“10. The test for viability is that the evidence indicates that the current cost of building out the entire site (at today’s prices) is at a level that would enable the developer to sell all the market units on the site (in today’s market) at a rate of build out evidenced by the developer, and make a competitive return to a willing developer and a willing landowner. 11. The developer will need to demonstrate to the planning authority, and to the Planning Inspectorate on appeal, that the affordable housing obligation as currently agreed makes the scheme unviable in current market conditions. 12. A viable affordable housing provision should be proposed. This should deliver the maximum level of affordable housing consistent with viability and the optimum mix of provision. The proposal may consider whether adjustments should be made to the affordable housing tenure and mix and, where relevant, phasing may also be considered. Timing and level of off-site affordable housing contributions may also be considered, as may any other aspect of the affordable housing requirement. 13. The developer will need to submit clear, up-to-date and appropriate evidence. Wherever possible, this should take the form of an open book review of the original viability appraisal and should clearly demonstrate, by reference to evidence, that the proposals are not viable in current market conditions. The “original viability appraisal” is that which is the most recently agreed by the local planning authority and developer. 14. In those cases where an original viability appraisal was not prepared prior to planning permission being granted, the developer must clearly demonstrate through evidence why the existing scheme is not viable. A proposal to bring the scheme into viability should be submitted. 15. At appeal, if the developer is unwilling to proceed on an open book basis, general evidence of changes in costs and values since permission was granted can be submitted; however developers must consider whether this approach will provide sufficient evidence for the Planning Inspectorate to make a robust, impartial decision on viability.”
“22. Revised affordable housing obligations, in line with current market conditions and based on the test of viability in this Guidance, should incentivise developers to start building. 23. Section 106BC ensures that if an Inspector modifies an affordable housing obligation on appeal, that modification is valid for 3 years. If the development is not completed in that time, the original affordable housing obligation will apply to those parts of the scheme which have not been commenced. Developers are therefore incentivised to build out as much of their scheme as possible within 3 years. It will not be sufficient to commence one part of the development to secure the revised affordable housing obligation for the whole scheme. If developers are concerned about the viability of their scheme at the end of the 3 years, they can seek to modify the agreement again. This could be done through voluntary renegotiation or by making a new application under Section 106BA. 24. This 3 year period, and the need to secure as much development as possible in that period, should incentivise developers to build out. Local planning authorities may wish to make similar time-limited modifications or conditions when considering an application under Section 106BA. 25. It should be noted that Sections 106BA and 106BC prevent the outcome of the first application in relation to a planning obligation being more onerous for the applicant than the existing obligation. Care should be taken to ensure revised affordable housing requirements do not exceed the overall level of obligation required under the original agreement. Care must also be taken to ensure that any modified requirement meets the statutory and policy tests for planning obligations. 26. In the event of an appeal, the Inspector will consider all the evidence before them. Should the Inspector issue a new affordable housing obligation for a 3 year period, it will include provisions to reapply the requirements of the original agreement for the part of the site that remains uncommenced.”
“1. The appeal is allowed. For a period of 3 years from the date of this decision the planning obligation…………. shall have effect subject to the modifications as set out in the Schedule at the end of this Decision. Main Issue 3. The main issue in this appeal is whether the affordable housing requirement means that the development is not economically viable and if so, whether the obligation should be modified. Reasons Background 4. The appeal site is a large area of recent development at Chatham Quays. The development comprises 332 residential units and about 5,700 sq.m of commercial floorspace (retail and leisure). Construction of almost all of the development is complete and agreed figures presented in the Statement of Common Ground (SOCG) indicates that, as of July 2015, of the 332 consented flats, 229 are sold, 44 shared ownership units have been sold to a RSL, 39 are rented out and 20 remain vacant. In relation to the 16 commercial units, 6 are complete and are let and 10 remain vacant with works outstanding before they can be occupied. The SOCG records that these 10 units are deleted from the ratings list as they are not capable of occupation, although they have been constructed to shell and core. 5. The relevant schedule of the Planning Agreement relating to the affordable housing contribution was structured such that one-third of the amount would be due after occupation of the 75th unit, the 153rd unit and finally the 229th unit. The issue of viability was discussed between the developer and the Council in 2010 when it was agreed that the staged payments would be deferred until near the end of the scheme upon occupation of the 300th residential unit, in the hope that viability improved. However, payment was not made at that stage and the full amount of the contribution remains outstanding. Is the scheme viable? 6. There is a great deal of information relating to the viability of the scheme. The short answer to this question is contained in the SOCG, wherein the Council agree with the appellants’ figures and conclusion, that the scheme is not viable, with a projected loss of£12.35m . There is no evidence to contradict or cast any doubt over this figure. Therefore, I conclude that the scheme is not viable. Has the scheme stalled? 7. The DCLG guidance ‘Section 106 affordable housing requirements – review and appeal’ states that “unrealistic Section 106 agreements negotiated in differing economic conditions can be an obstacle to house building. The Government is keen to encourage development to come forward, to provide more homes to meet a growing population and to promote construction and economic growth. Stalled schemes due to economically unviable housing requirements result in no development, no regeneration and no community benefit.” 8. There is no definition of what constitutes a “stalled scheme”
““the development”, in relation to a planning obligation, means the development authorised by the planning permission to which the obligation relates”