“Without planning permission operations consisting of the construction of ten 3-storey town houses, foundations, undercroft parking and basements.”
“As the Council is aware, in order to deal with the matters of contamination, the diversion of the river culvert and the pile shield, the whole site had to be excavated prior to the works in connection with the erection of the approved dwelling houses commencing. The demolition of the original office building and the excavation of the land constituted a commencement of the approved development and this matter is discussed in more detail below.”
“7.8 Section 56(4)(aa) makes clear that the development of the appeal site began with the demolition of the original building which occupied the site. At that point in time, the extant planning permission for the erection of 9 houses was lawfully implemented. It therefore lasts in perpetuity. 7.9 It was only subsequently that the appellant took the view that the additional excavation would allow for the provision of an increased area of basement and that an additional, tenth, dwellinghouse could be built above the entrance to the subterranean car park. Notably the latter view was taken following positive pre-application advice provided by the Council.”
“The [Second Respondent] contends that the breach of planning control has not occurred as a matter of fact as the works and the construction of the tenth unit occurred after the implementation of the planning permission for the construction of nine houses at the site. This argument is fundamentally incorrect as the planning permission was never implemented due to the differing design of the basement and the construction of all ten units as part of the same works. The [Second Respondent was] advised of this scenario during the pre-application advice and during the enforcement investigation where it was made clear that any works to the tenth unit prior to the substantial completion of the approved development would potentially render the tenth unit as an amendment to the approved scheme and therefore would not allow for this to be applied for as a separate unit. Notwithstanding the above it is considered that the [2008 planning permission] was not implemented as the basement is substantially different to that approved and as this is an integral part of the development. Accordingly the whole scheme does not benefit from planning permission and is unauthorised. This view is supported by the [Second Respondent’s] own response to the PCN.”
“It is noted that the developer has suggested that the steps to remedy the breach could be achieved through the demolition of the tenth unit and the infilling of the additional area of the basement. It is up to the inspector to consider whether such an approach is appropriate. However the LPA consider that the planning permission as approved … was never implemented as the development on site clearly does not accord with the approved plans due to the fundamentally different basement design and the construction of 10 houses as opposed to 9. This planning permission has now expired. Without the works on site benefiting from and being in accordance with an extant planning permission the development cannot be adequately controlled through conditions. The LPA maintains that the only way to ensure the development is carried out in accordance with the approved plans and with appropriate conditions is for it to be implemented in accordance with an approved planning permission.”
“I agree with [Counsel for the Secretary of State] that the power under section 177(1) to grant planning permission in respect of the matters stated in the enforcement notice as constituting a breach of planning control is linked to an appeal under ground (a) rather than under ground (f). But Mr Ahmed’s appeal included express reliance on ground (a) and he would have been deemed in any event to have made an application for planning permission by virtue of section 177(5) as it existed as the material time. Although his ground (a) appeal sought planning permission only in respect of the development as built, which constituted the whole of the matters stated in the notice as constituting a breach of planning control, the power under section 177(1) was to grant planning permission “in relation to the whole or any part of those matters”
“13. So it was within the power of the inspector in that case – where an appeal had been made under ground (a) and the planning application fee had been paid - to vary the notice and grant permission for something less than what was being sought by the appellant, provided that what was permitted could be regarded as “part” of the development as built. This is, of course, entirely consistent with the position in respect of an appeal pursuant to section 78 of the Act, where an inspector may grant a more limited permission, provided it forms “part” of what was applied for. 14. But the crucial point is that an inspector can only grant consent pursuant to section 177 of the Act if the appellant has applied for permission pursuant to section 174(1)(a) and paid the requisite planning application fee ….” … 16. Given that the appellant has not specified ground 174(2)(a) in its appeal, the alternative of granting planning permission (either for the 10 house scheme or the revised 9 house scheme) is not open to the inspector in this case (and the appellant clearly wants to avoid a further grant of permission in any event). 17. The alternative of granting permission for the built scheme or a reduced scheme (which formed “part” of the built scheme) had been open to the inspector in the Ahmed case. And as the Court of Appeal noted in Ahmed, it was clearly crucial to their decision that there was an appeal under ground (a) (see paragraph 31 of the judgment). The absence of an appeal under ground (a) is similarly crucial in this case.”
“24. The [Second Respondent] contends that “even if was to be found that the 2008 planning permission at the appeal site had expired, that would not preclude the inspector from varying the notice to require that the development conforms to its provisions”
“Ground (b) 4. …. Nine conditions were imposed. Condition 1) is the normal three-year time limit for the commencement of development. Condition 9) states “Development shall not begin until a scheme to deal with contamination of the site has been submitted to and approved in writing by the local planning authority” and “Development shall not begin until measures approved in the scheme have been implemented”. 5. The basis of the [Second Respondent’s] ground (b) appeal is that the breach of planning control alleged in the notice has not occurred as a matter of fact, due to the work involved in the construction of the tenth unit commencing after the implementation of the permission for the construction of the nine units. They agree there has been a breach, but do not accept that it is the one described in the notice, their contention being that the breach is “simply the erection of one additional dwellinghouse and the formation of an enlarged area of basement accommodation”. 6. I consider that the following conclusions should be drawn from the facts and from the case law to which my attention has been drawn and the further cases about which I consulted the parties: - (a) Work on site began in 2010 and by27 May 2011 the demolition of the existing offices had been completed and piling mats had been laid. (b) The pre-commencement conditions have all been complied with, since the pre-commencement elements of Condition 9 have been met to the extent required by the Council. (b) Much of the work carried out is as depicted on the approved plans, but the basement area is a lot larger than shown, and now incorporates basement accommodation, and the Claygate Lane terrace has been built with an additional unit over the entrance to the basement parking area. These are substantial changes, which have all been made during the course of a continuous process of work, and they raise issues relevant to planning, including assessments of flood risk and land contamination and standards of residential amenity. (c) In deciding whether the work carried out is authorised, I am to look at what has been done as a whole and reach a judgement as a matter of fact and degree on that whole. Looked at in this way, in my planning judgement the work that has been carried out is so different from what was approved that it does not constitute the implementation of the 2008 permission. (d) It follows that the matters alleged in the notice to be a breach of planning control have occurred. The appeal on ground (b) has therefore failed. Ground (f) 7. The [Second Respondent] maintain that the requirement to demolish all ten units and the underground car parking and basements is excessive. They consider that a requirement to demolish the tenth unit and infill the extended parts of the basement, so that the development would conform with the permission, is all that is necessary. The Council have doubts about the efficacy of this approach. As they have pointed out, requirements directed only at the differences could lead to an unconditional planning permission being granted under s 173(11) once the requirement has been complied with. 8. The requirements of the notice would result in the loss of nine residential units, which appear to have been built substantially in accordance with the plans approved in 2008, apart from the basement accommodation. Their demolition is an outcome that should be avoided unless there are no other means of remedying the breach of planning control. 9. The enforcement procedure is intended to be remedial. When work is carried out that differs substantially from approved plans, with the result that the development as a whole is unauthorised, provision is made by section 173(4)(a) for the breach of planning control to be remedied by making the development comply with the terms (including conditions and limitations) of the permission. Condition 1) does not in my opinion prevent the adoption of this approach in this instance and there should be no difficulty in compliance, since the differences between the work carried out and what was authorised are clear-cut and the work needed to make the development comply with the permission has already been identified. 10. I have therefore varied the first requirement of the notice so that it requires the development to comply with the permission. The appeal has succeeded on ground (f) to this extent. Ground (g) 11. The request for a longer compliance period now needs to be dealt with in the light of this variation. I have extended the period from nine months to twelve months, firstly, because the work required is now more complex and, secondly, because the [Second Respondent’s] representations indicate that a further planning application, or applications, may be submitted and sufficient time should be allowed for this to be done and the decision-making process to take place. The appeal has therefore succeeded on ground (g) to this extent.”
“Make the operations comply with the terms (including the conditions and limitations) of the planning permission granted on27 May 2008 ….”