“Hedgerow (loss): Under the current proposals development of the site will result in a c. 5m net loss of hedgerow habitat (UK BAP priority habitat) to create an access. A c. 10m new native hedgerow will be planted elsewhere on-site to mitigate this loss (not currently shown on the proposals)… Each new section of Cornish hedgerow will be planted with native trees and shrubs and should be bordered by a minimum 3m development free buffer seeded with a native wildflower/ grass seed mix. New sections of hedgerow must be positioned to maximize connectivity across the site by connecting directly to retained hedgerows; and must be of the same construction type and width as the hedgerow lost.”
“Hedgerow (loss and degradation): Development of the site will result in a c. 5m net loss of hedgerow habitat (UK BAP priority habitat) to create an access. To mitigate this loss, new native hedgerow habitat must be constructed elsewhere on-site, measuring double the length of hedgerow to be lost in accordance with Cornwall Council’s pending Biodiversity Supplementary Planning Document (SPD).”
“If you are losing features of ecological interest then you need to compensate for them. Compensation is nearly always required at a greater level than the loss incurred because newly created habitats tend to have much smaller biodiversity value than the old features which have been lost. Note that compensation is not always acceptable. Loss of well established features such as mature trees and hedges, or coastal or benthic habitats are very hard to compensate adequately for and your ecologist will be able to advise you on whether this option is likely to be viable”
“Bees and other insects feed on pollen providing food for birds and other wildlife - Sanctuary and movement corridor for birds and other wildlife - Refuge for locally distinctive wildflowers and other plants - Wildlife linkage features to other habitats.”
“The Council has requested conditions to be applied. Where necessary I have amended the wording of these in the interests of precision and clarity in order to comply with advice in the Planning Practice Guidance…I have added a condition in the interests of biodiversity to secure the mitigation and enhancements pursuant to the Preliminary Ecological Appraisal which was submitted at the appeal.”
“Details of the appearance, landscaping, layout and scale (hereinafter called the reserved matters) shall be submitted to and approved in writing by the local planning authority before any development begins and the development shall be carried out as approved.”
“No development shall commence until a Landscape and Ecological Management Plan (LEMP) setting out the management and maintenance of green infrastructure to be managed for biodiversity and landscape purposes has been submitted to and approved in writing by the Local Planning Authority. For the avoidance of doubt the LEMP shall comply with the recommendations, mitigation and enhancement measures contained within the Preliminary Ecological Appraisal Report. All elements of the Landscape Scheme shall be implemented and maintained in accordance with the approved details unless otherwise agreed in writing by the local planning authority. All work shall be completed in accordance with the timetable agreed.”
“Third parties have also raised concern in terms of the impact of the proposed development on the ecology of the area. However, the outline planning permission requires, via condition, that mitigation and enhancement measures pursuant to the Preliminary Ecological Appraisal Report are secured via the submission of a Landscape and Ecological Management Plan (LEMP) prior to the development of the site. I am therefore satisfied that a mechanism is in place for appropriate ecological mitigation despite the removal of a part of the existing roadside hedgerow habitat to form the access.”
“In view of the above relevant case law, the [authority] is satisfied that the submitted plan and drainage strategy will, on the whole, ‘satisfactorily’ secure the management and maintenance of green infrastructure on the site for biodiversity and landscape purposes. This is deemed to be within the spirit and intentions of both the outline and reserved matters consents and their respective conditions.”