“My business is concerned with the retrieval of used concrete products from such sites as roadway renovation, building sites under demolition and airport runways and thereafter the processing and crushing of these otherwise wasted materials into recycled products to be used instead of natural materials such as stone and gravel. … I have 18 lorries and have equipment worth in the region of£2,000,000 …. I employ 50 full time and 3 part time staff.”
“Fowles Crushed Concrete Ltd undertakes only the reception, recycling and re-sale of concrete and soil and operates solely from Robb’s Nurseries. FCC has three members of staff being one concrete salesman, a secretary and a bookkeeper. It has one car and no other equipment.”
“This activity has been carried out since 1982 but became a larger business after 1992 when Quicks Limited went bust and left the site.”
“I also began importing high quality soil which I intermixed with the lower quality soil in the large heap at the north-western end and started selling off the mixed soil.” (Emphasis added)
“You couldn't expand with him. What he give you is what had.”
“The making of a material change in the use of land to use for a haulage contractors yard including the stationing of portable buildings for use as offices …, the parking and storage of trailers and vehicles, the installation and operation of a concrete crusher and soil hopper and the storage of materials including soil concrete and excavated materials.”
“There are 3 separate businesses operating in the area described in paragraph 9. The areas occupied are not clearly defined or physically separate. Vehicles belonging to the firms are mixed up although buildings appear to be occupied on an individual firm basis. Fowles Haulage occupy buildings 11 and 14, park their 6 lorries on the L-shaped hardstanding area and conduct the concrete crushing operation.”
“It will be appropriate to impose conditions on the grant of planning permission, the effect of which would be to ensure that the various elements of the work are carried out in accordance with the intended phasing proposals.”
“The County Council may wish to grant planning permission only for a limited period, either to enable the extent to which the site is operated in a satisfactory manner to be monitored or in response to Green Belt policy. In that case the Council would be able to impose a time limited condition. In view of the extent and cost of the works envisaged as an integral part of the current proposal, to achieve the substantial environmental and visual improvements to the site, any limited period should not be less than 7 years. The works, much of which are required as the result of the actions of previous occupiers of the land and not the applicant, will need to be financed out of the revenue and profit of the recycling operation. A period of less than 7 years would not give sufficient certainty or financial return to enable the works to be put in hand.”
“Use of land for the reception, processing and recycling of waste concrete and the carrying out of engineering operations to restore and landscape part of the site.”
“Use for the reception, processing & recycling of waste concrete”
“The permission hereby granted shall be for a limited period of 7 years from the date of issue whereupon the use will cease, all fixed and mobile plant and any stockpiles of processed or unprocessed material shall be removed, all roadways and hardstandings broken up and the site restored in accordance with the details contained in the application and such details as may be subsequently approved under condition 12.”
“At the time of the Council’s initial site visits (early Summer 94), the repair/maintenance of the fleet of lorries was carried out within a group of dilapidated agricultural buildings. The inadequacy of the buildings meant that very often repairs were carried out in the open yard. More recently the operator has been using one of the former brick-built agricultural buildings lying within the adjoining site.”
“Use in connection with crushing and recycling of waste concrete to produce aggregate and fill.”
“I accept that, should the concrete crushing use not be granted permission in this appeal, then this building would not require to be retained. Its sole function is related to the concrete crushing and recycling use.”
“Crushing and reprocessing of waste concrete and haulage yard”
“Workshop for servicing of vehicles associated with the concrete crushing use”
“that the tenant ought not to be granted a new tenancy in view of other substantial breaches by him of his obligations under the current tenancy or for any other reason connected with the tenant’s use and management of the holding.”
“(1) This section applies where planning permission for carrying out any development of land has been granted subject to conditions. (2) The local planning authority may, if any of the conditions is not complied with, serve a notice (in this Act referred to as a “breach of condition notice”) on— (a) any person who is carrying out or has carried out the development; or (b) any person having control of the land, requiring him to secure compliance with such of the conditions as are specified in the notice. (3) …. (4) The conditions which may be specified in a notice served by virtue of subsection (2)(b) are any of the conditions regulating the use of the land. (5) A breach of condition notice shall specify the steps which the authority consider ought to be taken, or the activities which the authority consider ought to cease, to secure compliance with the conditions specified in the notice. (8) If, at any time after the end of the period allowed for compliance with the notice— (a) any of the conditions specified in the notice is not complied with; and (b) the steps specified in the notice have not been taken or, as the case may be, the activities specified in the notice have not ceased, the person responsible is in breach of the notice. (9) If the person responsible is in breach of the notice he shall be guilty of an offence.”
“(11) Where— (a) an enforcement notice in respect of any breach of planning control could have required any buildings or works to be removed or any activity to cease, but does not do so; and (b) all the requirements of the notice have been complied with, then, so far as the notice did not so require, planning permission shall be treated as having been granted by virtue of section 73A in respect of development consisting of the construction of the buildings or works or, as the case may be, the carrying out of the activities.”
“Anyone who had any experience of the operation of the former law relating to the enforcement of planning control knows that it was disfigured by time-consuming litigation over technicalities, raised by determined litigants who sought to evade the effects of enforcement action taken against them by local planning authorities on behalf of their local communities. From time to time, there were judicial explosions on the topic.”
“I am quite satisfied that one of parliament's main purposes in 1991, in overhauling Part II of the 1990 Act, was to spare those like Mr Eyre the pain of returning to those arid technicalities.”
“When the Council refused the application on17th July 2001 authority to serve enforcement notices was given. However, when these were served and subsequently appealed it was not possible to consider all appeals at one Planning Inquiry. The enforcement appeals were to be heard at an inquiry on 21/01/03 but at the opening the Inspector advised that the relevant restoration conditions did not have timescales attached and were therefore unenforceable. Accordingly the enforcement notices were withdrawn.”
“Given the failure of the Council’s previous enforcement efforts to secure restoration and BAA’s legal commitment to restore the site, it is no longer considered necessary to pursue enforcement action against those conditions associated with restoration of the site…”
“It is the present intention of the LPA that any further action which they might take would be by means of Enforcement Notices and not by any other means and in any event the LPA will not for a period of 3 months from today take any further enforcement or other action in respect of the Site.”
“The making of a material change in the use of land to use for a haulage contractors yard including the stationing of portable buildings for use as offices …, the parking and storage of trailers and vehicles, the installation and operation of a concrete crusher and soil hopper and the storage of materials including soil concrete and excavated materials.”
“For the purposes of this Act uses and operations are lawful at any time if— (a) no enforcement action may then be taken in respect of them (whether because they did not involve development or require planning permission or because the time for enforcement action has expired or for any other reason); and (b) they do not constitute a contravention of any of the requirements of any enforcement notice then in force.”
“Mr Fowles maintains, and over the years I have observed, that for over 10 years he has carried on a variety of businesses on the site beside the concrete crushing and related transport and storage, including an independent haulage business with ancillary vehicle parking and maintenance, waste skip storage and hire service; and a demolition business.”
“Q. Based on the evidence that you have seen on the site, based on your site visits and your knowledge over the years, when do you say the breach of planning control by the making of a material change of use occurred? A. I don’t think I could deduce a date from the sort of visual observations that I have conducted over the years.”
“Looked at in that way, there may not be a change in what has occurred. It may be that what had previously been permitted under the 1994 permission, for example, did not include these other uses. So it is not a change from that use, but, if you like, it is a change from the previous situation.”
“So long as the mixture of uses on the premises, which the judge held to be the relevant planning unit, remain substantially unchanged, there would be no material change of use. Those uses, as already indicated, included workshops, offices, stores, messing facilities and parking for a variety of vehicles both under cover and in the open. This is just such a mixture of uses as would be required by a wide variety of undertakings whose business was the operation of some kind of vehicular transport and who required a base from which to operate. Whether, in any particular case, the proposed use of the premises by such an undertaking would involve a material change of use would depend on the detailed nature of the proposal. But it would be of no relevance to the use of the premises to inquire for what purpose the vehicles parked there were to be used when they left their base.”
“I had a pair of gates about halfway up it between the shared part and the present entrance to my yard which I locked every night. They were broken down one night so I moved them up to the present entrance and now I lock them with a large digger behind them to make them impregnable as the entrance is narrower there.”
“Included within the application site are buildings which are used for the maintenance of the plant and vehicles associated with the operation, a weighbridge on the access road and a control office adjacent to the gate into the site.”
“Notwithstanding the above I must report that since your officers first direct involvement in this site (Summer 94) considerable progress has been made. The access used by a very large number of HGV’s was nothing more than a mud track. The entire length of the access from within the site and up to the highway boundary has now been laid in concrete. The actual yard has been substantially tidied up, a number of old buildings demolished and resurfacing applied to a high standard. … A 3m high barrier fence has been erected to help protect the few residential properties adjoining the approach road. Gates have been installed so restricting unauthorised access.”
“A range of buildings exist on the adjoining site which is under the control of SPS and Mr Fowles does have an arrangement with them to use Building No 1 (adjacent to the Control Office on his site) to maintenance purposes.”
“This activity has been carried out since 1982 but became a larger business after 1992 when Quicks Limited went bust and left the site.” (Emphasis added)