people were in the process of being hired to carry out this work. I would be grateful if you would ensure that this work is carried out at the earliest possible opportunity, as the building is listed and falls within a conservation area. I will be re-evaluating this case in a month's time; by then I would hope that the required works are well underway. "
“PLEASE NOTE Most importantly there are two certificates which are required for building completion: - 1) Part P electrical certificate 2) Completion certificate for Building Control. Plus any conditions put on the property by the authorities which I know there are several. There is a lot more work yet to be done on the property which may take months before the end result. ”
“ This development has been reasonably constructed with materials commonly adopted for developments of this type and age… However, there are a number of legal/technical issues and letters of confirmation in respect of discharging conditions which should be obtained by your solicitor for our review, as requested throughout this report. Subject to the provision of this information and satisfactory resolution of the issues raised in this report, in particular remedial works to snagging items identified, from a building surveyor's perspective you would be in a position to proceed with the purchase of the freehold of 28-29 Tenby Street.”
“… we have revisited the property on4 March 2009 and can confirm that the snagging works have been completed satisfactorily… We understand that the electrical certificates are available and that a review has been undertaken of the heating within the property which indicates that the heaters are appropriately sized for the size of the rooms etc. The Building Regulation Completion Certificate is also available for review. We therefore consider that the property is currently in a satisfactory condition and suitable for occupiers and that it is suitable for the sale to be progressed. ”
“ We write further to the Notice to Complete served on10 August 2009 . Our client has been advised that the works detailed in the snagging list remain incomplete and therefore we consider the contract to be rescinded. We seek payment of the deposit monies of£200,000 together with interest and our client's legal and surveyors fees … if payment is not received, we will prepare court documentation for issue. ”