‘The District Judge was wrong in law on the facts as he found them when he decided that although he was bound by the decision in George Parke v. The Fenton Gretton Partnership (which was a case admitted by the District Judge as being ‘on all fours’ with the present case) he would nevertheless exercise his discretion in the Respondent’s favour.’
‘On11 February 2008 the Referring Party accepted your repudiation of the contract. On23 June 2008 the Referring Party submitted as its claim for damages arising from the Responding Party’s breach of contract its assessment of the value of the works it had completed at the date of your repudiation of the contract in the sum of£189,134.69 and indicating that it was due a further payment of£86,730.24 . You have failed to respond to the Referring Party’s assessment of the value of the works it has completed and have not made any payment in respect of the same. In the circumstances a dispute exists between the Referring Party and you as to the sums to be paid in respect of the work the Referring Party has undertaken at your instruction. The Referring Party seeks an award of damages for your breach of contract and an adjudicator will be asked to determine what further sums if any are to be paid as damages to the Referring Party in respect of the works it carried out at the property and will be asked to make an award that: 1. That the Responding Party pay the Referring Party damages of£86,713.24 or such sum as the adjudicator shall decide being the unpaid value of the works, pleaded by the Referring Party at the date of the Responding Party's breach of contract. 2. …’
‘30. It therefore seems to me that there is no real issue of bankruptcy of Mr and Mrs Shaw. There is no real issue of the right to pursue the arbitration being lost because of a supervening bankruptcy. It seems to me that this is simply a decision for Mr and Mrs Shaw as to whether they choose to pay the amounts due or not. To set aside the statutory demand simply to require the respondent to pursue enforcement by other means of a sum that (it is quite clear both from the facts of the case and all the authorities I have referred to) is undoubtedly due, is a step which, in my judgment, on the facts of this case [is] not one which the court should take. I do have a discretion. For those reasons, I exercise my discretion and decline to set aside the statutory demands.’
‘Before the Court can interfere it must be shown that the Judge has either erred in principle in his approach or has left out of account or has taken into account some feature that he should, or should not, have considered, or that his decision was totally wrong because the court is forced to the conclusion that he has not balance the various factors fairly in the scale.’
‘I would not rule out the possibility that ability to pay may be a relevant factor in certain circumstances. But for the reasons that I have given, I find it difficult to conceive of circumstances where ability to pay can be the sole or principal reason for refusing to set aside a statutory demand. No such circumstances have been identified in the present case.’
‘11.5.1 Where the court is faced by an application to set aside a statutory demand issued in support of a judgement based upon an adjudication award it has a discretion as to whether or not to set aside that statutory demand. In exercising that discretion the court should give great weight to the policy of the 1996 Act, namely that adjudicator's awards are to be paid and execution of judgments based upon adjudicator's awards should not be delayed pending final determination of the dispute whether by litigation or arbitration. However, in exercising the discretion the court should be alive to the possibility that bankruptcy proceedings could be used to stifle genuine litigation to finally resolve the dispute provisionally determined by adjudication. Therefore, if the evidence suggests that bankruptcy proceedings are being used to prevent a party pursuing a genuine dispute the statutory demand should be set aside. If however the position is that the court has refused a stay of execution based upon the inability of the claimants to repay an award (as it has in this case) and, if it is clear that the debtor has the funds to pay the judgment sum (as is the case in this matter) then, the discretion should be exercised against the setting aside of the statutory demand. 11.5.2 A late issue of a statutory demand shortly before the final determination of the dispute by arbitration or litigation would also lead to the exercise of the discretion to set aside the demand on the grounds that it was being used oppressively.’
‘The authorities are illustrations of the well established practice of the Companies Court that, if a company has a genuine and serious cross claim, which is likely to exceed the petition debt, the court will normally exercise its discretion by dismissing the winding up petition and allowing the company the opportunity to establish its cross claim in ordinary civil proceedings. A company should not be prevented from raising a cross claim in winding up proceedings simply because it could have raised or litigated the claim before the presentation of the petition or it has delayed bringing proceedings on the cross claim. The failure to litigate the cross claim is not necessarily fatal to a genuine and serious cross claim defeating a winding up petition. However, in deciding whether it is satisfied that the cross claim is genuine and serious, the court is entitled to take into account all the relevant circumstances, such as the fact that a company has not even attempted to litigate the cross claim, or that there are reasons why it has not done so.’
‘85. the objective which underlines the Act and the statutory scheme requires the courts to respect and enforce the adjudicator’s decision unless it is plain that the question which he has decided was not the question referred to him or the manner in which he has gone about his task is obviously unfair. It should be only in rare circumstances that the courts will interfere with the decision of an adjudicator … 86. It is only too easy in a complex case for a party who is dissatisfied with the decision of an adjudicator to comb through the adjudicator’s reasons and identify points on which to present the challenge under the labels ‘excess of jurisdiction’ or ‘breach of natural justice’ … The task of the adjudicator is to find an interim solution which meets the needs of the case. Parliament may be taken to have recognised that, in the absence of an interim solution, the contractor or sub-contractor or his sub-contractors will be driven into insolvency through a wrongful withholding of payments properly due. The statutory scheme provides a means of meeting the legitimate cash flow requirements of contractors and their sub-contractors. The need to have a right answer has been subordinated to the need to have an answer quickly. 87. In short, in the overwhelming majority of cases the proper course of the party who is unsuccessful in an adjudication under this scheme must be to pay the amount that he has been ordered to pay by the adjudicator. If he does not accept the adjudicator’s decision is correct (whether on the facts or the law) he can take legal or arbitration proceedings in order to establish the true position …’ (b) The paying party can, as Chadwick LJ indicated, issue a claim form or an arbitration notice in order to obtain a substantive decision on the merits, and that may lead to some or all of the money, originally ordered to be paid by the adjudicator, being repaid to the paying party. But that does not affect the temporary finality of the adjudicator's decision, or the directive that that decision must be complied with and, if necessary, enforced by the court. (c) The fact that the paying party has commenced substantive arbitration proceedings is usually irrelevant to the successful parties right to enforcement (and indeed execution) of any judgment: see Harlow and Milner v. Teasdale (No 2)[2006] EWHC 535 (TCC) . (d) The only authority of which I am aware in which the existence of ongoing arbitration proceedings affected the mechanics of enforcement is my decision in Kier Regional Ltd v City & General (Holborn) Ltd[2008] EWHC 2454 (TCC) . But that was a case where the enforcement of an adjudicator's decision had in fact been ordered by the court in 2006. The difficulty was that the claimants had done nothing to execute that judgement and only sought charging orders and the like at a time when the substantive arbitration was only a few weeks away. In those wholly exceptional circumstances I granted a stay of execution.’
‘In my judgment it cannot be right that an employer or main contractor can be made bankrupt when it is known that he has proper proceedings on foot which, if successful, will result in a payment to him. I do not accept that the scheme of the 1996 Act is that an adjudication can be pursued to bankruptcy no matter the underlying state of account. The court would be required to close its eyes to the overall position, which in the context of bankruptcy is in my judgment wrong in principle.’
‘Where the statutory demand is based on a judgment or order, the court will not at this stage go behind the judgment or order and enquire into the validity of the debt nor, as a general rule, will it adjourn the application to await the result of an application to set aside the judgment or order.’