“I accept that in the First List the description of development subject to permission CA.49 differs from that given on the actual decision notice for that application, but to my mind this has no bearing on this matter. I am clear it is unambiguous that the First List includes all of the site subject of permission CA.49, and so includes the Green Area, Blue Area and Red Area.”
“41. Under Condition 1 permission CA.49 allowed excavations within the Green Area, and it was accepted that work in connection with this element of the permission was undertaken immediately the permission was granted. Moreover, it would appear that the on-going development then contemplated involved a quarry void continuing to be present. This was because Condition 4 prohibited tipping outside of the excavated area, while Condition 6 said that any further fixed plant that may be required in connection with the undertaking had to be sited on the floor of the quarry. 42. I see no reason why permission CA.49 would have prevented a second quarry void being opened in the Green Area, provided that there was continued compliance with the conditions imposed. This would have meant that tipping and further fixed plant associated with the second quarry would have had to be in the original void initially, until such times as the second quarry void became large enough for them to be accommodated there. 43. However, by infilling the original quarry void with landfill and then restoring the land, nearly all visual evidence of that previous permission in the landscape was swept away and no quarry presently remains. As a result, it would not now be possible to resume permission CA.49 by excavating elsewhere, as, at the outset at least, there could be no compliance with Conditions 4 and 6. This is because tipping would have to take place outside the excavated area and further fixed plant could not be confined to the quarry floor, as no such floor would exist. 44. Therefore, noting the Pilkington judgment, whilst I accept that it is possible to excavate mineral from elsewhere in the Green Area, for the reasons given above I nonetheless consider that the total infilling of the quarry under the landfill permission has made it physically impossible to carry out that which was authorised, as the works cannot be in accordance with the associated conditions. Consequently, in connection with the Green Area, I consider that permission CA.49 cannot be considered as a relevant planning permission capable of being reviewed under the ROMP procedure. 45. I have also had regard to the judgment known as Hillside, but I see nothing in that to lead me to different conclusions on the status of the Green Area. 46. Accordingly, I conclude that permission CA.49 can no longer be treated as a relevant planning permission insofar as it concerns the Green Area.”
“48. In this regard I have been particularly mindful of the LaFarge judgment6. Although this is a Scottish judgment, made by the Inner House of the Court of Session, given the close parallels with English legislation I consider it to be strongly persuasive. It concerned a minerals development where permission had been granted in principle with conditions to require full details of the operations before works began – conditions that seemed to be similar in effect to Condition 2 on permission CA.49. The judgment went on to address the status of land akin to the Blue Area at High Close Quarry, where details in connection with the condition had been neither submitted nor approved. It differed though to the situation before me as the challenge against the Scottish Ministers was, among other things, on the omission of this land from the First List. However, this difference, to my mind, has no particular bearing on the application of the judgment insofar as it concerns this case. 49. That judgment found that the land to which the relevant permission relates means land in respect of which specific minerals development has been authorised7. Lord Marnoch also expressed the opinion that, in order to meet the definition of a relevant planning permission, the full and final permission for the carrying out of operations relating to minerals development is required8. However, by approving only the principle of the winning and working of minerals, the permission subject of that judgment merely prevented subsequent opposition to the principle of such development. It did not authorise the activity of winning and working of minerals throughout the site, as that would only occur once the details were discharged and approval given in accordance with the conditions. Accordingly, the judgment found the parts of the site that enjoyed the benefit of a relevant planning permission were only those where specific minerals development had been subsequently authorised through the discharge of the relevant condition. It did not include the other areas, which were akin to the Blue Area at High Close Quarry, where the permission in principle had been granted but the outstanding details had never been submitted, and so the winning and working of minerals had never been authorised. 50. In my opinion, although the Blue Area has undoubtedly been subject of a valid planning permission for what I have found to be the winning and working of minerals, such development cannot now take place there as it has not been authorised by the approval of full details by the MPA, under the discharge of Condition 2. As such, I find there is not a relevant planning permission for the Blue Area.”
“34. The 1954 Permission was, by the express terms of the grant, for “the continued working of High Close Quarry” such that the quarry had necessarily to continue in existence under that permission for its working to be continued. The conditions of the 1954 Permission reinforce that position with their requirements, dependent on the continuation of the quarried area, for no tipping of future waste material to a height exceeding the original ground level, for no tipping of waste material to take place outside the excavated area and for any further fixed plant which might be required to be sited on the floor of the quarry. These conditions are intrinsically tied not just to the existence of the quarry void at the time of grant in 1954 but also to the ongoing existence of the same thereafter so that there continued in existence the excavated area into which waste could be tipped and the quarry floor on which any required further fixed plant could be sited. Further, there was no requirement for any restoration of the quarry, whether on a phased or progressive basis or at all. On the contrary, all that was required on conclusion of operations was that the site should be cleared of all pieces of plant and building material and left clean and tidy. Thus, it was contemplated that a quarry, albeit disused, would then remain. 35. However, once the void left in the Green Area when working ceased in 1956 was thereafter landfilled and restored under the Landfill Permission, High Close Quarry (or any quarry, even a disused one) ceased to exist and no continuation of its working in the Green Area was thereafter possible in any form but certainly not in accordance with the terms of the 1954 Permission with a remaining excavated area for the tipping of waste material and quarry floor for any required fixed plant. Just as in Pilkington the later construction of a bungalow under a second permission had “destroyed” a smallholding on which a previously consented bungalow was to be built (the basis of the impossibility in question)18, so here the landfilling in the Green Area has obliterated any quarry and thereby precluded any further working of the same. Any working thereafter would thus not be the continuation of what had gone before but the initiation of fresh working and the creation of a new quarry in the Green Area, not in accordance with the terms of the 1954 Permission.”
“What must be shown is that development in fact carried out makes it impossible to implement the second permission in accordance with its terms.”
“"The land to which a relevant planning permission relates" means, in my view, the land in respect of which specific minerals development has been authorised. In the circumstances of the present case land which satisfies that description comprises only the three areas identified in the 25 inch map. The remainder of the 600 hectares does not satisfy that description since winning and working of minerals in these areas has never been authorised. The reporters did not truly "cut down" 1965/79.”
“26. In my judgment the Lord Ordinary and the Inner House were plainly correct. Counsel for the appellant criticised their reasoning as inadequate. But once the general scheme of Schedule 9 of the 1997 Act is understood the first point is really quite a short one. The procedure at what the Lord Justice Clerk called Stage 1 is administrative and preliminary in nature. It involves the identification of sites and the setting of an order of priority for Stage 2 (with activity on a dormant site being frozen in the meantime). By contrast Stage 2, which is initiated in every case by a paragraph 9 application, requires decisions calling for planning judgment.”