“3A.(1) The principal objective of the Secretary of State and the Gas and Electricity Markets Authority (in this Act referred to as “the Authority”) in carrying out their respective functions under this Part is to protect the interests of existing and future consumers in relation to electricity conveyed by distribution systems or transmission systems. (1A) Those interests of existing and future consumers are their interests taken as a whole, including…. (b) their interests in the security of the supply of electricity to them;”
“Ability to make claim 9. 1 If the licensee has received the Authority’s consent under paragraph 9.5, it may make a claim for a Last Resort Supply Payment, under standard condition 38 (Treatment of Payment Claims for Last Resort Supply) of the Distribution Licence, from each Relevant Distributor. 9. 2 The licensee must not make a claim for a Last Resort Supply Payment if, and to the extent that, it has waived its ability to do so by Notice given to the Authority before the Authority gave it a Last Resort Supply Direction. … 9. 4 The total amount of the Last Resort Supply Payment… to be claimed by the licensee must not exceed the amount by which: (a) the total costs… reasonably incurred by the licensee in supplying electricity to premises under the Last Resort Supply Direction and a reasonable profit, plus (b) any sums paid or debts assumed by the licensee to compensate any Customer in respect of any Customer Credit Balances, are greater than: (c) the total amounts recovered by the licensee through Charges for the Supply of Electricity to premises under the Last Resort Supply Direction (after taking all reasonable steps to recover such Charges). 9. 5 If the Authority considers it appropriate in all the circumstances of the case for the licensee to make the claim notified to it in accordance with paragraph 9.3, the Authority will give its consent to the licensee. 9. 6 The Authority may determine that an amount other than the one calculated by the licensee is a more accurate calculation of the relevant amount.” (Emphasis added)
“2.26 We would generally prefer a SoLR not to make a claim via these arrangements for costs it has incurred carrying out its role althoughwe recognise that circumstances may exist which would justify a departure from this general rule. The circumstances of every supplier failure are different and there may be some where a SoLR incurs costs which would not otherwise be recoverable. An efficient SoLR should be able to minimise its exposure to these costs. 2. 27. Following appointment of a SoLR that had not waived its right to make a claim, we will decide on a case-by-case basis whether it might be appropriate for a SoLR to make a claim on the levy. We would consider whether the amount of any claim or the reasons for any claim were reasonable. For example, we may in certain circumstances consider it appropriate to approve the claim where it relates to costs associated with the protection of customers who held a credit balance with the failed supplier as outlined above.” (Emphasis added)
“Our methodology criteria for SoLR levy claims are as follows: • Additional: whether the costs claimed are additional to the costs to the SoLR of serving existing customers. In addition, we consider whether these costs would have been expected at the time of the SoLR’s bid and whether any commitments were given in relation to these costs in their competitive SoLR bid. Although the SoLR is generally expected to know or predict the costs they will incur in serving a new customer base and take these into account in their competitive bid, there may be cases where this is not possible. • Directly incurred as part of the SoLR role: whether the costs were incurred as a result of taking on customers in an emergency situation as opposed to normal customer acquisition routes. It would not be appropriate for us to allow the SoLR to claim for costs they would have incurred through a normal acquisition route. • Otherwise unrecoverable: whether the SoLR could have recovered the costs through other means. It would not be appropriate for us to allow the SoLR to claim for costs it could have recovered through the administration process or customer charges, for example. • Unavoidable: whether the SoLR had made all reasonable efforts to avoid the cost in the first instance or absorb the cost. • Efficient: whether the SoLR has taken all reasonable steps to reduce the magnitude of any unavoidable and unrecoverable costs incurred, and therefore the total amount claimed.”
“We will consider allowing access to the industry levy for a Last Resort Supply Payment to cover these costs of honouring domestic customer credit balances and other costs. Our preference is for Licensees to waive their right to the levy. Where a Licensee does not waive their right to the levy, we would consider any claim under the levy on a case by case basis, and decide whether any claim was justified taking into account all the circumstances of the case.”
“23. State if the Licensee agrees to waive its right to make a claim for a Last Resort Supply Payment before being appointed a SoLR. 24. If not, please specify the basis on which the Licensee expects to make a claim for a Last Resort Supply Payment. This should specify what types of costs (or other areas as set out in the Relevant Licence Conditions), including but not limited to credit balances, the Payment would cover. Please specify the upper limit of any claim the Licensee would make for such a payment, or categories of costs to which the payment relates.”
“Can Direct Debits be automatically transferred to the new incoming supplier? Our view is that it would not be possible to transfer direct debits directly through the SoLR process. The SoLR could seek their own commercial arrangements alongside, but separate from, the SoLR process, with the current providers of direct debit management services to Extra Energy customers to help manage the transition to the new supplier.”
“ScottishPower’s systems and processes have the capacity to register and manage the additional customers from Extra Energy… has all necessary industry processes and arrangements in place to manage additional customers across Great Britain and is able to maintain adequate and increased credit cover where required within reasonable timescales.”
“The decision to appoint a SoLR involves Ofgem making a judgement taking into account the full range of criteria and all the information provided by suppliers. In total, we received eight submissions from suppliers, setting out the terms they would offer to customers if they were to be appointed as the SoLR. Below, we have set out the material factors on which we based our decision that Scottish Power’s proposal was the best deal for customers.”
“All of the suppliers who were willing to honour credit balances indicated their intention to use the levy to cover some or all the costs of honouring credit balances through the levy. Most suppliers intended to use the levy to cover all of the costs of honouring credit balances, with a minority offering to contribute to these costs. Scottish Power proposed to make a substantial contribution toward covering credit balances, thereby claiming the least through the levy overall and minimising costs to all consumers. The majority of suppliers stated their intention to use the levy to cover a range of additional costs they expected to incur if appointed as SoLR, other than the costs of honouring open credit balances. Scottish Power’s bid identified the fewest costs in this regard, as compared to others’.”
“[b]idders put forward a range of solutions to “onboard”
“we are significantly concerned with their post-SoLR compliance performance with regards to former Extra Energy customers, and it would be helpful if you can impress upon them [ScottishPower] the urgency of this situation.”
“3. Our current concerns with the company – compliance/enforcement 3. 1… There has been a significant delay in PWC generating final bills for former Extra Energy customers, which is due to the poor data that they inherited from Extra Energy which has required significant work to remedy… 3. 2. SP did not agree to buy the debt book and have argued that they consider it is PWC’s responsibility to sort out final bills. Whilst this is true to some extent, SP have a responsibility to the customers that they have inherited to ensure as smooth a transition to SP as possible, as well as to honour credit balances. PWC have requested ScottishPower to pay them for generating final bills for customers with credit balances, once they have resolved the data issues. ScottishPower are not happy about this, claiming this was a cost they hadn’t considered in their SoLR bid, and are seeking reassurance that they can claim for this from the levy. Our view is that it will be very difficult to justify costs related to this in a levy claim as it is ScottishPower’s responsibility as the appointed SoLR to ensure they do everything in their power to return credit balances to customers as soon as possible. We haven’t experienced this issue to this extent with other SoLRs.”
“1.31. We need to look in more detail at the information supplied to ScottishPower to confirm its view that it suggested that 92% of customers were on the DD payment method. We also need to consider why the debt levels of the ex-Extra Energy customers are so high – to what degree is the level of debt a consequence of failure in the information provided as part of the SoLR process, or of the timescale and process for returning customer credits and /or collecting debt, and where does the responsibility for these factors lie? However, before those questions we need to ask whether the industry levy can be used to protect SoLR suppliers from debt accrued after the transfer of customers? (My view, no, it cannot).”
“The claim contains some new elements which we have not seen before – for example customer debt and service/operational costs for credit balances. Therefore, this will take some time to consider and we may require additional information to understand more about the circumstances and rationale behind the individual figures.” “This type of claim has not been seen before. There is a significant question over whether this type of cost is recoverable – i.e. protecting SoLR suppliers from debt accrued after the transfer of customers.”
“Considered Direct Debit assumptions – Assumed transitioning Direct Debits would be straight forward – but this did not occur due to data protection issues (e.g. bank details) and then rules that they had to ask customer for consent. As default customers were then transferred to quarterly not monthly payment plan, caused further issues. Note: consider then the issue was assumption Direct Debit transfer was the root cause of issue (not realistic and not foresee the data protection/consent impact), rather than the percentage of customers on Direct Debit.”
“ScottishPower did not specifically indicate that they intended to claim for debt provision or associated costs, however ScottishPower did indicate that they may claim for unforeseeable and unexpected costs. It is considered that the industry levy is not a mechanism that should be used to recover customer debt to a SoLR supplier, irrespective as to how that debt has arisen. Costs reclaimed should be in relation to costs incurred as part of the transition period and it would be unreasonable and unexpected to consider that the industry levy would cover costs which were incurred significantly after the initial onboarding period. While it has been indicated that the increased debt level has been partly as a result of the lower than anticipated number of customers on direct debit mandates (than initially assumed), the information on the estimated percentage of customers paying by Direct Debit was not provided until after the SoLR bidding process was complete. Furthermore, it was reasonably foreseeable (and this seems to be a more significant factor) that ScottishPower would not be able to use the current licence and would require consent to use the Direct Debit details. As highlighted in earlier publications for SoLR events, as part of the SoLR process we revoke the existing licence and during the SoLR bid we ask what licence they would transfer customers too [sic] if they were actiing [sic] as SoLR. In addition, it is noted that circa half of the debt cost is associated with SME debt and it is difficult to see how it would be reasonably expected that the industry levy would cover costs for SME debt when SME credit balances are not covered. Businesses are expected to go through the administration process in the same way if any other service provider entered into insolvency proceedings.”
“Our view - debt 1. 42. We have not previously been asked to consent to the recovery of debt costs. To do so now would set a precedent that could have very significant consequences for the SoLR process. In particular, accepting that consumer debt could be recovered from the levy could reduce the incentive for future SoLR’s to chase consumer debt – and if more widely known could impact on the behaviour of at least some consumers of failed supplier, making it more difficult for SoLR’s to recover debt, thus creating an unvirtuous feedback loop into the process. 1. 43. Unless we wish to set a radical new precedent that risks increasing the costs passed to consumers, we need to reject the claim for debt costs. Whether it is entirely fair for the SoLR to cover the costs of debt where that debt is much higher than BAU levels, is another question.”
“1.30. ScottishPower has claimed£3,517k for debt costs. This is made up of the elements shown below, for the cost of following up customer debt, for working capital used to finance the debt, and the customer debt itself. 1. 31. In theory, the claim for debt appears to meet the tests that we would normally use to judge whether a cost is recoverable. •. The debt is an additional cost faced by ScottishPower that arose only in relation to customers taken on by ScottishPower acting in its role as a SoLR supplier. •. ScottishPower say that they anticipated that debt would arise, as normal, and made a provision of£1.2m for debt, but the debt is£4m (hence the£2.8m claim for debt provision). Factors raised by ScottishPower include its expectation, based on information provided by us following its appointment, that 92% of customers were on DD payment method (the outturn position is 56% on DD). ScottishPower was unable to use customers prior DD mandates and this (ie they needed fresh consent), and this [sic], and issues with customer data and customer reluctance to pay bill[s] while credit balances were not confirmed, led to levels of debt [that] was substantially higher than anticipated/expected compared to the same number of customers acquired by normal acquisition routes. •. While debt is in principle recoverable, there is a point in the debt recovery cycle where it is commercial practice to cease recovery efforts and either write the debt off / sell the debt book/ pass it to an agency for collection. 1. 32. Whether the level of customer debt was avoidable and whether ScottishPower has done all that it can to collect the outstanding debt and therefore minimise the claim, is a judgement call. However, it is arguable that it would be unreasonable and unacceptable to place the burden of customer debt on the industry levy, as this would make consumers responsible not just for the economic and efficient cost of the work necessary to on-board the customers of a failed supplier and refund credit balances a supplier failure, but also the cost of customer debt. The levy is not a mechanism that should be used to recover customer debt to a SoLR supplier, irrespective as to how that debt has come about.” (Emphasis added)
“1.21 We are uncomfortable with ScottishPower’s claim for£3.5m for customer debt (and related costs). Customer debt is a commercial risk for any supplier. In this case debt costs for the ex-Extra Energy customers are higher than forecast by ScottishPower based on BAU metrics for its existing customer base. 1. 24. Consenting to this element of the claim, without ScottishPower having specified that they would seek to recover debt in the RFI, or in the absence of an agreement that it could be recovered, would set an unhelpful precedent that could expose the SoLR regime to the cost of unanticipated consumer debt. This could lessen the incentive for future SoLR’s to collect debt. 1. 25. Equally, a decision to rule out the recovery of debt may reduce the flexibility we have for future SoLR’s. If general market conditions and concerns about the issue of customer debt (including the overhang of debt from a failed supplier) make suppliers less likely to volunteer for a SoLR role, we may end of having to instruct a supplier to act as a SoLR. Should we do so, customer debt is one of the costs that the levy would be required to consider (and perhaps we would need to provide some reassurance on this at the outset). 1. 26. In the absence of perfect information, it is easier to reach a yes/no decision on the basis of a general principle, than to consider any point in between. If we wish to retain flexibility to consider debt as a recoverable cost for future SoLR’s we could explore options based on a risk sharing arrangement for consumer debt. On that basis we might consider allowing ScottishPower to recover: [the memo goes onto set out various arithmetic risk sharing options including the cost of work to recover the debt; the cost of the debt and the collection costs ora portion of the debt costs.] 1. 27. Of these options, 50:50 may be the sweet spot. It feels more robust to go with 50:50 on the basis that while ScottishPower made no explicit provision for the recovery of debt, and without seeking to pin down the responsibility for the extent of the debt, we are broadly sympathetic to the situation in which it found itself (and which other SoLRs could find themselves). This approach would allow ScottishPower to recover half of the debt and the costs of collection (£1.5m ). 1. 28. If we wish to we could also consider consenting to ScottishPower recovering the cost of working capital for the entire debt as part of the calculation of the cost of capital. This could lift the total recovery for debt related costs to midway between£1.5 and£2m (possibly closer to£2m ). 1. 29. An alternative approach is to reject the claim for debt costs and only allow debt costs in future where a SoLR has expressly provided for them in the RFI or we have instructed a supplier to act as a SoLR. This would be justifiable on the basis that the supplier made provision for the debt or did not volunteer for the SoLR role. But if we restricted the recovery of debt to SoLRs we appointed then it could narrow the choices we may have between suppliers. 1. 30. I think we need to have a further discussion on this point, which has a significant impact on the amount we would be minded to consent to and would represent an important evolution in our approach to assessing LRSP claims.”
“1.2 ScottishPower's claim is the most complex we have seen so far. The background is as much a part of the story as the costs claimed: the circumstances of the SoLR incident; the quality of the SoLR data; the tension in the relationship between PwC (the administrators for Extra Energy) and ScottishPower, which appears to have driven by different viewpoints and competing objectives; and issues that ScottishPower did not anticipate before appointment. 3. 3 We are uncomfortable with ScottishPower’s claim for£3.5m for customer debt (and related costs). Customer debt is a commercial risk for any supplier. In this case debt costs for the ex-Extra Energy customers are higher than forecast by ScottishPower based on BAU metrics for its existing customer base. 3. 4. On balance, we recommend that we do not consent to the recovery of any of the£3.5m claim for debt costs. Each levy decision is taken on a case-by-case basis, and we are confident that we could reject this element of the claim while retaining the flexibility to allow customer debt costs to be recovered in future. For example, we may be more receptive to a case where a SoLR has expressly provided for them in the RFI or where we have instructed a supplier to act as a SoLR.”
“ScottishPower’s claim has presented us with a number of novel issues, and we have given considerable thought to these in reaching a minded-to position. In principle we are minded to consent to the recovery of the costs of credit balances and certain related costs, i.e. customer enquiries and direct complaints, billing, IT costs and for the costs of working capital associated with these costs. We are not minded to consent to the recovery of the costs of the Ombudsman Scheme, customer debt, or for transportation and registration services. The costs we are not minded to consent to represent around£5m of the claim and we appreciate that ScottishPower will be disappointed by our position. Our minded-to position aims to recognise the particular and challenging circumstances of this case, and balance this with the interests of consumers who ultimately fund the industry levy. We recognise that you may be disappointed and we would be happy to discuss our minded-to position. I have set out below a high-level summary of our position on those costs we are not minded to consent to.”
“Consumer debt The collection and recovery of customer energy debt is a commercial matter for suppliers to pursue. While the level of consumer debt may be higher than ScottishPower anticipated, we do not consider it would be appropriate for the industry levy to fund consumer energy debt. Consumer debt is distinct from credit balances and other costs associated with on boarding customers in order to comply with the terms of the Last Resort Supply Directive. It is in this cost, particularly, that we consider the LRSP claim to be broader in scope than the basis on which ScottishPower was appointed and different to the cost claimed for credit balances (and costs associated with credit balances and working capital), which is the basis on which ScottishPower was appointed.”
“noted they would review the detail within the slides, noting that it was a helpful meeting and the points we shared were useful. [The Ofgem representative] noted that Ofgem had already considered our claim in a lot of detail, but they would consider the additional detail we provide and come back to us.”
“We note the points ScottishPower has made in the additional information and have considered them carefully. It is for the SoLR to make the claim and to provide the evidence to support the claim. In making a decision we do not consider, for example, that we are bound to consent to a cost if we did not previously exclude it from the type of costs that could be claimed. Equally, we do not consider that we are bound to consent to the recovery of all or part of the cost of bad debt (or any other cost), because, in the RFI, ScottishPower said it may make a claim ‘if exposed to unexpected costs’. As we noted previously, we consider bad debt to be distinct from credit balances and associated costs. While we accepted that data quality issues were a factor in the cost of credit balances and associated costs, we do not consider that this restricts our discretion to reach a different position on the cost of bad debt. Each claim, and each part of a claim, is considered on its merit. In securing an outcome in the best interests of consumers we must have regard to the wider context of the SoLR regime and our assessment of claims from other SoLRs, in addition to reviewing the evidence against the criteria in our methodology.”
“Our decision process and methodology Our process to reach our minded-to position consisted of: • A quantitative check of the methodology for each cost item claimed. This includes determining how each total cost item was calculated based on data sent to us. • Ensuring costs are in line with commitments made at the time of the SoLR appointment. • Validation of assumptions with other data sources, where appropriate. • A qualitative assessment of each claim item against our methodology criteria. Our methodology is outlined in Annex 1.” (Emphasis added)
“We consider that consumer debt is different to credit balances and other costs faced by a SoLR when on-boarding customers and is a commercial matter for the SoLR to manage ... We consider that a claim for consumer debt goes beyond the reasonable scope of the basis on which ScottishPower was appointed and the costs that it indicated it may claim. Consumer debt is a commercial consideration and we would expect a supplier bidding for a SoLR appointment to have accounted for this in the bid, along with other commercial factors such as forecasts for margins and retention of customers … in our view consenting to a claim for debt costs could increase the potential costs of supplier failure faced by existing and future consumers if it lessens the incentive on a SoLR to collect debt effectively, in the knowledge that debt that could not be collected could be recovered as part of a LRSP claim … We welcome responses from stakeholders on whether our position strikes an effective balance between providing an appropriate framework for SoLR’s to recover additional costs and protecting the interests of existing and future energy consumers.”
“Claim for a Last Resort Supply Payment As set out in the gas and electricity supply standard licence conditions, a supplier may make a claim for any additional costs it incurs in complying with a LRSD. As part of their competitive bid to become a SoLR, a supplier will include whether they expect to make a claim for a LRSP, or whether it will waive this right, in whole or in part. As stated in our Guidance, our preference is for the SoLR not to make any claim, and we expect efficient SoLRs to be able to minimise their exposure to otherwise unrecoverable costs to reduce the costs smeared across the rest of the market through a LRSP. In our Guidance, we explain that we will decide on a case-by-case basis whether it might be appropriate for a SoLR to make a claim under these arrangements. We also explain that we would consider whether the amount of any claim or the reasons for any claim were reasonable. In that Guidance, we note that, in certain circumstances, we may consider it appropriate to approve a claim where it relates to costs associated with the protection of customers who held a credit balance with the failed supplier. ScottishPower indicated at the time of our SoLR appointment process that it would not waive its right to make a claim. ScottishPower committed to funding£10m of open and closed credit balances and said that it would claim for any balances above this£10m level and associated costs, for example to cover working capital requirements.”
“Our decision On balance, taking into consideration all information available to us and the specific circumstances of this case, we are minded to consent to ScottishPower claiming a LRSP of up to£10.6m . We have taken this decision in light of the broader market considerations and our wider statutory duties to protect both existing and future consumers. … For the avoidance of any doubt, we consider on a case-by-case basis whether it may be appropriate for any SoLR to make a claim for a LRSP. We have set out below our reasons for our decision. This should not be taken as setting a precedent for any future claims, which would also be considered on their merits and on a case-by-case basis, taking into account all relevant circumstances of the particular case.” (Emphasis added)
“We have sympathy for the respondent’s concerns about the level of operational costs claimed by ScottishPower. … However, after very careful consideration of the circumstances of this case and all of the information available to us, and on a fine balance, our decision is to consent to the recovery of ScottishPower’s claim for service/operational costs. … ScottishPower incurred unforeseen costs when billing customers – for example those with credit or debit balances less than£30 . Due to the circumstances of the failure of Extra Energy, ScottishPower did not have direct access to Extra Energy’s billing platform and relied upon the arrangements put in place by the administrator with a third-party billing provider. As a result the billing costs were in excess of those usually incurred by suppliers when issuing monthly or quarterly bills. While we consider that the billing costs are high, our decision on balance to consent to the recovery of the service/operational costs claimed by ScottishPower reflects the volume of the work necessary to on-board customers, the data quality and other significant issues which ScottishPower encountered.”
“We recognise that a SoLR supplier can face differing levels of challenge with data quality. We consider that the work undertaken by ScottishPower was required to ensure that the data for former customers of Extra Energy was both complete and accurate, a necessary condition for the successful on-boarding of customers and resolution of customer enquiries. Our decision is, therefore, to consent to the recovery of this cost.”
“Stakeholder views One respondent agreed with Ofgem’s minded-to position on consumer debt. The respondent considers that a claim for additional bad debt goes beyond the reasonable scope of a LRSP claim and any additional bad debt costs should be factored into a supplier’s SoLR bid. In making its claim for these costs, ScottishPower has noted it considers that consumer debt is no different from other costs incurred by a SoLR and considers that Ofgem’s position on debt is inconsistent with its minded-to position to consent to the other costs which ScottishPower has claimed. They have also noted that, in bidding for the SoLR appointment, ScottishPower did not place a limit on the value of the claim it would make and said that it may make a claim for any unexpected costs. ScottishPower considers that the claim for debt is consistent with the criteria that Ofgem uses to assess claims. ScottishPower have suggested that, if Ofgem’s decision is that it is unlikely to allow a LRSP claim for debt costs, future SoLRs will be incentivised to "price in" an additional margin of error for bad debt (to cover unforeseen circumstances). They consider that this would result in worse outcomes for consumers (by suppliers potentially bidding with higher rates in respect of all SoLR appointments), rather than allowing a mechanism by which unforeseeable debt can be recovered from the industry levy in appropriate cases, thus avoiding the need for it to be priced in to the bids made by SoLRs. Our decision We consider that consumer debt is different to the other costs that ScottishPower has claimed which are directly related to the obligation to refund customer credit balances and to the work necessary to validate and migrate customer data from Extra Energy to ScottishPower’s system, to allow ScottishPower to comply with the terms of the LRSD. We recognise that ScottishPower did not place a limit on the value of the claim that it reserved the right to make, and indicated that it may make a claim for any unexpected costs. However, we continue to consider that the claim for consumer debt is outside the reasonable scope of the basis on which ScottishPower was appointed as the SoLR and the reasonable scope of any LRSP claim. While we do not set out in advance the costs that a SoLR may or may not claim, as noted above, our expectation is that a claim will be principally for the cost of credit balances and costs associated with migrating customers from the failed supplier to the SoLR. In making a decision, we are able to have regard to a wide range of factors, including (for example) our view of whether it is reasonable that the wider industry should fund the commercial risks associated with the cost of debt. Taking account of all of the circumstances of the case and having regard to our duty to protect the interests of consumers, we do not consider that the claim for debt is a reasonable cost to be recovered via the industry levy. While we are open to a range of costs forming part of a claim for a LRSP, we consider that a decision not to consent to the recovery of consumer debt sets the most appropriate balance between the ability of a SoLR to recover legitimate and efficient costs and protecting the interests of consumers. We do not consider that our approach should lead to potentially worse outcomes for consumers (i.e. suppliers potentially bidding with higher tariffs being charged to consumers in respect of all SoLR appointments), and note that only a single respondent has raised this as a concern. Nor do we consider our decision on the claim for debt to be inconsistent with our decision on the claim for the other costs claimed by ScottishPower. Our decision to consent to the recovery of service/operational and data quality costs is finely balanced and we do not consider that a decision to consent to some of the costs in the claim means that we are bound to consent to all of the costs claimed by ScottishPower. For the above reasons our decision is that we do not consent to the recovery of ScottishPower’s claim for the recovery of consumer debt.”
“For the avoidance of any doubt, we consider on a case-by-case basis whether it may be appropriate for any SoLR to make a claim for a LRSP. We have set out below our reasons for our decision. This should not be taken as setting a precedent for any future claims, which would also be considered on their merits and on a case-by-case basis, taking into account all relevant circumstances of the particular case.” … While we are open to a range of costs forming part of a claim for a LRSP, we consider that a decision not to consent to the recovery of consumer debt sets the most appropriate balance between the ability of a SoLR to recover legitimate and efficient costs and protecting the interests of consumers.” (Emphasis added).
“Where the Act has conferred the decision-making function on the Director, it is for him, and him alone, to consider the economic arguments, weigh the compelling considerations and arrive at a judgment… so long as he directs himself correctly in law, his decision can only be challenged on Wednesbury grounds. The court must be astute to avoid the danger of substituting its views for the decision-maker and of contradicting (as in this case) a conscientious decision-maker acting in good faith with knowledge of all the facts… If (as I have stated) the court should be very slow to impugn decisions of fact made by an expert and experienced decision-maker, it must surely be even slower to impugn his educated prophesies and predictions for the future.”
“noted they would review the detail within the slides, noting that it was a helpful meeting and the points we shared were useful. [The Ofgem representative] noted that Ofgem had already considered our claim in a lot of detail, but they would consider the additional detail we provide and come back to us.”