“solar farm and associated development”
“construction of a solar park comprising the installation of (circa) 14,200 ground mounted solar panels; inverter cabin; electricity substation; switchroom; coms building; pole mounted CCTV system; 2.4 metre high security fencing; associated access gates and gravel roads.”
“15.0 Flood Risk TGC commissioned a Flood Risk Assessment (FRA) and this accompanies the application. The Site is located in Fluvial Zone 1. This implies that the entire developable area of the Site has a lower than 1 in 1,000 year probability of being affected by fluvial flooding. Notwithstanding the above, the Proposals have the potential to introduce impermeable area around the Site where the land has previously been permeable and thus could increase the flood risk to adjacent sites. The proposals would only introduce a small area of impermeable surfaces through the steel pile system used for the tables/racking system and the inverter stations concrete bases. Any access and maintenance roads are proposed to be constructed from permeable materials and will therefore not contribute to increasing runoff rates from the Site. The total impermeable area equates to approximately 270m², which is only around 0.25% of the totally site area and will have a small impact on run off rates from the Site. It is proposed to incorporate a SuDS scheme, as detailed within the FRA accompanying this application. The scheme will effectively reduce the run off rate to less that the current runoff rates, as storage and infiltration on site will be improved. On the basis of the above, it is considered that the Proposals comply with Policy CS 18 of the Shropshire Core Strategy as the development would include appropriate SuDS to manage surface water and reduce existing run off rates.”
“ Elements of setting that contribute to the significance of the heritage asset 5.19. The building derives its significance in part from its evidential value, contained in its historic post-medieval fabrics and surviving features. 5.20. Further significance is derived from the building’s rural, mostly agricultural, setting which reflects well the setting within which the property would have originally been constructed. Impact of the Proposed Development 5.21. Development of a solar PV array at the Site will not impact upon the building’s physical fabric or its immediate rural setting and therefore will not alter the evidential value which this heritage asset holds. 5.22. Views toward the Site from the Listed Building are well screened by the hedges and trees which comprise the property’s northern boundary. 5.23. It is assessed that the Proposed Development will not present any visual impact upon the Listed Building’s wider landscape setting and will not detract from the ability to understand, interpret or appreciate the Listed Building, nor affect the limited value which its wider setting contributes to its overall significance. No negative effect on the Listed Building’s setting is predicted.”
“ Elements of setting that contribute to the significance of the heritage asset 5.26. The Conservation Area derives its significance from the group value of its historic buildings and area’s informal layout and wide variety of architectural forms and styles. The Conservation Area contains fine examples of half-timbered, brick and stone buildings in a variety of traditional building styles with a Grade II* Listed Parish Church of All Saints situated within a spacious setting. Impact of the Proposed Development 5.27. The Proposed Development is not visible in views from the majority of the Conservation Area, where extant buildings, mature trees and hedges, along with the undulating local topography, serve to effectively screen the area from the Site. The only exception may be the area to the extreme south of the churchyard, where there may be intermittent views across the landscape to the Site, more likely in winter when intervening deciduous trees will have lost their foliage. It is assessed that this potential change to the wider agricultural setting of the Conservation Area would result in no adverse impact upon its significance.”
“SuDS Design The impermeable areas across the site are small, therefore no formal drainage is required. As such a pragmatic approach has been take to promote infiltration and create storage across the site. This involves the installation of swale and scrape features running parallel to the site contours within downslope areas of the site. These features will intercept and distribute flows, create storage, attenuate runoff and promote infiltration across the site. Since the modules are located on a sloped frame between approximately 0.8m and 2.5m above ground level, it is anticipated that rain falling on each solar panel table will runoff the panels and flow/infiltrate in the sheltered rain shadow area underneath the down-slope modules. A 25mm gap surrounding the panels will allow water to drain off each module. In addition the SuDS design will not consider the runoff from the access and maintenance roads as these will be constructed of grass trucks /unbound crushed stones / gravel or similar permeable materials, which will allow infiltration of water on these areas. The access roads will therefore not increase surface water runoff rates from the site. The enclosed layout indicates the solar PV modules will be supported by steel racking systems, which are to be set on driven piles. The increase in impermeable area due to the piles has been estimated to be around 40m². Including the 4 intervener stations with a plan of around 30m² each and the POC/switch gear station of around 63m², the additional impermeable area is around 183m². Applying a 20% increase for inconsistencies the total impermeable area is around 270m². Therefore a conservative estimate of the volume of runoff from the total impermeable area had been calculated to be approximately 20.6m³ for a 6 hour duration, 1 in 100 year rainfall event. In order to adopt a pragmatic approach and promote infiltration across the site, a system of swales and scrapes are proposed to manage the surface water runoff. The details showing surface water management features of varying storage capacity are outlined in Drawing 3001.”
“Further to the below, please find attached Site Design Rev. A5. This supersedes Rev. A4. You will note that we have removed all the panels to the north of the existing overhead line, bringing the panels well away from the ridge line and containing them behind and below this existing visual element. We are also happy to reduce the panels to a maximum height of 2.6m… We’re happy to make these changes to alleviate the specific concerns raised over the last few days from the local community, however are somewhat frustrated that these weren’t brought up before. For example, we repeatedly offered to meet with the Parish and the anti-group however this wasn’t take (sic) up. For example, the below is from my email of28 October 2014 into which you were copied.”
“I have seen the proposed revision posted on the portal today. Mr Jamieson states in his e mail that they have removed all the panels to the North of the existing power line. When you look at the plan he provides you can see this statement is not true. They are proposing to remove the panels only on the western side of the site. The eastern side which is more visible from the viewpoints we have used is unaltered. Consequently the changes have no effect in reducing the impact on landscape character nor the visual impact that our viewpoints demonstrate. There is no ridge on the eastern side of the site other than the ride to the south at the top of the slope where they are proposing the locate the comms building, substation and switch room.”
“The amendment did not affect the energy output, the area of the site or any other key aspects of the proposals. The layout changes were considered at the time by the Council to be minor and beneficial in the context of the scale of the development and relevant land use issues. The Council took the view that a formal public re-consultation was not essential in the circumstances and the Inspector accepted this position in determining the application.”
“The proposals are inappropriate in terms of scale and location and fail to protect and enhance the natural and historic environment and the and the character and high quality of the local countryside. They are therefore contrary to Core Strategy Policies CS5, CS6 and CS17. The proposals also fail to sustain and enhance the significance of the setting of the Neen Sollars Conservation Area and associated heritage assets and therefore conflict with paragraphs 131, 132, 137 and 137 of the NPPF. The renewable energy benefits of the proposals are significantly and demonstrably outweighed by the adverse impacts.”
“The Inspector notes that in the email exchange with the Council on6th March 2015 various amendments were offered and some of these plans have been submitted with the appeal documents. While he seems to have Rev A5 on the layout it is actually still marked A4 and although the area covered has decreased the number of modules has gone up to 17,180 – clearly the appellant needs to sort this out. However, he does not believe these were ever the subject of consultation and, since the minutes of the committee meeting have not been provided, it is not clear if these suggested changes were reported to members before they determined the application.”
“Rev A5 of the site design was submitted6th March 2015 as noted below. This accompanied the appeal as it was the layout which Grahame [the second defendant’s planning officer] based his presentation on. He was happy to accept this layout as part of the application, supported its inclusion as part of the scheme and it appears on the online public register. The number of panels has increased as the row spacing has been decreased.”
“Whilst not strictly relevant to the introduction of the plan we also note that the developer submitted revised plans at the last minute and that these were not subject to further and proper consultation. It is not clear if those plans included a red line change to move the track in response to issues raised by the ecology report by Shropshire Council as offered in correspondence from the developer. They certainly changed the layout of the panels and introduced a second inverter building and yet submitted no new reports substantiating the change such as a revised flood report explaining why the run off from more tightly packed panels would not be an issue.”
“7. On6 March 2015 the appellant made a number of amendments to the submitted planning application. These included a revised site design (layout), some changes to the northern boundary landscape treatments and an offer to reduce the maximum height of the proposed panels to 2.6m. The design and height of the perimeter security fencing had already been amended. 8. The changes were put forward to address concerns raised by SOGHCG and others. The main change was to draw back the northern edge of the panels in the western of the two fields to the line of the overhead power cable thus removing the panels from the north-facing slope in that area. However, in doing so the appellant has increased the number of panels that would be installed from the number given in the summary details above to some 17,200. That is an increase of 21%. The appellant pointed out during the site visit that this would be accommodated by reducing the distance between the arrays. I have no evidence about the impact of this, if any, on the scheme output or the construction period. 9. The Council has confirmed that these changes were not subject to consultation but were reported, displayed and explained to the council members. I understand that they visited the appeal site on the same day that the planning application was determined. The decision that they made was based on the changes put forward on 6 March. 10. This is not a case where the appellant is seeking to amend the proposals through the appeal process. The changes were accepted by the Council notwithstanding the absence of further consultation. Furthermore, SOGHCG and others have had the chance to make comment upon them as part of the appeal process. Taking all these matters into account, I have determined this appeal on the same basis as the Council.”
“The proposed scrape and swale system shown in drawing J-4864-CFM 3001 in the Flood Risk Assessment is acceptable.”
“132. When considering the impact of a proposed development on the significance of a designated heritage asset, great weight should be given to the asset’s conservation. The more important the asset, the greater the weight should be. Significance can be harmed or lost through alteration or destruction of the heritage asset or development within its setting. As heritage assets are irreplaceable, any harm or loss should require clear and convincing justification.”
“Setting of a heritage asset: The surroundings in which a heritage asset is experienced. Its extent is not fixed and may change as the asset and its surroundings evolve. Elements of a setting may make a positive or negative contribution to the significance of an asset, may affect the ability to appreciate that significance or may be neutral.”
“Can a proposed scheme be amended?”
“N.2.1 If an appeal is made the appeal process should not be used to evolve a scheme and it is important that what is considered by the Inspector is essentially what was considered by the local planning authority, and on which interested people’s views were sought.”
“ 9. The delivery of an efficient, customer focused appeal process which is of benefit to all depends on continuing constructive dialogue between the applicant and the local planning authority during the progress of planning applications. Where such dialogue takes place it should be possible for acceptable amendments to be agreed prior to the local planning authority’s decision. Thus should there be any subsequent appeal it can be about the scheme considered by the local planning authority, including any amendments made to overcome legitimate planning concerns. This allows the local planning authority to conduct any necessary public consultation in accordance with their SCI, ensuring that any third parties who may be interested in a proposal have a fair opportunity to comment on any amendments to a scheme before it comes to appeal… 13. However, where it is clear that the local planning authority are unwilling to co-operate in a constructive dialogue it may be necessary for the appellant to carry out consultation on amendments to a scheme on which it is proposed to appeal or where an appeal has been lodged. In deciding whether the amendments can be accepted in such cases it will be crucial to consider proposed amendments and make their views on them known. Where consultation has been carried out by the appellant, particular care will need to be taken to ensure that statutory bodies and local people have been made properly aware of what is proposed and have had adequate chance to comment; timescale will clearly be relevant.”
“Regard is to be had to the development plan for the purposes of any determination to be made under the Planning Act the determination must be made in accordance with plan unless material considerations indicate otherwise.”
“in considering whether to grant planning permission for development which affects a listed building or its setting, the local planning authority or, as the case the may be, the Secretary of State, shall have special regard to the desirability of preserving the building or its setting or any features of special architectural or historic interest which it possesses.”
“…Paragraph 134 of the NPPF appears as part of a fasciculus of paragraphs, set out above, which lay down an approach which corresponds with the duty in s.66(1). Generally, a decision-maker who works through those paragraphs in accordance with their terms will have complied with the s.66(1) duty. When an expert planning inspector refers to a paragraph within that grouping of provisions (as the Inspector referred to para.134 of the NPPF in the Decision Letter in this case) then-absent some positive contrary indication in other parts of the text of his reasons-the appropriate inference is that he has taken properly into account all those provisions, not that he has forgotten about all the other paragraphs apart from the specific one he has mentioned. Working through these paragraphs, a decision-maker who had properly directed himself by reference to them would indeed have arrived at the conclusion that the case fell within para.134, as the Inspector did.”
“62 From reviewing the authorities I derive the following principles: i) Any party to a planning inquiry is entitled (a) to know the case which he has to meet and (b) to have a reasonable opportunity to adduce evidence and make submissions in relation to that opposing case. ii) If there is procedural unfairness which materially prejudices a party to a planning inquiry that may be a good ground for quashing the Inspector's decision.”
“85 Provided that certain factors are borne in mind, it does not generally matter whether what is at issue is characterised as “natural justice” or “procedural fairness”
“it is clear from decisions in the last 60 years that what is required is an opportunity to be heard, an opportunity to participate in the procedure by which the decision is made.”
“36. The reasons for a decision must be intelligible and they must be adequate. They must enable the reader to understand why the matter was decided as it was and what conclusions were reached on the “principal important controversial issues”, disclosing how any issue of law or fact was resolved. Reasons can be briefly stated, the degree of particularity required depending entirely on the nature of the issues falling for decision. The reasoning must not give rise to a substantial doubt as to whether the decision-maker erred in law, for example by misunderstanding some relevant policy or some other important matter or by failing to reach a rational decision on relevant grounds. But such adverse inference will not readily be drawn. The reasons need refer only to the main issues in the dispute, not to every material consideration. They should enable disappointed developers to assess their prospects of obtaining some alternative development permission, or, as the case may be, their unsuccessful opponents to understand how the policy or approach underlying the grant of permission may impact upon future such applications. Decision letters must be read in a straightforward manner, recognising that they are addressed to parties well aware of the issues involved and the arguments advanced. A reasons challenge will only succeed if the party aggrieved can satisfy the court that he has genuinely been substantially prejudiced by the failure to provide an adequately reasoned decision.”