"1. The identified improvements to mitigate the impact of the development on the highway network are required prior to development commencing in the area. The implementation and timing of the required improvements cannot be guaranteed. Without these improvements congestion on the main highway network will increase as will 'rat running' through adjacent residential streets all of which will introduce additional hazards on the highway. Additional delays will also affect the reliability of bus services. [...] 2. The suggested improvements for junctions not included in the CIL schedule are not considered adequate to mitigate the impacts of the development on the highway leading to an unacceptable level of congestion."
"[...] the argument presented was that the primary reason for refusal was not considered valid as where highways infrastructure improvements are set out in a CIL list; that infrastructure can only be provided through the payment of a CIL contribution. The timing of the delivery of the improvements is also not within the developer's control. A requirement that the improvements are delivered prior to development is therefore inconsistent with the items being on the CIL list. Therefore in paying the CIL contributions the developer is doing everything that can be asked of them in terms of mitigation for those items on the CIL list. Legal advice on this matter has also been sought. It has been confirmed that the case set out by the applicant was sound and the reason for refusal initially recommended could not be sustained, as there is no legal mechanism for the developer to deal with the required mitigation measures previously identified, other than through paying the CIL charge."
"Of the six junctions set out above the following three junctions are of particular relevance to the consideration of the current application [...]"
"Don't vote or take part in the meeting's discussion on a proposal unless you have been present to hear the entire debate, including the officers' introduction to the matter. This would include where the committee is considering an adjourned item or a deferred item where that matter is not being fully reheard at the meeting and the member was not present at the earlier committee meeting."
"No development approved by this permission shall be commenced until full details of the proposed means of foul drainage disposal, including if proposed, details of any proposed Package Treatment Plant and any necessary environmental permits, have been submitted to and approved in writing by the Local Planning Authority. The approved drainage works shall be completed prior to the completion or occupation of any dwelling on site, whichever is the sooner. [...] 19. There shall be no discharge of foul or contaminated drainage from the site into either the groundwater or any surface waters, whether direct or via soakaways. Prior to being discharged into any watercourse, surface water sewer or soakaways system, all surface water drainage from parking areas and hardstandings shall be passed through trapped gullies and silt traps to BS 5911:1982 with an overall capacity compatible with the site being drained and shall be retained thereafter."