“…adopted a legally erroneous approach to the question of whether a condition precedent (a Grampian condition) could or ought to be imposed to secure the provision of off-site highway works”
“restricted by existing buildings and steep banks to either side. Fol Hollow, which extends beyond the 30mph limit of the town, has the character of a country lane. Waggs Lane has housing to each side and gives access to a primary school…..”
“It is the case that existing residents use this route, and have done so to date without giving rise to recorded personal injuries. The increased number of daily walking trips would however result in a corresponding increase in the likelihood of pedestrians passing each other on the narrow footways, and at times stepping into the carriageway. The result would be an increased risk to the safety of pedestrians in Waggs Road” 9. Road Traffic iv). The access road to the development would lie in an existing 30 mph zone. It was agreed that for the purpose of applying MfS guidance, the relevant speed of traffic was 30mph. The proposed visibility splay at the access road would allow a driver waiting to exit the road a line of sight of 43m west of the junction along Waggs Road (described in MfS as the Y value) and of 35m or 30m east of the junction towards Fol Hollow, depending what point is taken. MfS provides a minimum “stopping sight distance” (“SSD”) of 40m. v). It follows that the access road fails to meet the MfS minimum recommendation for the SSD or Y value as far as visibility to the east is concerned. All parties accepted that the minimum SSD or Y value was 43m. vi). The Inspector notes that falling below the minima of the MfS will not necessarily lead to a significant problem and refers to certain mitigation measures (widened footways on the south western approach to the school and to the restriction of traffic speeds on Waggs Road). She goes on to conclude, given the particular characteristics of the present site, in particular that the access road will emerge within sight of Fol Hollow, a road with an unrestricted speed limit, that there is “no basis for concluding that a visibility splay below recommended levels would be appropriate”. vii). The mitigating factors include “speed humps and 2 stretches of footway build-out”
“cannot be confident that a scheme of speed reduction provided by way of a Grampian Condition could or would, in this case take account also of potential effects on road users and local residents”
“…the Framework states that planning decisions should take account of whether safe and suitable access can be achieved and a safe and accessible environment created. Whilst town centre facilities, services and transport links would be nearby, access to these facilities by pedestrians would in the majority of cases be along the sub-standard footways of Waggs Road. The proposed road junction would fail to provide safe highway conditions. A package of works to the highway sufficient to appropriately limit these impacts cannot be assured and in their absence the detrimental effect of the development on the safety of highway users would I consider, be severe”
“very significant shortfall when it is remembered that the subject under consideration is the distance required by a moving vehicle to stop short of a collision”
“The owner of the land to which the application relates may object to the grant of planning permission for reasons which may or not be sound on planning grounds. If his reasons are sound on planning grounds no doubt the application will be refused. But if they are unsound, the mere fact that the owner objects and is unwilling that the development should go ahead cannot in itself necessarily lead to a refusal. The function of the planning authority is to decide whether or not the proposed development is desirable in the public interest. The answer to that question is not to be affected by the consideration that the owner of the land is determined not to allow the development so that permission for it, if granted, would not have reasonable prospects of being implemented. That does not mean that the planning authority, if it decides that the proposed development is in the public interest, is absolutely disentitled from taking into account the improbability of permission for it, if granted, being implemented. For example, if there were a competition between two alternative sites for a desirable development, difficulties of bringing about implementation on one site which were not present in relation to the other might very properly lead to the refusal of planning permission for the site affected by the difficulties and the grant of it for the other. But there is no absolute rule that the existence of difficulties, even if apparently insuperable, must necessarily lead to refusal of planning permission for a desirable development. A would be developer may be faced with difficulties of many different kinds, in the way of site assembly or securing the discharge of restrictive covenants. If he considers that it is in his interests to secure planning permission notwithstanding the existence of such difficulties, it is not for the planning authority to refuse it simply on their view of how serious the difficulties are.”
“there is nothing before me to demonstrate that a solution to ensure that the effects on the Radar would be adequately mitigated would become available within the time limit for implementation”
“this Inspector simply applied the policy as a mandatory requirement without scope for discretion on his power. Given its term, that is not altogether surprising”
“leaves it open to the Secretary of State to refuse to impose such a condition if there are reasons other than the unlikelihood of implementation. But the unlikelihood of implementation is not by itself a sufficient reasons to refuse……”