“After the application date, applicants will not have the automatic right to update or expand their submitted applications. However, applicants must still fully engage with any requests for further information issued by Ofgem. In addition, every applicant is required to keep Ofgem informed by email about material developments and changes that may impact project deliverability by the applicable deadline (of 2030 or 2033).”
“..by the time the Claimant submitted its Application, it was clear to the Claimant (and to all other interested parties)….. that: a. Ofgem intended to progress the Scheme at speed, in the public interest; and b. Given that, applicants were expected to act competently and efficiently to avoid steps that might cause delay to the progress of the Scheme. … I do not consider that there could be any doubt whatsoever about the requirement to provide all relevant information in the application, on time.”
“The application does not include a full financial model which limits our ability to assess the robustness of the commercial case. Screenshots and assumptions, while helpful, do not provide sufficient transparency or granularity to evaluate financial viability with confidence”
“For example, as mentioned in the ECAF documents, Ofgem envisaged that it would take account of information supplied in response to queries that it raised on applications. Second, as reflected in the “minded-to” decisions themselves, Ofgem reserved a residual discretion to consider additional information provided that it could not be characterised as such that it should have been “properly included” in the application. For example, a scenario in which a local planning authority informed an applicant after the9 June 2025 cut-off date that information previously provided by it to the applicant – and used in support of the application - was incorrect. Such information would be clearly relevant to the application, but could not properly have been included by the applicant in its application. We would also have been willing to consider information if (depending on the circumstances) the failure to comply with the deadline was either caused or contributed to by: (i) fault on the part of Ofgem, or (ii) any external or objective circumstances outside of the Claimant’s control.”
“We would ask that you consider this evidence which was not provided due to an unfortunate and unintentional typing error. This model is clearly referred to in our response as is presented exactly as was at 7th June.”
“After careful consideration, we are of the opinion that Eligibility Criteria of Deliverability has not been met for the reasons already outlined in the minded to decision letter. After consideration of your representations, we acknowledge the clarification provided, including the submission of a financial model and references to prior investment experience, the following remain the reasons for insufficient evidence at this stage: Incomplete Financial Model at Time of Submission: The financing plans sub-criterion specifically requires a financial model to be submitted. The absence of a full financial model in the application limited our ability to assess the robustness of the commercial case. The late submission of this material, while noted, has not been considered in the eligibility determination. As set out in section 2.13 of the ECAF, applicants do not have an automatic right to update or expand upon submitted applications. We have therefore made our assessment on the basis of the documentation properly submitted by the deadline of9 June 2025 to maintain fairness, transparency, and confidence in the scheme’s outcomes.”
“The Claimant had been given a fair and equal opportunity to comply with the Eligibility Stage application deadline, and had been informed prior to the submission of its Application of the importance of providing a complete application and of the consequences of not doing so. The sole reason for the Claimant’s failure to comply with this deadline was its own fault or carelessness… Other bidders would have spent significant time and effort before the deadline ensuring that their applications were complete and compliant. It would be unfair to the other bidders seeking to be awarded LDES C&F if the Claimant was given an additional opportunity, and time, to submit additional material after the deadline had already expired.”
“The Defendant has breached the requirements of procedural fairness by ignoring the representations made to it in the process, including the provision of the Financial Model by the Claimant promptly following the MTD.”
“57…..the fundamental requirement of the second limb....is to give an opportunity to a person whose legally protected interests may be affected by a public authority's decision to make representations to that authority before (or at least usually before) the decision is taken..”
“Our role is principally to correct errors of law made by public authorities and ensure that fair procedures have been complied with.”
“First, the obligation on the decision-maker is only to take such steps to inform himself as are reasonable. Secondly, subject to a Wednesbury challenge… it is for the public body and not the court to decide upon the manner and intensity of inquiry to be undertaken…Thirdly, the court should not intervene merely because it considers that further inquiries would have been sensible or desirable. It should intervene only if no reasonable authority could have been satisfied on the basis of the inquiries made that it possessed the information necessary for its decision. Fourthly, the court should establish what material was before the authority and should only strike down a decision not to make further inquiries if no reasonable authority possessed of that material could suppose that the inquiries they had made were sufficient.”
“the critical factor which gives rise, or may give rise, to a duty to seek clarification is where the tender as it stands cannot be properly considered because it is ambiguous or incomplete or contains an obvious clerical error rendering suspect that part of the bid. If the inability to proceed with a bid, which may be an advantageous addition to the competitive process, can be resolved easily and quickly it should be done, assuming there is no change to the bid or risk of that happening. If there is an obvious error or ambiguity or gap, clarifying it does not change the bid because, objectively the bid never positively said otherwise.” ii) However, as Mr Sinclair accepted in his reply, the public law issues arising out of his pleaded grounds of challenge do not raise the question whether the Decision was proportionate. There is no “read across”