“1. The challenge relates to a grant of outline planning permission (OPP) on23 October 2024 for residential development of up to 181 dwellings on a 7-hectare site at Heybeck Lane, Dewsbury. The site forms part of a larger 120-hectare parcel of land (MXS7) which was allocated for residential development in the Defendant’s Local Plan adopted in 2019. The remainder of the allocation, being by far the larger site, is known as the Leeds Road site and was subject to a contemporaneous application for OPP. 2. Applications relating to OPP in relation to both sites were determined by the Defendant’s Strategic Planning Committee (SPC) at a meeting on8 December 2022 . Both applications were the subject of resolutions to approve the proposals (subject to the SSHCLG not calling them in) and subject to the delegation of the issue of the decision notice to the Head of Planning on completion of a set of conditions and execution of a section 106 agreement. 3. The Officer’s Report in relation to the Heybeck Lane application cross refers to the Leeds Road report given that both sites dealt with similar issues and were being considered at the same meeting. The final list of conditions was completed and the section 106 agreement executed in relation to the claim site and OPP granted in relation to Heybeck Lane in October 2024. The OPP in relation to the Leeds Road site has not been issued but the claimant has indicated its intention to judicially review that grant of OPP as well.”
“[f]ailure to publish the section 106 agreement For anyone not familiar with planning procedures, this is shorthand for a binding agreement between an applicant for planning permission and the local planning authority, undersection 106 of the Town and Country Planning Act 1990 , whereby the applicant undertakes planning obligations enforceableby the local planning authority. in accordance with Article 40(3)(b) of theTown and Country Planning (Development Management Procedure) (England) Order 2015 [(the 2015 DMP Order)], rendering the grant of planning permission invalid.”
“Planning Application 2020/92350 Outline application for residential development (Use Class C3) of up to 181 dwellings, engineering and site works, demolition of existing property, landscaping, drainage and other associated infrastructure (amended and further information received) Land south of, Heybeck Lane, Chidswell, Shaw Cross, Dewsbury.”
“Biodiversity a) Contribution (amount to be confirmed) or off-site measures to achieve biodiversity net gain (only applicable if 10% can’t be achieved on-site b) Securing other off-site measures (including buffers to ancient woodlands, and provision of skylark plots).”
“Claimed biodiversity net gain not accepted. Earlier independent assessment identified a 14% net loss.”
“Ecological considerations 10.64 Chapter 15 of the NPPF and Local Plan policy LP30 apply. Of particular note, paragraph 174 of the NPPF requires the proposed development to achieve a biodiversity net gain. 10.65 Much of the commentary set out in the accompanying committee report for application ref: 2020/92331 is also relevant to the Heybeck Lane site. The same ecological surveys appended to chapter 14 of the ES submitted with application ref: 2020/92331 have also been submitted in support of the Heybeck Lane application. Similarly, a letter regarding bat surveys of lofts (dated23/08/2022 ) was submitted. Of specific relevance to the Heybeck Lane site, that letter noted that the loft of 39 Heybeck Lane has previously been converted and there is therefore no accessible loft space to inspect for bat presence. A High-Level Biodiversity Net Gain Assessment (01/11/2022 ), including findings of a walkover survey undertaken in October 2022, was also submitted. 10.66 At the Heybeck Lane site, the applicant’s biodiversity net gain calculation (using the Biodiversity Metric 3.1) confirms the proposed development would achieve the following net gains (post-intervention): • Habitat units: 10.03% • Hedgerow units: 10.61% 10.67 Of note, no net gain in river units is proposed, as the existing river unit baseline was found to be zero. It is also noted that the proposed 10.03% net gain in habitat units is partly reliant upon off-site interventions. 10.68 The proposed net gains are considered achievable. Delivery of the proposed off-site interventions would need to be secured via the recommended Section 106 agreement. 10.69 As with application ref: 2020/92331, the council is able to make an informed decision on the current outline application. Further surveys would be required at Reserved Matters stage (if outline permission is granted). The applicant has proposed a policy-compliant biodiversity net gain, and has met other requirements of relevant planning policies. Conditions and provisions (secured via a Section 106 agreement) can be applied to mitigate the ecological impacts of the proposed development.”
“10.70 Several Tree Preservation Orders protect trees and groups of trees within and adjacent to the application site, and an ancient woodland (Dum Wood) is designated to the east of the site. Local Plan policy LP33 states that planning permission will not be granted for developments which directly or indirectly threaten trees or woodlands of significant amenity, and proposals should normally retain any valuable or important trees where they make a contribution to public amenity or have other benefits. 10.71 The applicant’s Hedgerow Assessment and Report (July 2018) at appendix 14.9 of the ES submitted with application ref: 2020/92331 states that three of the MXS7 site’s hedgerows can be defined as “important” under theHedgerow Regulations 1997 , and that a further five hedgerows just fall short of being classified as “important”, due to there being either one too few woody species or associated features, or by not being adjacent to a public right of way. One of the “important” hedgerows is within the Heybeck Lane site. 10.72 The proposed development (as illustrated indicatively) largely retains existing trees and hedgerows, and an appropriate buffer is proposed adjacent to the ancient woodland. The applicant’s landscaping proposals are currently indicative, however they illustrate potential biodiversity connections across the site. 10.73 The applicant’s illustrative layout and supporting arboricultural impact assessment demonstrates that the site can be developed while incorporating the existing important trees, woodlands and hedgerows into the, and avoiding adverse impact on these features. Significantly more detail would, of course, be required at Reserved Matters stage, including details of how the site’s hedgerows would be retained. 10.74 Further assessment regarding impacts on Dum Wood is set out in the accompanying committee report for application ref: 2020/92331. 10.75 As noted by KC Trees, the hedgerow identified as “important” appears to be impacted by the proposals. This would need to be considered further at Reserved Matters stage when, if the hedgerow is not to be retained and worked around, mitigation would be required, possibly in the form of translocation of the hedgerow to a new site more associated with the adjacent ancient woodland.”
“A development of this scale would have significant impacts requiring mitigation. The following planning obligations securing mitigation (and the benefits of the proposed development, where relevant to the balance of planning considerations) would need to be included in a Section 106 agreement: …. 7) Biodiversity a) Contribution (amount to be confirmed) or off-site measures to achieve biodiversity net gain (only applicable if 10% can’t be achieved on-site); b) Securing other off-site measures (including buffers to ancient woodlands, and provision of skylark plots). …. 10) Ancient woodland – management plan (and works, if required) for public access to Dum Wood (outside application site, but within applicant’s ownership).”
“The request made by the Chidswell Action Group to delay determination of the application is noted, but is not supported. As part of the recent reconsultation, letters and emails were sent to everyone who had previously been consulted and everyone who had previously commented on the application, and four new site notices were posted on02/11/2022 . This greatly exceeds the consultation effort required by the relevant legislation, and would have ensured a good level of local awareness regarding the application and the reconsultation.”
“13) Ecological mitigation and enhancement details (including an Ecological Design Strategy, measures to address impacts on birds including ground-nesting farmland birds), and details of mitigation and delivery measures to be submitted. … 24) Construction (Environmental) Management Plan to be submitted.”
“material considerations are being left to be dealt with as Reserved Matters. Without an accurate baseline survey, the [committee] will not be able to determine whether 10% BNG is actually achievable, because the BNG achievable onsite is uncertain – leaving a grant of Outline Planning permission vulnerable to a legal challenge.”
“[w]ithout accurate baseline information, how can the [committee] determine whether the proposal will avoid/mitigate significant loss or harm to biodiversity? Or what compensatory measures will be appropriate?”
“[o]ne of the problems with having the list of conditions like this is that it summarises the conditions doesn’t tell you what’s in them”
“… yes the applicant surveys ecological survey information is now fairly old it's over four years old it has been supplemented by a walkover survey carried out in October of this year which is of some use but, officers and the applicants as well do accept that full detailed surveys would need to be redone to inform the proposals brought forward at reserved matters stage and that would be an appropriate point to do it, you would then have bang up-to-date information that will take into account all the information that we have so far - new on-site observations, if need be the council's biodiversity officer can accompany the applicant’s consultants on site, if there's any disagreement as to how certain ecological features need to be categorised in as an input into the biodiversity net gain calculations, if that needs to happen that can be done. And of course, reference can be made to the significant volumes of information that local residents have gathered regarding sightings of it was mentioned Kingfishers and Red Kites and other species that have been seen on site that there is evidence of.”
“… we request details of all outstanding agreements being drafted and discussed prior to the decision date on Chidswell & Heybeck. Specifically, the S106 / S278 / Reserved Matters - and any other details which need to be agreed prior to determination. It's our understanding these draft documents should already be published on the Planning Portal so we'd appreciate a timely response to this request. We would also ask if you have a target completion date for these outstanding matters.”
“Thanks for your email. To clarify – it is only the Section 106 agreements (one for each application: 2020/92350 and 2020/92331) that need completing prior to the council’s decisions (on the two applications) being released. Section 278 agreements relate to works to the highway. Reserved matters would be addressed in later applications which would be put to public consultation. Section 106 agreements are being drafted. Their provisions will secure the Heads of Terms set out in the committee reports for the two applications. No drafts of the agreements are in the public domain (nor are they required to be). The completed agreements will be posted online along with the council’s decisions, when issued. As to when that will happen, I can’t confirm precisely, however later this summer is likely.”
“Further to my voice message left on your Kirklees' extension today, we would be grateful to know why applications 2020/92350 and 2020/92331 are no longer present on Kirklees' planning portal. We would be grateful to know: The target date for completion of the S106 agreements and the release of the Council's decision; If you will be updating Kirklees' planning portal immediately at the point of completion of S106 agreements and release of the Council's decision? We would request you to please notify ourselves to the CAG email as soon as the S106 agreements are completed and the Council's decision is going to be released.”
“Thanks for your messages. Yes – there has been a problem with the council’s website today, affecting access to several applications. The council’s IT people are trying to resolve the matter. As regards the Section 106 agreements, we had hoped to complete these by the end of this month. Whether or not that happens depends on various factors, including progress with National Highways. Once the Section 106 agreements are completed, planning permissions are usually issued within a few days. For both applications, the decision letter and the Section 106 agreement should appear online at the same time (the day after the decision is issued, as the council’s website updates overnight).”
“a biodiversity management and enhancement plan detailing: (a) details of the biodiversity habitat creation and/or enhancement proposed; and (b) a detailed management and maintenance regime to secure such biodiversity habitat for a period of 30 years … .”
“a biodiversity management and enhancement plan detailing the biodiversity habitat creation or enhancement proposed on all or part of the Offsite BNG Land [i.e. the ancient woodland] (as identified in the Offsite BEMP by reference to a plan) such plan to include a detailed management and maintenance regime to secure such biodiversity habitat for a period of not less than 30 years... .”
“4. On-Site Biodiversity Net Gain 4.1. The Owner shall not Occupy more than 90% of the Dwellings (or comply with such other requirement for timing of provision as may be contained in the BEMP) until the Owner has completed the works of habitat creation and/or enhancement set out in the BEMP and has served notice on the Council confirming completion of such works. 4.2. From the date of notice served pursuant to paragraph 4.1, the Owner covenants to comply with the requirements of the BEMP (or any amended BEMP submitted by the Owner to the Council and approved by the Council) for a period of 30 years. 5. Off-Site Biodiversity Net Gain 5.1. Where an Offsite BEMP applies, the Owner shall not Occupy more than 90% of the Dwellings (or comply with such other requirement for timing of provision as may be contained in the Offsite BEMP) until the Owner has completed the works of habitat creation and/or enhancement set out in the Offsite BEMP and has served notice on the Council confirming completion of such works. 5.2. From the date of notice served pursuant to paragraph 5.1, the Owner covenants so as to bind the relevant part of the Offsite BNG Land identified in the relevant Offsite BEMP only to comply with the requirements of the Offsite BEMP (or any amended Offsite BEMP submitted by the owner of the relevant Offsite BNG Land from time to time to the Council and approved by the Council) for a period of 30 years.”
“1. Prior to the commencement of development (save for enabling works which for the purposes of this condition shall comprise site preparation, remediation works, provision of construction and temporary access roads, diversion and/or laying of strategic site-wide utilities, and works associated with archaeological surveys) of any phase or sub phase of the development hereby approved, details of appearance, landscaping, layout and scale (hereinafter called the “Reserved Matters”) of that phase or sub phase shall be submitted to and approved in writing by the Local Planning Authority … .”
“Site preparation comprises the installation of temporary facilities, installation of Heras or other fencing, installation of temporary construction compounds, and removal of existing structures and vegetation. Site preparation does not include ground works which are defined as excavation, remediation, grading and other activities related to the modification of the ground surface or subsurface.”
“6. Prior to the commencement of development (including ground works) of any phase or sub phase of the development hereby approved, a Construction (Environmental) Management Plan (C(E)MP) for that phase or sub phase shall be submitted to and approved in writing by the Local Planning Authority. The C(E)MP shall include a timetable of all works, and details of: • Hours of works (including times of deliveries); • Point(s) of access and routes for construction traffic (which shall avoid Chidswell Lane); • Construction vehicle sizes; • ….. • Measures to control and monitor the emission of dust and dirt during construction; • Site waste management, including details of recycling/disposing of waste resulting from construction works; • Mitigation of noise and vibration arising from all construction-related activities; • Artificial lighting used in connection with all construction-related activities and security of the construction site; • Site manager and resident liaison officer contacts, including details of their remit and responsibilities; • Engagement with local residents and occupants or their representatives; and • Engagement with the developers of nearby sites to agree any additional measures required in relation to cumulative impacts (should construction be carried out at nearby sites during the same period). The development hereby approved shall be carried out strictly in accordance with the C(E)MP so approved throughout the period of construction and no change therefrom shall take place without the prior written consent of the Local Planning Authority. Reason: In the interests of amenity, to ensure the highway is not obstructed, in the interests of highway safety, to ensure harm to biodiversity is avoided, and to accord with Policies LP21, LP24, LP30 and LP52 of the Kirklees Local Plan. This pre-commencement condition is necessary to ensure measures to avoid obstruction to the wider highway network, to avoid increased risks to highway safety, and to prevent or minimise amenity and biodiversity impacts are devised and agreed at an appropriate stage of the development process.”
“24. Each application for the approval of Reserved Matters shall include details of faunal enhancement measures (together with arrangements for their maintenance and management) informed by up-to-date and comprehensive ecological surveys (including surveys of protected species) prepared and submitted by the developer. Following approval in writing by the Local Planning Authority, the measures (which may include the provision of bird and boxes, and provisions relating to hedgehogs and badgers) shall be implemented on a phase-by-phase basis in accordance with the details so approved. No phase or sub phase of the development hereby approved shall be first occupied prior to the implementation of the faunal enhancement measures so approved for that phase or sub phase, unless the approved details include alternative proposals for the timing of installation of the measures (in which case those alternative proposals shall be complied with). The measures shall be maintained and managed in accordance with the approved details for a minimum period of 30 years thereafter. Reason: To secure mitigation, enhancement and compensation for the ecological effects resulting from loss of habitat and to accord with policy LP30 of the Kirklees Local Plan and chapter 15 of the National Planning Policy Framework. 25. No removal of hedgerows, trees or shrubs shall take place between 1st March and 31st August inclusive, unless authorised in writing by the Local Planning Authority in response to evidence to be submitted in writing to the Local Planning Authority demonstrating that no birds will be harmed and/or that there are appropriate measures in place to protect nesting bird interest on site. Reason: To prevent significant ecological harm to birds, their eggs, nests and young and to accord with Policy LP30 of the Kirklees Local Plan and chapter 15 of the National Planning Policy Framework. 26. Each application for the approval of Reserved Matters relating to residential use shall include floor plans (providing details of internal layouts of the residential accommodation) and a schedule of accommodation (providing unit size mix information and gross internal floorspace figures in sqm) for all residential units. Reason: To enable the quality, amenities and housing mix of the residential accommodation to be assessed in accordance with policies LP11 and LP24 of the Kirklees Local Plan and chapter 5 of the National Planning Policy Framework.”
“Ecological mitigation and enhancement details (including an Ecological Design Strategy, measures to address impacts on birds including ground-nesting farmland birds), and details of mitigation and delivery measures to be submitted.”
“Section 106 Schedule 5 (with net gain to be achieved not via a contribution”
“to carry out, submit and have approved the Biodiversity Assessment prior to any work that could … adversely [sic] the relevant habitats within the site”
“3.1. The Owner [developer] covenants with the Council [LPA] that notwithstanding Clause 3.2 of the Original Agreement the Owner shall not begin the Development (within the meaning of Section 56 of the 1990 Act) or otherwise commence clearance of hedgerows, trees and shrubs, or any other features of potential ecological importance within the Site, until: 3.1.1. up to date and comprehensive ecological surveys (including surveys of protected species) as required by condition 24 of the Planning Permission have been carried out and submitted to the Council; and 3.1.2. details of measures to protect any habitats to be retained within the Site during construction works (including site clearance and enabling works) have been submitted to and approved in writing by the Council; and 3.1.3. the Biodiversity Assessment required by paragraph 2.1 of Schedule 5 of the Original Agreement has been undertaken and submitted to the Council and approved by the Council in writing. 3.2. The Owner covenants with the Council to comply with the measures approved pursuant to paragraph 3.1.2 of this Deed.”
“… Condition 1 defines the enabling works for the purposes of this condition as site preparation, remediation works, provision of construction and temporary access roads, diversion and/or laying of strategic site-wide utilities, and works associated with archaeological surveys. The covenants in the supplemental planning obligation are not to begin development or otherwise commence clearance of hedgerows, trees and shrubs, or any other features of potential ecological importance within the Site until the updating ecological surveys and other measures have been completed. The covenant does not promise that the Owner will not commence the enabling works carved out in condition 1 prior to the submission of matters set out in clause 3. For these reasons ground 3 is arguable.”
“I am not convinced that the BNG figures were inaccurate. The officer’s statement that an updating assessment would be required was effectively an update to the baseline assessment. However, for similar reasons to those set out under ground 3, it is arguable that the BNG requirements were not properly secured by condition or otherwise and I am not convinced that the supplementary planning agreement saves the Defendant.”
“3.1 The Owner [developer] and the Council [LPA] agree that the first paragraph of clause 3.1 of the Supplemental Deed [SPO (1)] shall be deleted and replaced with the following paragraph: ‘The Owner covenants with the Council that notwithstanding Clause 3.2 of the Original Agreement the Owner shall not begin the Development (within the meaning of Section 56 of the 1990 Act) or otherwise undertake any works associated with the Development including the works identified as "enabling works" in Condition 1 of the Planning Permission or otherwise commence clearance of hedgerows, trees and shrubs, or any other features of potential ecological importance within the Site, until:’ 3.2. The Owner and the Council agree that a new Clause 3.3 shall be inserted into the Supplemental Deed as follows: ‘3.3 For the avoidance of any doubt the Owner and the Council agree that the reference to "the pre-development biodiversity value" in the definition of "Biodiversity Assessment" in paragraph 1.1 of Schedule 5 of the Original Agreement is and shall be interpreted as a reference to the biodiversity value of the Site prior to the earlier of i) the beginning of the Development (within the meaning of Section 56 of the 1990 Act), ii) the undertaking of any works associated with the Development including the works identified as "enabling works" in Condition 1 of the Planning Permission, and, iii) the commencement of the clearance of hedgerows, trees and shrubs, or any other features of potential ecological importance within the Site.’”
“3.1 The Owner covenants with the Council that notwithstanding Clause 3.2 of the Original Agreement the Owner shall not begin the Development (within the meaning of Section 56 of the 1990 Act) or otherwise undertake any works associated with the Development including the works identified as ‘enabling works’ in Condition 1 of the Planning Permission or otherwise commence clearance of hedgerows, trees and shrubs, or any other features of potential ecological importance within the Site, until: 3.1.1 up to date and comprehensive ecological surveys (including surveys of protected species) as required by condition 24 of the Planning Permission have been carried out and submitted to the Council; and 3.1.2 details of measures to protect any habitats to be retained within the Site during construction works (including site clearance and enabling works) have been submitted to and approved in writing by the Council; and 3.1.3 the Biodiversity Assessment required by paragraph 2.1 of Schedule 5 of the Original Agreement has been undertaken and submitted to the Council and approved by the Council in writing. 3.2 The Owner covenants with the Council to comply with the measures approved pursuant to paragraph 3.1.2 of this Deed. 3.3 For the avoidance of any doubt the Owner and the Council agree that the reference to ‘the pre-development biodiversity value’ in the definition of ‘Biodiversity Assessment’ in paragraph 1.1 of Schedule 5 of the Original Agreement is and shall be interpreted as a reference to the biodiversity value of the Site prior to the earlier of i) the beginning of the Development (within the meaning of Section 56 of the 1990 Act), ii) the undertaking of any works associated with the Development including the works identified as ‘enabling works’ in Condition 1 of the Planning Permission, and, iii) the commencement of the clearance of hedgerows, trees and shrubs, or any other features of potential ecological importance within the Site.”
“The purpose of article 40(3)(b) of the Order appears from its wording and statutory context. Certain documents must be placed on the planning register in the period before an application for planning permission is finally disposed of. They include a copy of a planning obligation (or a highways agreement) which it is proposed to enter into or which has been entered into. The purpose of publication is to enable members of the public to know the terms of a proposed or agreed planning obligation, and to enable them to comment on the proposed or agreed planning obligation if they choose to do so. The article envisages that members of the public may comment on the subject matter of the planning obligation. Publication of the section 106 agreement is not intended to provide an opportunity to make comments on wider issues to do with the desirability or otherwise of the grant of planning permission. Those matters will have been dealt with by the planning committee which resolved to grant the planning permission.”
“This is not a case where the intention underlying article 40(3) of the Order was that any failure to comply would result in the invalidity of a decision taken following such a failure. A breach of article 40(3) could occur in a wide range of factual circumstances, from situations where the content of a proposed section 106 agreement was not known to situations where, even though the agreement was not placed on the planning register, the content may in fact be in the public domain. The impact of the failure on the ability of members of the public to comment on the subject matter of a proposed section 106 agreement will, likewise, vary depending on the facts of a particular case. In those circumstances, I do not consider that the intention, or the purpose, underlying article 40(3) requires that any failure to comply renders a subsequent decision invalid. It is necessary to evaluate the consequences of non-compliance on the facts of the case.”
“a) if significant harm to biodiversity resulting from a development cannot be avoided (through locating on an alternative site with less harmful impacts), adequately mitigated, or, as a last resort, compensated for, then planning permission should be refused; …”
“(i) result in no significant harm or loss to biodiversity in Kirklees through avoidance, adequate mitigation or, as a last resort, compensatory measures secured through the establishment of a legally binding agreement; (ii) minimise impact on biodiversity and provide net biodiversity gains through good design by incorporating biodiversity enhancements and habitat creation where opportunities exist; (iii) safeguard and enhance the function and connectivity of the Kirklees Wildlife Habitat Network at a local and wider landscape-scale unless the loss of the site and its functional role within the network can be fully maintained or compensated for in the long term; (iv) establish additional ecological links to the Kirklees Wildlife Habitat Network where opportunities exist; and (iv) incorporate biodiversity enhancement measures to reflect the priority habitats and species identified for the relevant Kirklees Biodiversity Opportunity Zone.”
“All development in Kirklees, as set out in national policy and the policies described in this document, will be expected to not result in significant loss or harm to biodiversity through avoidance, mitigation and compensatory measures and seek opportunities to enhance biodiversity value and ecological links. … In order to safeguard and enhance the function and connectivity of the Kirklees Wildlife Habitat Network, the council will also seek to ensure that development proposals do not result in the fragmentation of the network and provide improved ecological links, particularly to the Kirklees Wildlife Habitat Network, where opportunities exist.”
“(a) for regulating the development or use of any land under the control of the applicant (whether or not it is land in respect of which the application was made) or requiring the carrying out of works on any such land, so far as appears to the local planning authority to be expedient for the purposes of or in connection with the development authorised by the permission; … .”
“…. [t]here are no special rules for the interpretation of planning conditions. They are to be interpreted in a manner similar to the interpretation of other public documents. The court asks itself what a reasonable reader would understand the words to mean when reading the condition in the context of the other conditions and of the consent as a whole. This is an objective exercise in which the court will have regard to the natural and ordinary meaning of the relevant words, the overall purpose of the consent, any other conditions which cast light on the purpose of the relevant words, and common sense. … . As a planning permission is a document created within the legal framework of planning law, the reasonable reader is to be treated as being equipped with some knowledge of planning law and practice … .”
“the [committee], even if not actively or deliberately misled, were given material advice in the [officer’s report] and orally which transpired to be incomplete or inaccurate to a significant degree when the decision notice was issued and the section 106 agreement published. That error of law is compounded by the Defendant’s failure to publish the section 106 agreement in time for public comment, prior to issuing the decision (additional Ground 5). … paragraph 10.69 of the [officer’s report] … states that the ‘council is able to make an informed decision’ (i.e. without deferral for updated ecological reports or BNG assessment) because ‘Further surveys would be required at Reserved Matters stage […] the applicant has proposed a policy-compliant biodiversity net gain […] Conditions and provisions (secured via a Section 106 agreement) can be applied to mitigate the ecological impacts of the proposed development’. …That statement should be read as advice to members that conditions will be applied, and an agreement will be finalised, which mitigates ecological impacts as far as possible and achieves at least 10% biodiversity net gain. For the reasons set out in the Grounds 3 and 4, this did not happen. …. The consequences of the [committee]’s reliance on officer advice is that outline planning permission was issued without the effective ecological conditions and ‘’policy compliant’ biodiversity net gain provision which the SPC took into account as material when resolving to grant it. Due to the timing of publication of the section 106 agreement, and the supplemental deeds, the SPC were deprived of expert comment on the agreement’s implications for the ecological protection of the site.”