“The [Examining Authority] must ensure that the rights of interested parties and anyone else that could be affected by a proposed change are protected. The principles of fairness and reasonableness, as established by relevant case law, will guide the [Examining Authority] in their consideration of a material change request.”
“(1) An order granting development consent may include provision authorising the compulsory acquisition of land only if the Secretary of State is satisfied that one of the conditions in subsections (2) to (4) is met. (2) The condition is that the application for the order included a request for compulsory acquisition of the land to be authorised. (3) The condition is that all persons with an interest on the land consent to the inclusion of the provision. (4) The condition is that the prescribed procedure has been followed in relation to the land.”
“… (a) it is proposed to include in [a DCO] a provision authorising the compulsory acquisition of additional land; and (b) a person with an interest in the additional land does not consent to the inclusion of the provision” (regulation 4) “Additional land” is defined as “… land which it is proposed shall be subject to compulsory acquisition and which is not identified in the book of reference submitted with the application as land”
“The [Examining Authority] may make orders as to costs of the parties at the inquiry and as to parties by whom the costs are to be paid, and every such order may be made a rule of the High Court on the application of any party named in the order.”
“The Examining Authority will notify interested parties when it has completed the examination. An application for costs must be received by the Inspectorate… within 28 days of the date of the notification. Late applications for an award of costs will only be accepted if the party making the application for an award of costs shows good reason for not having complied with the time limit for submission.”
“2. Where the objections to a compulsory acquisition request have neither been disregarded by the Examining Authority nor withdrawn before the decision of the Secretary of State on a development consent application and the objectors have been successful in objecting to the compulsory acquisition request, an award of costs will normally be made against the applicant for the development consent and in favour of the objectors. An award of costs in such a case does not, of itself, imply unreasonable behaviour by the applicant for development consent.”
“There was no longer an issue about the attenuation basin, which can be relocated to the [Claimant’s] satisfaction. Updated work plans, land plans and an updated [book of reference] reflect the associated changes, including reduction in the extent of associated [compulsory acquisition].”
“In relation to the relocation of the attenuation basin and the reduction in its capacity, all works would be undertaken within the existing Order limits and I am satisfied that its impact has been adequately assessed. Additional planting should contain its visual impact. I am therefore satisfied that the new arrangement is lawful and has no unassessed environmental impacts.”
“13. … On18 June 2014 … Mr Tim Walmsley of [the Council] sent an email to [the Claimant’s solicitors] in which he stated that, following agreement of the layout of the attenuation pond, there had been revisions to the Land Plans and Book of Reference, copies of which he sent, and in which he asked for approval of such revisions at the earliest opportunity in preparation for the Compulsory Acquisition Hearing which at the time the parties thought would be held on26 June 2014 . This confirmation was ultimately given at the Hearing on22 July 2014 . 14. Costs of the negotiations with [the Council] in relation to the attenuation pond up to the hearing on22 July 2014 are requested to be awarded to the [Claimant].”
“The ExA has considered the application and has concluded that the award sought for negotiations with [the] Council concerning the attenuation pond up to the hearing on 22 July appears to be valid insofar as the compulsory acquisition powers sought were modified by the Council (i.e. the [Claimant] was ‘successful’) and the application is timely, having regard to paragraphs 3, 4 and 6 of Part D of the published Guidance. The ExA has therefore agreed to consider the application to this extent.”
“Our clients were objectors to the compulsory acquisition of their property and consequently would have claimed their costs in their entirely under Part D if the order was not made or their entire landholding was excluded from the order, whether because of their representations or otherwise. It would have been unnecessary additional expenditure of time and money on all sides to have made a costs application on the basis of unreasonable behaviour in respect of costs which might have been recovered in a more straightforward and economical manner. In terms of the land now excluded from the order that has proved to be the case. If a costs application had been made last year in respect of unreasonable behaviour on that issue then the expense incurred on all sides would have been unnecessary. Whether the present order was to be made at all was unknown at the close of the examination, not least if our clients’ access concerns were made out but could not be addressed in the current application. It was also, at the close of the examination, uncertain as to what matters would be the subject of an unreasonableness application in the event of the objection not being successful in those respects. There was an outstanding Freedom of Information request to [the] Council…. It would therefore have involved unnecessary additional time and expense to make three potentially overlapping costs applications (following the close of the examination; following receipt of the FOI response and during Ministerial consideration of the application; and following the Ministerial decision). For these reasons a single costs application was made when the scope of the costs following the event and unreasonableness claims was known. Whilst part B, paragraph 31 of the [Costs Guidance] says that application for an award of costs must be received within 28 days of notification of the completion of the examination neither that time period nor the guidance as a whole has any statutory basis. It is not within any of the statutory rules nor within statutory guidance (although thePlanning Act 2008 does provide for statutory guidance on certain other matters). It is not therefore a justification for not considering the merits of a costs application, particularly where a costs application has to be addressed by the promoter and the [ExA] at this stage in any event.”
“At no point was the application for development consent withdrawn, at no point was the [Claimant] formally notified that the compulsory acquisition request in respect of the [Claimant’s] land was withdrawn. In addition, we also repeat the points made on timing of the application in our letter of1 June 2015 and therefore do not set out those points again within this letter of response. It cannot be the requirement of the Guidance that each and every time there is an amendment to the Book of Reference a claim for costs must be made, such a position would place the [Claimant], Council and ExA under an unbearable administrative burden.”
“8. The extent of land to be acquired for construction of the proposed attenuation pond was reduced during the examination and your case is that your clients should be treated as ‘successful objectors’ entitled to reimbursement of the costs of opposing compulsory acquisition of their land, to the extent that it was unnecessarily extensive for construction of an overly large pond. 9. The Council modified the application for powers of compulsory acquisition as soon as it reached agreement with the Environment Agency about the determinants of the size of the pond. The Book of Reference was amended and the reduced extent was agreed at a compulsory acquisition hearing on22 July 2014 . It had always been apparent in the Council’s dealings with your clients, before the powers were sought and subsequently, that the final extent of the pond remained to be determined; and the Council gave repeated assurances that it would only seek to acquire such land as was necessary to satisfy Environment Agency requirements. 10. The fact that your clients objected to compulsory acquisition, the extent of which remained to be determined, is to be expected. Landowners would wish to protect their position, notwithstanding assurances from the acquiring authority. The Council could have refrained from seeking powers of compulsory acquisition until the need was clear. Instead it proceeded on an uncertain footing and modified the extent of land to be compulsorily acquired when clarity was achieved. Your clients could thus be treated as ‘successful objectors’ having regard to paragraph D5 of the… [Costs] Guidance. 11. That status was recognised in the Inspectorate’s letter of19 May 2015 , which concluded that the application was timely. However, my reading of paragraph D6 of the… [Costs] Guidance convinces me that the application for an award of costs on this ground was actually out of time. It should have been made within 28 days of the Council’s modification of the extent of compulsory acquisition at the hearing on22 July 2014 i.e. by19 August 2014 rather than on2 March 2015 following the Secretary of State’s decision on the DCO, more than six months later. 12. I acknowledge your decision to combine costs applications and ignore the published guidance in the interests of expense and efficiency. Had you informed the Inspectorate of that intention, or sought support for that approach it might have been possible to interpret the… [Costs] Guidance on timeliness more flexibly, but you did not. The implications of the Human Rights Act for the compulsory acquisition process, including the costs of opposing interference with the right to enjoyment of property, would suggest that it could be inappropriate to have an overly rigid approach to timeliness. Nevertheless, being too flexible would frustrate the administrative process and could expose acquiring authorities to applications for awards of costs long after the appropriate event, constraining the proper exercise of their function. 13. As professionally represented active participants in the examination, your clients were well aware of the modification, were present at the hearing and agreed to the pond changes. They should have been aware of the… [Costs] Guidance and if your clients were minded to ignore it for reasons relating to uncertainty, scope or time and expense, they might reasonably have been expected to forewarn the Council and the [ExA] of a pending costs application, as is customary in the wider planning regime. The infrastructure planning regime is largely shaped by administrative guidance and the fact that it does not have statutory force is no good reason for ignoring it. 14. I have also considered making a partial award of costs for reasons of flexibility but can find no good reason why the Council should be required to compensate your clients for the lateness of the application. You have offered no credible reason why your clients should not have applied in a more timely fashion and the application fails on this count.”
“… a claim for judicial review of a decision, act or omission all or part of which is subject to the provisions of the UNECE Convention on Access to Information, Public Participation in Decision-Making and Access to Justice in Environmental Matters done in Aarhus, Denmark on25 June 1998 [“the Aarhus Convention”], including a claim which proceeds on the basis that the decision, act or omission, or part of it, is so subject.”
“… [Each] Party shall ensure that, where they meet the criteria, if any, laid down by its national law, members of the public have access to administrative or judicial procedures to challenge acts and omissions by private persons and public authorities which contravene provisions of its national law relating to the environment.”