“The weight to be given to them will depend upon the circumstances of each case and is a matter for the decision maker. Interdependence would normally mean that each part of the development is dependent on the other, as, for example, in Burridge v Breckland District Council [2013] JPL 1308 at [32] and [42].”
“The threshold for irrationality in the making of such a judgment is a difficult obstacle to surmount (see e.g. Newsmith Stainless Limited v Secretary of State for the Environment, Transport and the Regions[2017] PTSR 1126 ).”
“The EIA Directive is intended to operate in a way which ensures that there is appropriate EIA scrutiny to protect the environment whilst avoiding undue delay in the operation of the planning control system which would be likely to follow if one were to say that all the environmental effects of every related set of works should be definitively examined before any of those sets of works could be allowed to proceed (and the disproportionate interference with the rights of landowners and developers and the public interest in allowing development to take place in appropriate cases which that would involve). Where two or more proposed linked sets of works are in contemplation, which are properly to be regarded as distinct “projects”, the objective of environmental protection is sufficiently secured under the scheme of the Directive by consideration of their cumulative effects, so far as that is reasonably possible, in the EIA scrutiny applicable when permission for the first project…is sought, combined with the requirement for subsequent EIA scrutiny under the Directive for the second and each subsequent project. The adequacy and appropriateness of environmental protection by these means under the EIA Directive are further underwritten by the fact that alternatives will have been assessed at the strategic level through scrutiny of relevant development plans…”
“But the Directives and jurisprudence of the European Court of Justice recognise that it is legitimate for different development proposals to be brought forward at different times, even though they may have a degree of interaction, if they are different "projects". The Directives apply in such a way as to ensure appropriate scrutiny to protect the environment, whilst avoiding undue delay in the operation of the planning control system. Undue delay would be likely if all the environmental effects of every related set of works had to be definitively examined before any of those works could be allowed to proceed. Where two or more linked sets of works are in contemplation, which are properly to be regarded as distinct "projects", the objective of environmental protection is sufficiently secured under the Directives by consideration of their cumulative effects, so far as that is reasonably possible, when permission for the first project is sought, combined with the requirement for subsequent scrutiny under the Directives for the second and each subsequent project.”
“If conditions of planning permission are to provide the answer to the problem of the connection of private sewers to public sewers which are not adequate to bear the additional load, it would seem essential that there should be input to planning decisions from both the relevant sewerage undertaker and OFWAT.”
“It is possible to subdivide the third category of consideration into two types of case. First, a decision-maker may not advert at all to a particular consideration falling within that category. In such a case, unless the consideration is obviously material according to the Wednesbury irrationality test, the decision is not affected by any unlawfulness… There is no obligation on a decision-maker to work through every consideration which might conceivably be regarded as potentially relevant to the decision they have to take and positively decide to discount it in the exercise of their discretion.”
“The principles are not complicated. Planning officers' reports to committee are not be read with undue rigour, but with reasonable benevolence, and bearing in mind that they are written for councillors with local knowledge…Unless there is evidence to suggest otherwise, it may reasonably be assumed that, if the members followed the officer's recommendation, they did so on the basis of the advice that he or she gave… The question for the court will always be whether, on a fair reading of the report as a whole, the officer has materially misled the members on a matter bearing upon their decision, and the error has gone uncorrected before the decision was made. Minor or inconsequential errors may be excused. It is only if the advice in the officer's report is such as to misdirect the members in a material way – so that, but for the flawed advice it was given, the committee's decision would or might have been different – that the court will be able to conclude that the decision itself was rendered unlawful by that advice. Where the line is drawn between an officer's advice that is significantly or seriously misleading – misleading in a material way – and advice that is misleading but not significantly so will always depend on the context and circumstances in which the advice was given, and on the possible consequence of it. There will be cases in which a planning officer has inadvertently led a committee astray by making some significant error of fact… or has plainly misdirected the members as to the meaning of a relevant policy…There will be others where the officer has simply failed to deal with a matter on which the committee ought to receive explicit advice if the local planning authority is to be seen to have performed its decision-making duties in accordance with the law…But unless there is some distinct and material defect in the officer's advice, the court will not interfere.”
“…First, there must have been a mistake as to an existing fact, including a mistake as to the availability of evidence on a particular matter. Secondly, the fact or evidence must have been ‘established’, in the sense that it was uncontentious and objectively verifiable. Thirdly, the appellant (or his advisers) must not have been responsible for the mistake. Fourthly, the mistake must have played a material (not necessarily decisive) part in the Tribunal's reasoning.”
“Detailed consideration has also been given as to whether the ‘Sewer Reinforcement Scheme’ forms part of the same project as the strategic mixed-use development of Plasdŵr. However, it was concluded that there are a number of factors that militate strongly against the scheme being an extension to the mixed-use scheme including that the proposal is: • being constructed on/under land which is not directly connected or adjacent to the mixed-use scheme and, in reality, is an expansion of the existing public sewerage network and, therefore, they are effectively stand-alone projects; • being undertaken by Welsh Water, a statutory undertaker, not the developer of the mixed-use scheme and on land within separate ownership; • being undertaken not to serve only the foul needs of the mixed-use scheme, but also of existing (and potential future) developments in the area, therefore, whilst there is a functional relationship there is no functional interdependence. 3.13 In light of the above, Members should note that a revised Screening Opinion has been adopted for the current application, which mirrors the Opinion for the overall infrastructure works (i.e. is not considered under 11(c) and is concluded to - not amount to EIA development).”
“Some disruption and inconvenience is likely to result from demolition and construction works, however, given the scale and nature of the works being undertaken in accordance with the submitted CEMP. It should be noted that the contents of the CEMP are wide ranging and separate legislation, including control in respect of health and safety and over noise and other sources of pollution, are relevant in respect of some matters.”