“Central Government development consent is perceived as a more arduous route than planning permission from a local planning authority. If your solar farm is above the Statutory Capacity Threshold, you face a tougher approval regime”
“4.3.10 The applicant must provide information proportionate to the scale of the project, ensuring the information is sufficient to meet the requirements of the EIA Regulations. 4.3.11 In some instances, it may not be possible at the time of the application for development consent for all aspects of the proposal to have been settled in precise detail. Where this is the case, the applicant should explain in its application which elements of the proposal have yet to be finalised, and the reasons why this is the case. 4.3.12 Where some details are still to be finalised, the ES should, to the best of the applicant’s knowledge, assess the likely worst-case environmental, social and economic effects of the proposed development to ensure that the impacts of the project as it may be constructed have been properly assessed.”
“The Powering Up Britain: Energy Security Plan81 states that government seeks large scale ground-mount solar deployment across the UK, looking for development mainly on brownfield, industrial and low and medium grade agricultural land. It sets out that solar and farming can be complementary, supporting each other financially, environmentally and through shared use of land, and encourages deployment of solar technology that delivers environmental benefits, with consideration for ongoing food production or environmental improvement.”
“Along with associated infrastructure, a solar farm requires between 2 to 4 acres for each MW of output. A typical 50MW solar farm will consist of around 100,000 to 150,000 panels and cover between 125 to 200 acres. However, this will vary significantly depending on the site, with some being larger and some being smaller. This is also expected to change over time as the technology continues to evolve to become more efficient. Nevertheless, this scale of development will inevitably have impacts, particularly if sited in rural areas.”
“2.10.53 From the date of designation of this NPS, for the purposes ofSection 15 of the Planning Act 2008 , the maximum combined capacity of the installed inverters (measured in alternating current (AC)) should be used for the purposes of determining solar site capacity. 2.10.54 The capacity threshold is 50MW (AC) in England and 350MW (AC) in Wales.91 2.10.55 The installed generating capacity of a solar farm will decline over time in correlation with the reduction in panel array efficiency. There is a range of sources of degradation that developers need to consider when deciding on a solar panel technology to be used. Applicants may account for this by overplanting solar panel arrays.92 2.10.56 AC installed export capacity should not be seen as an appropriate tool to constrain the impacts of a solar farm. Applicants should use other measurements, such as panel size, total area and percentage of ground cover to set the maximum extent of development when determining the planning impacts of an application. Fn 91 The combined maximum AC capacity of the installed inverters may only exceed the aforementioned thresholds for the sole purpose of overcoming reactive power consumption within the solar farm between the inverters and the connection point. Fn 92 `Overplanting’ refers to the situation in which the installed generating capacity or nameplate capacity of the facility is larger than the generator’s grid connection. This allows developers to take account of degradation in panel array efficiency over time, thereby enabling the grid connection to be maximised across the lifetime of the site. Such reasonable overplanting should be considered acceptable in a planning context so long as it can be justified and the electricity export does not exceed the relevant NSIP installed capacity threshold throughout the operational lifetime of the site and the proposed development and its impacts are assessed through the planning process on the basis of its full extent, including any overplanting..”
“2.10.70 In many cases, not all aspects of the proposal may have been settled in precise detail at the point of application. Such aspects may include: • the type, number and dimensions of the panels; • layout and spacing; • the type of inverter or transformer; and • whether storage will be installed (with the option to install further panels as a substitute). 2.10.71 Applicants should set out a range of options based on different panel numbers, types and layout, with and without storage. 2.10.72 Guidance on how applicants should manage flexibility is set out at Section 2.6 of this NPS.”
“2.6.1 Where details are still to be finalised, applicants should explain in the application which elements of the proposal have yet to be finalised, and the reason why this is the case. 2.6.2 Where flexibility is sought in the consent as a result, applicants should, to the best of their knowledge, assess the likely worstcase environmental, social and economic effects of the proposed development to ensure that the impacts of the project as it may be constructed have been properly assessed. 2.6.3 Full guidance on how applicants and the Secretary of State should manage flexibility is set out in Section 4.3 of EN-1.”
“I have a query about Energy Policy Statement EN-3 guidance on how to determine whether development capacity is below the threshold for a Nationally Significant Infrastructure Project (NSIP). The guidance has given rise to some confusion because, as solar panels become cheaper, there is an incentive for developers to overplant and rely on "clipping" to keep sites below the NSIP threshold. This does not appear to be permitted by EN-3, but it would be helpful to have more explicit guidance.”
“In the Energy Policy Statement EN-3 guidance, overplanting is countenanced where reasonable, to address panel degradation. Unreasonable overplanting, or overplanting for any other reason, would not be supported. It will be a matter of planning judgement for the decision maker in any case to decide what the purpose of the overplanting is and whether it is reasonable. Due to the variable nature of solar projects, it would be difficult to determine a single overplanting measurement that would be appropriate in all circumstances which is why it is for decision makers to take into account the specifics of each project.”
“…The loss of cereal cropland and modified grassland habitat may havean adverse impact on some specialist farmland birds i.e. skylark and yellowhammerhowever, in the local context this loss is extremely limited and therefore effects areconsidered to be negligible.”
“Considering the nature, scale and location of the Proposed Development and nature of the receiving environment, whilst there may be some impact on the surrounding area and nearby designated sensitive areas as a result of this development, which could also include possible heritage issues, it would not be of a scale and nature likely to result in significant environmental impact.”
“1. The scale, design and nature of the proposed development would have significant adverse impacts on landscape character and visual amenity, contrary to Policies 16, 22 and 34 of LPP2 2. The proposed development would harm the character and appearance of the Hawksworth and Thoroton Conservation Areas and the settings of designated heritage assets, contrary to Policies 1 and 11 of LPP1 and Policies 16 and 28 of LPP2. 3. The proposals would entail the development of significant areas of best and most versatile agricultural land, contrary to policies 1 and 16 of LPP2. 4. The Appellant has failed to investigate the nature, extent and significance of archaeological remains present on the appeal site, contrary to Policy 29 of LPP2. 5. The proposals pose a significant risk to otters and bats, species protected under theConservation of Habitats and Species Regulations 2017 .”
“If there is a cap on the connection to the grid, capacity may be `clipped’, meaning that surplus energyis wasted when the site is operating at maximum capacity. Installing more panels and inverters thanrequired would enable the site to deliver 49.9MW for more of the year.”
“In the absence of surveys, there is no evidence for this conclusion. Skylark and Yellowhammer are listed under s.41 of the NERC Act as species of principal importance and Nottinghamshire’s Biodiversity Action Plan records both species as in local decline.”
“The evidence for the conclusion is based upon the readily apparent suitability of surrounding habitat within the local area, and the absence of any cumulative effects of the Proposed Development incombination with other developments in the local area which may impact specialist farmland birds in a regional context. Furthermore, the statement above is quoted only in the context of assessing potential impacts and does not include the subsequently described benefit of ecological enhancement measures and new habitat creation that not only negates any losses but will provide an overall net gain in the biodiversity value of the Application Site resulting from the Proposed Development.”
“4.16. If the DC capacity in excess of the 49.9 AC were removed from the scheme this would result in a scheme which is between 8% and 22% smaller. Should any element of this additional DC capacity be removed, there are a multitude of permutations as to how this could be achieved. The reduction in the size of the scheme may not necessarily only result in a reduction in area of land take but could result in part from a different configuration of panels within the existing redline area. Equally, any reduction in the size of the scheme from a reduced area of landtake could take many forms, from the removal of entire fields, to a ‘shrinking’ of the scheme from the edges. 4.17. The assessments undertaken on behalf of the Appellant on the whole current scheme find that all impacts are acceptable and the planning benefits outweigh harms. A reduction of the scale of the nature suggested above would make no material difference in planning balance. 4.18. In terms of quantifying this non material reduction, whilst there may be localised variations on different disciplines, in absence of any specific reduced scheme it is not possible to undertake a detailed assessment. 4.19. The Appellant remains firmly of the view that the adverse impacts of the current scheme are limited and substantially outweighed by the benefits and that it would not be possible to achieve the same energy generation and benefits on a reduced area.”
“Up to 58% of the Appellant’s overplanting is for a purpose other than to account for degradation and is therefore in breach of what is permitted by EN-3. Additionally, this excessive overplanting leads to a variety of planning harms. These are both material considerations for the Inspector.”
“The LPA does not take a point on this matter as they do not have the resources to assess in such detail, but the LPA does consider overplanting should be taken into account because it results in landscape, heritage and character impacts, making the scheme larger in area than perhaps it would otherwise need to, to generate the same capacity.”
“Inspector to decide if scale of overplanting proposed is `reasonable’ as per footnote and whether the appeal development is `considered acceptable in a planning context so long as it can be justified’. There must be threshold point of providing more than is reasonable for what is required to generate the 49.9MW. It is the LPA’s case that the harm is disproportionately large for the unquantified benefit that the overplanting would provide.”
“18. The Appellant’s proposal to generate 49.9MW for longer periods, is not permitted by EN-3 and would necessitate the wastage of a large proportion of the energy generated. 19. While the R6P’s proposed condition would enable the Inspector to ensure the development remains below the NSIP threshold, this would not represent best use of the land. The site could deliver more energy without the need for clipping and wastage if it were to obtain a development consent order.”
“Given the flexibility of the proposed planning conditions, the panels, inverters and other infrastructure may be larger or otherwise more prominent than assessed and the site more densely planted, with different potential adverse landscape, visual, glint and glare, ecology, and recreational impacts. The amount of energy generated and the level of clipping required remains undetermined. The Appellant cannot be said to have carried out a `worst-case scenario’ assessment of the proposed development.”
“9. Both the Infrastructure Layout and Landscape Masterplan revised drawings identify areas within the appeal site for an `Indicative Solar PV Array’. However, the layout of other features of the proposed development, such as access tracks, inverters and associated hardstanding, substation and construction compounds, fence line, and permissive paths are not indicative. Siting for these elements of the proposal is a matter for determination. The scheme proposes 26 inverter substations and 95 CCTV posts, along with two temporary construction compounds. A new vehicular entrance to the site is proposed off Thoroton Road by removing 17 m of existing hedgerow. Two options are shown for grid connection to the 132 kV overhead line within the appeal site. Option 1 Fig12A provides for a lattice tower 23 m high, whereas Option 2 Fig12B depicts wooden poles 9 m high. 10. The application drawings indicate typical details for panels, inverters, security CCTV, fencing and access tracks. These indicate bi-facial panels 2.8 m high at the top and 0.8 m above the ground at the bottom, inverter substation units 3 m high, substation electrical equipment 3.85 m high, with a 15 m high communications tower. Palisade fencing around the substation is shown as3 m high, with deer fencing 2.4 m high around the site and the bridleway, andCCTV towers 3.5 m high. These details are illustrative. However, the appellant’s landscape evidence is based upon panels with a maximum height of 2.8 m. Inverters and the substation would be sited on raised ground for flood risk reasons. The Statement of Common Ground (SoCG) submitted in May records that the proposed development would include 150,304 modules or PV panels. Throughout the Inquiry the appellant referred to the appeal scheme with an indicative number of 128,752 panels sitting across a buildable area of 157 acres (63.5 ha).I have dealt with the appeal on the basis that no specific details about the number, power rating, size and spacing of panels, or specification for the inverters, are included in the application. However, the `Indicative Solar PV Array’ would be sited within the defined fence line on the Infrastructure Layout. I am satisfied that there is sufficient evidence about the appeal scheme to properly assess the proposal on a worst-case basis.”
“The main issues in this appeal are: (a) The effect of the proposed development on the character and appearance of the area. (b) The effect on heritage assets. (c) The effect on agricultural land and food production. (d) Flood risk and flood policy. (e) Consideration of local and national planning policy and whether the benefits of the proposal would outweigh any harm. HTAG questions whether the capacity of the appeal scheme would mean that it was a NSIP, and I deal with this first. It is also necessary to clarify, procedurally, how the appeal should deal with matters concerning a grid connection.”
“29. The installed generating capacity of the solar farm would decline over time in correlation with the reduction in panel array efficiency. EN-3 notes that there is a range of sources of degradation that developers need to consider when deciding on a solar panel technology to be used and that account for this can be made by overplanting solar panel arrays. Footnote 92 adds that; `…this allows developers to take account of degradation in panel array efficiency over time, thereby enabling the grid connection to be maximised across the lifetime of the site. Such reasonable overplanting should be considered acceptable in a planning context so long as it can be justified and the electricity export does not exceed the relevant NSIP installed capacity threshold throughout the operational lifetime of the site and the proposed development and its impacts are assessed through the planning process on the basis of its full extent, including any overplanting’. 30. If overplanting is acceptable to address degradation to enable the grid connection to be maximised for the duration of the development, there would seem to be similar advantage in permitting additional overplanting to maximise utilisation of the available grid connection by exporting at the maximum export capacity permitted for the optimal proportion of time for that particular scheme. I do not read Footnote 92 as a policy limitation restricting overplanting solely to compensation for the degradation of panels over time. Such an interpretation would be at odds with the overall policy support for the generation of renewable energy. The Government has committed to sustained growth in solar capacity to ensure that it is on a pathway to meeting net zero emissions by 2050, and solar is a key part of the Government’s strategy for low-cost decarbonisation of the energy sector. The letter to HTAG from the then Minister of State for Energy Security and Net Zero, dated 22 May, cannot be considered determinative of policy interpretation, which is ultimately a matter for the Courts. 31. In respect of overplanting I asked the appellant to provide further details about the contribution of the dc elements of the proposed solar farm regarding; (a) the difference between the output power defined under the Standard Test Conditions and the actual meteorological conditions of the site, (b) performance degradation of the panels over time, and (c) the maximisation of energy production from inverters with a combined capacity of 49.9 MWac. In summary, this note identified 8% of the panel area for (a), 16-22% of the panel area for (b), with 8-14% of the panel area for (c). HTAG challenges these estimates. ID40 is based on a number of assumptions, but it does indicate the likelihood that a significant proportion of the overplanting would be intended to maximise electricity output from the proposed solar farm. HTAG argues that taking this into account would conflict with EN-3. However, I concur with the appellant that there is nothing in EN-3 or any other policy statement that precludes the design of a scheme to maximise energy generation to account for the factors set out in (a), (b) and (c) above. 32. HTAG considers that leaving illustrative matters for subsequent approval by discharge of conditions may mean that infrastructure would be more prominent than assessed and the site more densely planted with different impacts on the character and appearance of the area, glint and glare, ecology and recreation. However, the approach adopted by the appellant is consistent with EN-1 and EN-3 concerning flexibility in project details. In determining this appeal, I have considered the area defined by the fence line on the Infrastructure Layout, within which the Indicative Solar PV Array would be contained, to set the maximum extent of the proposed solar PV array for the purposes of assessing the planning impacts of the appeal scheme. I have not used ac installed export capacity to constrain the impacts of the proposed solar farm. 33. Given the extent of the area defined by the fence line containing the Indicative Solar PV Array, along with the likely number and power rating of the panels, it would be likely that the proposed solar farm would have a high ratio for MWdc Capacity / Maximum Export Capacity MECac. HTAG are correct that the amount of energy generated and the level of clipping that would be likely to be required remain undetermined. However, it seems to me that the optimal level of clipping for the scheme would be a commercial decision for the developer. It is not necessary to know in advance the precise MWh that the appeal scheme would be likely to generate, particularly as this would depend upon a number of factors, including the weather. Overplanting to optimise renewable energy generation from the proposed solar farm would not result in any conflict with relevant policy. 34. Taking all the above into account, I find that the proposed development, subject to the imposition of appropriate planning conditions, is not a NSIP, and that it is appropriate to determine the appeal under section 78 of the 1990 Act. Given this finding, HTAG’s conditional costs application falls away. Furthermore, in my judgement, the likely degree of overplanting in this case would not justify dismissing the appeal.”
“Clipping occurs when power production from solar panels exceeds the capacity of inverters. This results in ‘clipping’ of the daily energy curve at times of peak radiation, usually around midday, and represents potential energy forgone, but overplanting enables more of the energy curve to be utilised in the morning and evening.”
“In the planning balance that applies in this case moderate weight should be given to the harm that would result to the character and appearance of the area. The harm I have identified to designated heritage assets attracts considerable importance and weight but would be outweighed by the public benefits of the development. Against this overall harm must be weighed the benefits of the proposed development. Chief amongst these is the significant contribution of the appeal scheme towards the generation of renewable energy, the resultant reduction in greenhouse gas emissions and energy security benefits, which warrant substantial weight. This, along with moderate weight to be given to biodiversity gain and limited weight for the benefits to the local economy would, in my judgement, outweigh the harm I have identified.”
“In my judgement the planning balance here falls in favour of the appeal scheme. I consider that the proposal accords with the development plan taken as a whole and is consistent with the NPPF. I have taken into account all other matters raised in evidence, but I have found nothing of sufficient weight to alter my conclusions. For the reasons given above the appeal should be allowed.”
“Notwithstanding Condition 2, prior to their erection on site, details of the development indicated on the following plans, including siting, dimensions, materials, colour and finish, subject to the following limits for (c), (d), (e) and (g), shall be submitted to and approved in writing by the local planning authority: … (c) 04668-RES-SOL-DR-PT-001 Rev 3 – Typical PV Module and Rack Detail. The top of all PV Modules and Racks shall not exceed 2.8 m above the existing ground level. … The development shall be carried out in accordance with the approved details and retained as such for the duration of the development hereby permitted.”
“The Inspector will need to decide the appropriate approach to distinguishing, on the basis of capacity, between an NSIP scheme and one which is not. The first question is whether this could be achieved by means of a suitably worded planning condition? IF the answer is no - would the proposed development then meet the criteria for an NSIP scheme that would require development consent, and if so would that preclude granting planning permission? IF the answer is yes - would it be the case that ‘overplanting’ would no longer be a consideration that was relevant to answering the NSIP question - irrespective of the dc/MEC ratio for a scheme? IF that is correct whether overplanting should nonetheless be taken into account in considering the planning merits of the proposal? IF so would the extent of overplanting be a consider likely to affect the area of land occupied by PV panels? IF the PV panels in the local context would be likely to result in some harm to relevant planning considerations would there be more harm with more overplanting? IF so would additional overplanting increase the quantum of harm in the planning balance? IF overplanting would be likely to utilise the available grid connection more effectively by exporting at the MEC for a greater proportion of the time, would that increase the MWhr / year of renewably generated electricity exported to the grid above that which would be exported from a scheme with less overplanting? IF so would that increase the quantum of benefit in the planning balance? In that scenario would the appropriate planning balance weigh any overall harm from the scheme over the duration of the development, along with any legacy harm, against the overall benefits of the scheme, including the addition to the grid of x MWhr / year of renewably generated electricity for the duration of the development, along with any legacy benefit? IF so how would that approach to the assessment of overplanting square with Footnote 92 of EN-3?”
“is necessarily based on less than complete information. It is not intended to involve a detailed assessment of factors relevant to the grant of planning permission, nor a full assessment of any identifiable environmental effects.”