“AND UPON the 1st Defendant agreeing that the Decision was rendered unlawful by a material error of fact that was relied on by the Planning Inspector as making the development acceptable in landscape, character, and Conservation Area terms (“Ground 1 of the Claim”) and that the Decision would not have been the same had it not been rendered unlawful. AND UPON the 1st Defendant agreeing to consent to a quashing order under Ground 1 of the Claim.”
“(1) Decisions of the Secretary of State and his inspectors in appeals against the refusal of planning permission are to be construed in a reasonably flexible way. Decision letters are written principally for parties who know what the issues between them are and what evidence and argument has been deployed on those issues. An inspector does not need to “rehearse every argument relating to each matter in every paragraph” (see the judgment of Forbes J. in Seddon Properties v Secretary of State for the Environment (1981) 42 P. & C.R. 26, at p.28). ”
“i) There is a mistake to an existing fact. ii) The fact is uncontentious and objectively verifiable. iii) The Claimant is not responsible for the mistake. iv) The mistake played a material (but not necessarily decisive) part in the Decision. ”
“T1 3 x Mature Ash -Remove, T2, 1 x cherry - Remove, T3 2 x Thuja - lift canopy from current height of 2.5m to a height of 3.5 to 4m, T4 3x Holly - remove and replace with fruit trees or hedging, T5 mature apple - lift canopy from 2.5m to a height of 3.5 to 4m, T6 - mid-life spruce - remove and replace with fruit tree or hedging”
“One tree (T5) requires removal as a result of the proposed development, as it lies within the proposed new access to the new car parking area. It is also proposed to remove two limbs from tree T1 for Health & Safety reasons, as these are leaning over the existing car parking area and could present a future hazard. The removal of these limbs will not affect the overall health or visual amenity of this tree. Both of these trees are a part of an existing line of trees to the rear of the site and their removal will not have a significant impact on the overall appearance and visual amenity provided by these trees. ”
“2.25: …. The Appeal Scheme would preserve and enhance the character and appearance of the Selborne Conservation Area and the setting of nearby listed buildings. The development would have no adverse impact on the amenities of neighbouring residents and the landscaped nature of the site would be retained through the retention and provision of trees and hedgerows. …. 2.34 In their comments of 16/11/20 the Landscape Officer advised that, ‘Parked cars do not create the most appropriate or characteristic edge to Selborne, this space should be revisited’. In recognition of this and the ‘countryside edge’ that forms the eastern edge of the development site and the designated greenspace immediately beyond this, the car parking for the tourist accommodation was moved internally to the site to protect this sensitive rural ‘interface’. The new integrated car parking court will sit behind the belt of mature Cyprus, Holly, Ash and Spruce trees which will serve to shield the cars from longer distance views. The amendments to the proposal were made at the explicit request of the LPA’s Landscape consultee and are considered to constitute betterment of the pre-existing relationship of the site with the countryside edge.”
“To protect the character of the area, conditions are required which secure protection of the retained trees on the site, secure the scheme of soft landscaping and ensure replacement of any trees which die within a five year period, in order to ensure that the soft landscaping becomes established. ”
“5) Throughout the construction process, including demolition phases, the trees to be retained on the site shall be protected in full accordance with the details contained in the document ‘Arboricultural Method Statement and Tree Survey’ by Partridge Associated, dated8 March 2021 and drawing 2247/1B. ”